2022年2022年焊接控制 .pdf
CSPC NANHAI PETROCHEMICALS PROJECT CSPC 南海石化项目WELDING CONTROL 焊接控制PROJECT PROCEDURE: PR-8710-8100-0038 项目程序 : PR-8710-8100-0038 SEPCO Electric Power Construction Corporation 山东电力基本建设总公司REV版次DATE 日期REASON FOR ISSUE 修订原因BY 编制Chk d 审核QA 审查APPR 批准A 21 Aug 2003 Issued for Review ZRC LMX XLR GGS B13Sept. 2003 Issued for Review ZRC LH GSX LJG 007 Oct 2003 Issued for Approve ZRC LH GSX YJQ 01 20 Oct 2003 Issued for Use ZRC GWJ LWD LJG 02 28Nov.2003 Issued for Use GWJ LWD GSX YJQ 名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 1 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 2 of 30 Welding control修改记录Revision Information 版次Rev 章节号Section No. 主要修改内容Description of main changes 02 3. Modify “ QC1 ,QC2,QC3” to “ QC1-W,QC2-W,QC3-W”Attachment pages Modify “ QC1 ,QC2,QC3” to “ QC1-W,QC2-W,QC3-W”Attachment Adding “ thickness report ” ,” g rad eas s e ss e dsh e e t fo rsu b e n try p ro j ec t” ,m od ify ” Weld Record Acceptance Sheet”名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 2 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 3 of 30 Welding controlWELDING CONTROL焊接控制目录 TABLE OF CONTENTS No Page 1. 目的Purpose 4 2. 范围Scope 4 3. 定义Definition 4 4. 参考文件Reference 4 5. 职责Responsibilities 4 6. 程序Instruction 5 7. 记录 Records 15 8. 附件Attachments 16 名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 3 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 4 of 30 Welding control1目的 Purpose 本程序规范了中海壳牌南海石化工程汽电联产项目中SEPCO对 SEP1/2进行焊接控制、焊接热处理和探伤的监督,以确保其符合工程设计及规范的要求。This procedure provides the SEPCO requirements for monitoring SEP1/2 in their control of welding, post weld heat treatment, and NDE, to ensure them compliance with applicable project, design and Code requirements, on the Steam & Power Project of CSPC Nanhai Petrochemicals Project. 2范围 Scope 本程序适用于SEP1/2 在中海壳牌南海石化工程汽电联产项目永久厂房的制造和安装的过程中进行的焊接,焊接热处理及探伤活动。This procedure applies to SEP1/2 welding, post weld heat treatment, and NDE activities during fabrication and installation of permanent plant items on the Steam & Power Project of CSPC Nanhai Petrochemicals Project. 3定义 Definitions SEP1/2 山东电力建设一、二公司SEPCO No.1/2 Construction Company CMD 施工管理部Construction Manager Department QC1-W 焊接施工班组Welding Erection Group QC2-W 施工队或工程处焊接质检或焊接工程师Welding Inspector or Welding Engineer of Construction (or Erection) Team QC3-W 一、二公司施工部焊接质检或焊接工程师CMD Welding Inspector or Welding Engineer of SEP1, SEP2 4参考文件References PR-8710-8100-0025 焊接程序Welding Program PR-8710-8100-0026 焊工培训与考核程序Welder Training and Qualification Procedure WI-8710-8100-0003C 焊接材料控制Weld Material Control PR-8710-8100-0055 测量和校验设备Measuring and Test Equipment 5 职责 Responsibilities 5.1 SEP1/2 焊接工程师负责各自施工范围内焊接程序、程序资格认定测试、WPS 以及PQR 资格认定记录的现场准备、发布并维持;SEP1/2 welding engineer shall prepare, issue, and maintain welding procedures, procedure qualification testing, WPS, and PQR qualification records at site in his responsible construction area respectively. 5.2 SEP1/2 NDE工程师负责各自施工范围内无损检测程序准备、发布和维持;SEP1/2 NDE engineer shall prepare, issue, and maintain NDE procedures in his responsible construction area respectively. 名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 4 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 5 of 30 Welding control5.3 CMD 焊接工程师负责焊接全过程的监督管理,包括有关作业文件的审批。负责与 BSF 及有关方的协调和沟通;CMD welding engineer is responsible for the supervision of overall welding operations, including review and approval of job documents, coordination and contact with BSF in relevant aspects. 5.4 焊接施工班组 (QC1-W) 负责自己所焊焊缝的外观检查。Welding Erection group (QC1-W) will check the weld after complete welding operation. 