2022年滑坡治理-注浆加固施工组织设计方案 .docx
精选学习资料 - - - - - - - - - *K20+800 K20+935 左侧滑坡处治施工组织设计目 录1 工程简况······ ····· ····· ········ ········ ····· ········ ········ ············· ····· ········ ········ ············· ···1 1.1 地势地貌 ······· ····· ····· ········ ············· ············· ··· ····· ············· ········ ····· ··· ····· ····1 1.2 地层岩性 ······ ····· ····· ········ ············· ····· ········ ··· ····· ····· ········ ········ ····· ········ ····· 1 1.3 水文地质特点 ············· ············· ············· ········ ············· ········ ············· ········1 2 施工组织方案 ········ ·············· ········ ······· ········ ················ ········ ········ ········ ············1 2.1 施工方案 ······· ····· ····· ········ ············· ············· ··· ····· ············· ········ ····· ··· ····· ····1 2.2 施工程序 ······· ····· ····· ········ ············· ············· ··· ····· ············· ····· ········ ··· ····· ····12.3 施工监测要求及应急措施······ ········· ····· ········ ············· ········ ············· ·······63 施工场地布置 ········ ·············· ········ ············· ········ ············· ············· ········ ············6 3.1 临建 ····· ····· ········ ····· ············· ··· ··· ····· ········ ······· ········ ········ ········ ········ ········ ···6 3.2 拌和站 ·· ····· ········ ····· ············· ········ ············· ········ ············· ····· ········ ··· ····· ····· 6 3.3 施工临时用电 ·············· ········ ····· ············· ····················· ·········· ··· ····· ··· ·······6名师归纳总结 - - - - - - -第 1 页,共 16 页精选学习资料 - - - - - - - - - 3.4 施工临时用水 ·············· ········ ····· ············· ····················· ········ ············· ·······7 3.5 施工临时道路 ·············· ········ ····· ············· ····················· ········ ············· ·······7 4 施工总体部署 ········ ·············· ······· ········ ········ ······························· ········ ···········7 4.1 劳动力组织方案··········· ········ ····· ·································· ········ ············· ······7 4.2 主要材料供应方案·· ·············· ········ ····· ····················· ········ ····· ········ ··········94.3 主要施工机械设备使用方案············ ····· ······· ·············· ········ ············· ······95 工期方案及工期保证措施·············· ········ ············· ····················· ···················10 5.1 工程量 ·· ····· ········ ····· ············· ········ ············· ········ ·········· ········ ········ ··· ····· ···10 5.2 工期方案 ······· ····· ····· ········ ············· ············· ··· ····· ············· ········ ····· ··· ····· ··10 5.3 工期保证措施 ·············· ········ ····· ············· ····················· ········ ············· ·····11 6.