5.5 施工队或工程处焊接质检或焊接工程师(QC2-W) ,一、二公司施工部焊接质检或焊接工程师(QC3-W) 负责按比例对焊缝进行外观检查和验收。Welding inspector or welding engineer from construction (or Erection) team (QC2-W), CMD welding inspector or welding engineer from SEP1 or SEP2 (QC3-W) will check and accept the weld in proportion. 6程序 Procedure 6.1 焊接技术管理Management of Welding Technique 6.1.1 SEP1/2 工地级焊接工程师根据工程需要和要求确定各自的焊接工艺评定任务,具体组织实施,并将焊接工艺评定报告报CMD 、BSF 焊接工程师批准;Welding engineers at jobsite from SEP1/2, in response to construction requirement, shall know their respective welding quality requirements, do good arrangement of actual operations and then submit welding PQRs to CMD、BSF welding engineer for approval. 6.1.2 根据批准的焊接工艺评定报告,由 SEP1/2 工地级焊接工程师编制用于南海石化汽电联产项目焊接施工的焊接工艺规程(WPS ) ,报 CMD 及 BSF 焊接工程师审批;With approved welding procedure qualification record, welding engineers from SEP1 /2 shall prepare Welding Process Specification for CSPC Nanhai Petrochemicals Complex Steam & Power Project, and also submit it to CMD and BSF welding engineers for review and approval. 6.1.3 SEP1/2 各专业工程处(施工处)负责焊接的工程师,根据施工图纸及有关规范、标准和程序编制主要焊接工程一览表,绘制主要焊接工程施工技术记录图。主要焊接工程一览表应包括各种管道的等级和采用的焊接工艺规程(WPS ) 。还应包括焊后热处理、无损检测、硬度或金相试验,以及材料光谱分析( PMI )的频率。主要焊接工程一览表报BSF 焊接工程师批准后出版、发放,发放范围包括 CMD 、焊接和热处理工程师、焊接质检员和无损检测人员。All welding engineers from SEP1/2 Construction (or Erection) teams shall, in accordance with construction drawings and relevant specification, standard and procedure, prepare the Weld Task Schedule and Major Weld Operation Technique Diagram. Weld Task Schedule shall cover all piping grades, applied weld process, also post-weld heat treatment, non-destructive test, hardness/metallographic test, material spectral analysis. Major Weld Operation Technique 名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 5 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 6 of 30 Welding controlDiagram, after submitted to BSF weld engineer for approval, shall be issued to all CMD personnel who are responsible for weld, heat treatment, quality inspector and non-destructive test engineers. 6.1.4 SEP1/ 2 工地级焊接工程师制定主要焊接工程作业指导书编制计划,报CMD 批准,并由PMC 审核后实施; Welding engineers from SEP1/2 shall prepare the Documentation Requirement of Major Weld Operation Guide, then submit it to CMD and PMC review for approval prior to its implementation. 6.1.5 专业工程处(施工处)的焊接工程师根据焊接作业指导书编制计划,编写本单位焊接作业指导书,并送 CMD 和 PMC 审批;Welding engineers from Construction (or Erection) teams shall, in response to Documentation Requirement of Major Weld Operation Guide, prepare their own Weld Operation Guide and then submit it to CMD and PMC for approval. 6.1.6 SEP1/2 需编写通用焊接标准(GWS ) ,并上报SEPCO 项目部,由CMD 和 PMC 审批:SEP1/2 should write General Welding Standard(GWS), and submit to SEPCO CMD and PMC for approval. 6.1.7 各工程处 (施工处) 焊接工程师根据图纸、变更文件编制指导施工的焊缝记录单。焊缝记录单见附录 14;焊接工程师应将以下内容有关信息填写或打印到记录单中:Welding engineers from all Construction (or Erection) teams shall, in accordance with drawing and change order, prepare their Weld Record Sheet. Weld Record Sheet in Attachment 14. Welding engineers shall write down the following information onto record sheet. 选用的焊接程序(从经CMD 批准的焊接程序中选取)selected weld procedure (select among weld procedures approved by CMD) 系统号 /管线号(或部件号)system ident.no./pipeline ident.no. 焊接材料型号weld material model 焊缝号(现场设计的小口径管道可一条管线或一张图纸共用一张记录单,在附页中记录焊缝号)weld ident. No (for small bore design at jobsite, one sheet of record may be used for either one section pipe or one sheet of drawing, with weld indet.No in attached page) 焊接标准weld standard 母材材质、规格material specification and size ITP 编号ITP numbering 焊缝细节weld details 名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 6 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 7 of 30 Welding control预热和热处理要求/NDE 方法、比例等。Requirement on preheating and heat treatment/NDE method, proportion, etc. 6.1.8 以上焊接信息由焊接工程师编制汇总成表后,交专职工程师或技术组长审查。The above weld information, after documented by welding engineer into forms, will be submitted to discipline engineer or technique team leader for review and approval. 6.1.9 专业工程处 (施工处)焊接工程师,应深入现场检查焊接作业指导书的执行情况,及时解决施工中的技术问题,并做好焊接施工技术记录;Welding engineers from Construction (or Erection) teams shall remain at jobsite to inspect the implementation of Weld Operation Guide, so as to timely solve any technique problem and keep good record of weld performance. 6.1.10 工地级焊接工程师,在指导各工程处(施工处)焊接技术管理的同时,应深入现场,做好现场的技术监督;Welding engineers at jobsite, mean while giving weld technique guide to weld operators from Construction (or Erection) teams, shall stay at jobsite for the purpose of strengthening technical supervision at jobsite. 6.1.11 工程处(施工处) 焊接工程师做好焊接竣工资料的整理和工程总结,工地级焊接工程师做好竣工资料的审核和焊接工程总结工作。Welding engineers from Construction (or Erection) teams shall make preparation of as-built information and work summary in weld aspect , and while welding engineers shall be responsible for these information review and then developing summary about weld work. 6.2 焊工培训Welder Training 执行 PR-8710-8100-0026焊工培训与考核execute PR-8710-8100-0026 Welder Training and Examination 6.3 焊接材料管理Weld Material Management 执 行 WI-8710-8100-0003C焊接材料控制execute WI-8710-8100-0003C Weld Material Control 6.4 焊接设备管理Weld Equipment Management 6.4.1 各专业工程处(施工处)负责所使用焊接设备的日常维护、保养,并做好维护、保养记录;物资机械部负责对焊接设备的维修,并对焊接设备的维护、保养进行监督检查。All Construction (or Erection) teams shall do good management of weld equipment, such as daily maintenance, keeping record, while material/machinery divisions shall insist on supervision and inspection of weld equipment maintenance and repair. 名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 7 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 8 of 30 Welding control6.4.2 焊 接 及 热 处 理 设 备 的 测 量 表 计 , 应 按 期 进 行 校 验 , 确 保 工 艺 参 数 准 确 可 靠 , 具 体 执 行PR-8710-8100-0055 测量和试验设备Measuring gauge or meter for weld and heat treatment equipment must have current calibration certificate and be re-calibrated as required to insure accurate technical parameters by executing PR-8710-8100-0055 Measuring and Test Equipment. 6.5 工地焊接Weld Operation at Jobsite 6.5.1 重要系统或重大项目开工前,应由焊接工程师对焊工进行技术交底。焊接的准备工作(车间或现场)应根据 SEPCO 已获批准的GWS 去做。Welding engineers shall give technical explanation to welder prior to the commence of key or major work items. Welding preparation (In workshop or jobsite) shall be done in accordance with SEPCO approved General Welding Standard (GWS). 6.5.2安装班组负责现场管道焊缝号的标识,焊工根据焊缝记录单现场核对焊缝编号后进行工作。焊工在每条焊缝焊完后,认真清理, 检查合格后, 在焊缝附近用油性记号笔(不锈钢必须使用专用记号笔)标出焊缝号、焊工号及完成日期。Installation team shall be responsible for the identification of pipe weld location at jobsite, while welder, for doing specified weld operation in accordance with weld identification no. in reference to Weld Record Sheet. Welder must, after completing any weld operation, make clear, and then mark with oily pen (or with specially purpose pen if welding on stainless steel) the weld indent. No. welder numbering and completion date. 6.5.3 现场设计的管道,管道工程师应在管道立体竣工草图上,标注焊缝位置。For piping designed at jobsite, piping engineers shall mark weld location at three-dimensional piping as-built sketch. 6.5.4对 于 公 称 直 径 大 于80mm的 大 口 径 管 道 焊 缝 由 于 变 更 文 件 而 造 成 的 数 量 增 加 , 应 按 照PR-8710-8100-0047 “设计变更控制”要求进行。