工程质量 ······· ············· ········ ······························· ····· ··· ····· ··· ··············· ····· ····13 6.1 质量目标 ······· ····· ····· ········ ············· ············· ··· ····· ············· ········ ····· ··· ····· ··13 6.2 质量保证措施 ·············· ········ ····· ············· ················ ·· ········ ········ ········ ·····13 7 施工安全 ······· ············· ····· ········ ············· ········ ············· ····· ················ ············· ·15 7.1 安全目标 ······· ····· ····· ········ ············· ············· ··· ····· ············· ········ ····· ··· ····· ··15 7.2 安全保证措施 ·············· ········ ····· ············· ····················· ········ ············· ·····16 7.3 安全生产纪律 ······ ····· ············· ········ ············· ········ ············· ····· ········ ··· ····18 7.4 安全生产技术措施·· ·············· ········ ····· ····················· ·········· ········ ········ ···198 施工环境爱护、水土保持和文物爱护等措施和方案········ ····· ········ ········ ····209 文明施工保证措施及创建文明工地地规划···· ········ ····· ········ ············· ····· ··· ·219.1 对工作人员地要求·· ·············· ········ ····· ····················· ········ ····· ········ ········ 219.2 施工现场治理 ·············· ········ ····· ············· ····················· ········ ············· ·····2110 劳动卫生保证措施······ ····· ····················· ······················ ····················· ··········22*K20+800 K20+935 左侧滑坡处治施工组织设计1、工程简况待处治地滑坡位于 *K20+800K20+ 935 段左侧,南北向长约 65m 左右,东西向顺路线长度达 135m,平面上呈弧形,前后缘高差达 22m.1.1 地势地貌场地原始地势为丘陵,高速大路由东至西方向穿过该区 .边坡上部为阶梯状农田 .滑坡后壁位于农田之中,滑坡后缘自然边坡较平缓,滑坡两侧为走向垂直于路线方向地冲沟 .1.2 地层岩性第四系全新统(Qh)1填筑土:其成份为粉砂岩块石,主要分布于施工便道,厚度约 2 种植土:松软,分布于农田和山坡上,厚 0.300.40m.1.00m2.00m.名师归纳总结 3 亚粘土:褐黄色、褐红色,硬塑状,厚约厚1.60 2.00m,主要分布于边坡后面地农田.第 2 页,共 16 页- - - - - - -精选学习资料 - - - - - - - - - 白垩系下统( K1)1 粉砂岩:紫红色,以钙泥质胶结为主,局部夹泥质胶结,中厚层状,岩石遇水软化 .全风化层,褐红色,呈可塑硬土状,厚 1.606.70m;局部底部存在 2.20m 厚地泥化夹层;强风化层,岩石较破裂,岩芯呈碎石、碎块状,岩性较软 .1.3 水文地质特点 场地地下水主要接受大气降水补给.边坡上部汇水面积大,在雨季,边坡上部所汇聚雨水经坡面所形成地面流易在裂缝处下渗而转化为地下水 , 流向斜坡坡脚处,并于滑坡坡体内中部及坡脚处以下降泉地势式排泄 .2、施工组织方案2.1 施工方案.” .同时提倡节省理念和贯该滑坡治理工程施工地总体目标是“ 安全、经济、环保、舒服、美观彻交通部关于在大路建设中实行最严格地耕地爱护制度地如干看法从以上施工总体目标动身,结合该工程场地地势和工程地质条件,该滑坡治理工程设计采纳注浆处理方案 .2.2 施工程序依据设计方案,该滑坡治理工程涉及地主要子工程工程有:放坡施工;注浆加固;防排水措施施工 .2.2.1 放坡施工由于采纳注浆加固处理,只需对原坡面进行修整,自路基左侧起按原放坡设计坡比进行放坡,比例及高度参数如下:第一级:自坡脚由下至上按1:1.5 放坡,坡面植草防护,上部按坡顶地势掌握高度,最高处为 13m;其余坡面保持原有地势地貌 .2.2.2 注浆加固本滑坡处治设计采纳注浆加固,注浆区域为裂缝所围成地区域,即在整个滑体上钻孔,注浆,插钢筋 .钻孔深度设计要求穿过滑动面,进入滑床岩体 23m,注浆采纳孔口封闭纯压式注浆 .实行梅花形布孔,钻孔间距 5m,每排间距 5m.放坡坡面采纳植草防护 .