Possibly more big bore pipe 80mm or larger nominal diameter because of change requirement shall be dealt with in accordance with PR-8710-8100-0047 Design Change Control. 6.5.5 工地级焊接质检员应对工地的焊接活动,进行随机监督,并做好记录。监督记录见附录K。Welding Quality Inspector shall maintain random supervision of welding activities at jobsite, and keep sound record, as seen in Attachment K for supervision record. 6.5.6 如果焊缝有见证点(W 点)或停工待检点(H 点) ,工程处(施工处)焊接技术人员应及时通知工地级焊接质检员会同CMD 焊接质检员进行检查,H 点必须等有关人员检查完, 并在焊缝记录单上有关栏中签字,焊接班长才允许焊工施焊。名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 8 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 9 of 30 Welding controlIf Witness Point or Hold Point has been confirmed in weld operation, welding engineers shall time notify welding quality inspector to do inspection in coordination with CMD welding inspector. Weld team leader shall no right to assume weld operation at Hold Point until authorized inspectors have concluded the quality inspection and signed on appropriate column in Weld Record Sheet. 6.5.7在施焊之前,焊工应根据有关的程序,检查坡口组对,确认符合要求时,在焊缝记录单上相应的栏目内签字后方能进行施焊。Before weld operation, welder shall, in accordance with relevant procedure, inspect weld point status. No welding is permitted until confirming its being in compliance with requirement and then signing at appropriate column in Weld Record Sheet. 6.5.8 对于 159 的 I 类管道焊缝, 必须由焊接工程师或焊接质检员检查坡口组对合格后,并在坡口组对栏签字后方可施焊。其余焊缝,焊接技术人员或焊接质检员进行抽查。For Class 1 weld with 159 welding engineers or weld quality inspector must first inspect weld-point status, then sign on appropriate column in sheet prior to conducting weld operation. For other weld operation, welding engineers or quality inspectors shall take random inspection of welding result. 6.5.9 焊缝完成后,焊接工程师应及时通知工地级焊接质检员和CMD 焊接质检员进行验收。After having finished the weld operation, welding engineers shall make a prompt notification to welding quality inspector and CMD quality inspectors for acceptance. 6.5.10 管道焊接验收后,记录在相应的焊缝记录单上。The acceptance results of pipeline weld shall be recorded on corresponding Weld Record Sheet. 6.5.11 有编号的大口径支吊架和钢结构焊缝,验收后记录在支吊架/钢结构验收记录单上。 (支吊架 /钢结构验收记录单见附录12)For welding of numbered large bore pipe hanger and steel structure with it, the acceptance result shall be recorded on Acceptance Record Sheet of Hanger and Steel Structure (See Attachment 12). 6.5.12 小口径支吊架及没有编号的支吊架施工时,现场巡检,管线检查时验收并记录在相应的管线检查记录上。For small bore pipe hanger and same ones but without numbering, following up inspection and pipeline work acceptance shall require recording on appropriate record sheet. 名师资料总结 - - -精品资料欢迎下载 - - - - - - - - - - - - - - - - - - 名师精心整理 - - - - - - - 第 9 页,共 30 页 - - - - - - - - - Cspc Nanhai Petrochemicals Project SEPCO Electric Power Construction CorpPR-8710-8100-0038 Rev 02 Page 10 of 30 Welding control6.5.13 记录单上的焊缝完成后,焊接质检员或焊接工程师及相关检验人员应在记录单正面中的“焊缝外观检查”栏内签字,表示该批焊缝已完成外观验收。Welding quality inspector or welding engineer shall, after the weld operation has been finished as required on record sheet, sign in the column of Weld Appearance Inspection, indicating the appearance acceptance passes through. 6.5.14 焊接准备应符合WPS 中所说明的详细规定。如果进行了热切割,焊接准备就需要进行打磨或机械加工,以去除切割热影响区. The weld operation shall be prepared in compliance with detailed requirement given in WPS. If hot cutting has been done, weld preparation must include grinding or machining it for the purpose of eliminating the effect caused by hot cutting. 6.5.15 准备铁基钢所使用的手工工具(砂轮、钢丝刷等)不得用于奥氏体钢。不锈钢丝刷只能用于不锈钢或镍合金。 Some manual grinding tool (such as grinding wheel, steel wire brush, etc) used for machining carbon steel material shall not be used on austenic steel.