注浆加固主要包括注浆试验、注浆施工、注浆质量成效检验三个步骤 .2.2.2.1 注浆试验为了明白地层注浆特性,检验本次滑坡注浆处治所设参数地正确性以及能否达到估计地注浆成效,应先期进行注浆试验,并以试验成果修正注浆设计方案1 注浆试验地段地挑选 注浆试验地段地挑选在具有代表性,且地质条件中等偏劣地地段 件选在 K20+880 左侧 55m 处 10mx8.6m 地区域 .注浆试验支配如下:.本次注浆试验地段按设计文2注浆试验孔地布置11 个,其中注浆孔7 个,检查孔4 个.注浆孔依据3 个次序进本次注浆试验按设计要求布孔共行钻孔注浆,具体布置见下图:名师归纳总结 - - - - - - -第 3 页,共 16 页精选学习资料 - - - - - - - - - 注浆试验施工将严格依据分序加密原就进行,每序次孔施工时间间隔大于 12h.3 注浆试验钻孔注浆孔孔径 110mm.深度按设计要求穿过滑动面进入滑床弱风化岩层不小于 2m,采纳清水循环钻进,钻孔位置应不偏离设计孔位 0.1m,孔斜掌握在 2%以内 .4)试验孔注浆 本次注浆试验采纳孔口封闭式一次循环注浆,浆材选用 32.5 级一般硅酸盐水泥 . 水灰比初始为 1:1,并逐步减小至 0.6:1. 对于浆液性能地评判,如加入外掺剂需通过浆液室内试验确定 .按设计要求,注浆试验地浆液室内试验将包括以下几个方面:a、配比试验b、流淌性,凝聚时间c、结石地容重、强度、弹性模量 注浆压力.进行注浆试验时,可以采纳逐步提高注浆压力地方法,注浆量突然增大时,说明地层结构发生破坏或孔隙尺寸己被扩大,可把此时地注浆压力作为确定容许注浆压力地依据 .5) 注浆成效检验 注浆成效检验按设计要求在注浆试验孔注浆完成 动样进行室内土工试验 .2.2.2.2 注浆施工 1)总体施工次序 第一步:测量放线、布置注浆孔位;其次步:钻注浆孔;7d 后进行,试验方法为在检查孔钻孔取未扰第三步:注浆完毕后插入钢筋1 25,钢筋长度要求自设计坡面至滑动面以下岩层23m;第四步:依据设计开挖坡面;第五步:坡面防护施工 .2 注浆施工工艺孔位布置:注浆孔 :注浆孔孔径 91mm. 深度按设计要求穿过滑动面进入岩层 23m,孔间距为 5mx5m(平面),梅花形布置 .注浆孔地施工次序:注浆分两序施工,从地裂缝后缘起先施工第序孔,再施工第序孔 .注浆总体施工方向为沿滑坡边缘由上至下进行钻孔注浆 . 注浆材料采纳 32.5 级一般硅酸盐水泥,灌浆用水将选用符合拌制混凝土用水要求地水 .水灰比按设计要求,初灌时为 1:1,随后逐步降低水灰比至 0.6:1.水泥浆搅拌时问不少于 3min,浆液自制备至用完地时间不超过 4h. 注浆压力按初步设计注浆压力为 0.2Mpa-0.6MPa ,依据现场注浆情形进行调整 .注浆过程中,注浆压力或注入率突然转变较大时,应立刻查明缘由,实行相应地措施处理或上报设计和业主单位 . 注浆过程掌握与终止标准和封孔标准在孔口埋设 89 地无缝钢管,管口上端为套管母丝,埋入深度为进入孔口 2.5m.终止标准 :在设计压力下不吸浆或吸浆量 <0.4 L/min 时,连续 30 min,即可终止注浆 .采纳压力灌浆封孔,即在全孔灌浆完毕后,将全孔分成几段自下至上,采纳肯定地压力及浓浆封孔 . 施工操作要领拌.a、在配置浆液时,应先开动搅拌机,加水到肯定程度时方可向搅拌桶内依次加入水泥充分搅b、储浆池内地浆液应不断地搅动.c、单孔灌浆过程必需连续,中间停留时间不得过长,以免浆液凝固堵塞通道.d、当灌浆设备需修理时,在修理前,应将灌浆管道用清水清洗洁净.e、注浆过程中要对泵压及泵量变化进行记录. 特殊情形处理 冒浆处理名师归纳总结 - - - - - - -第 4 页,共 16 页精选学习资料 - - - - - - - - - a、表面堵盖处理:即大裂隙冒浆处,采纳旧棉花、麻线等物嵌入缝隙内,再用速凝材料进行封堵;当冒浆严峻时,可在冒浆部位浇筑混凝土盖板而后进行灌浆 .剂.b、采纳低压、浓浆、限流、限量、间歇灌浆地方法进行灌注 .必要时,可在浆液中掺入速凝 防止串浆地主要措施加大第一次序孔间地孔距 .b、适当地延长相邻两个次序先后施工地间隔时间,待前一次序孔灌浆地浆液基本凝固后,再 开头后一序孔地钻注工作 .c、发生串浆后,如串浆孔具备灌浆条件,可以同时进行灌浆,但应一台泵注一孔,否就应将 串浆孔用塞塞住,待灌浆孔灌浆终止后,串浆孔再行扫孔、冲洗,而后连续钻进和灌浆 . 大量漏失发生大量漏失时,采纳以下原就进行处理:a、采纳低压、浓浆、限流、限量、间歇灌浆地方法进行灌注 .b、必要时,可注入砂浆或其它惰性充填材料 . c、采纳水泥 -水玻璃处理 .2.2.2.3 注浆质量成效检验.注浆质量检验按设计要求在注浆终止3-7 天后进行,采纳钻孔取芯进行室内土工试验地方法检验孔数量不少于注浆孔总数地5%,检验终止后,按设计要求进行补充注浆.2.2.3 防排水措施施工该工程设计地排水系统为地面排水系统.地面排水系统设计有截水沟、排水沟和路基边沟.2.3 施工监测要求及应急措施 针对施工过程地安全隐患,我司将实行切实可行地防护措施.同时,为确保滑坡处治施工地安全,将协作相关单位自行施工监测包括对滑坡滑动监测和施工对滑坡影响地监测,随时把握滑坡整治施工过程中地边坡动态变化,滑坡裂缝地发生和进展以及对其它工程位置移和变形地影响 .将准时预报施工中显现地问题,并把获得地信息准时反馈到设计方,据此指导施工 .3、施工场地布置施工场地布置具体须按场地现场情形敏捷布置 .3.1 临建可依据现场实际情形,设置工地办公室、值班室及机械停放和材料堆场 .3.2 拌和站 在滑坡体外适当距离较平缓地场地处建一个拌和站,包括两个搅拌桶、一个装有搅拌机地储浆池( 2m× 2m、深 1.2m )、一蓄水池(3m× 3m、深 1.2m )、一水泥堆放场地(5m× 5m).具体施工布置依据现场条件进行调整 .3.3 施工临时用电本工程临时用电由建设单位指定地供电地点接出,到工地地配电间,装表计量 .1 不考虑生活用电地影响,施工机械设备用电高峰期用电容量约为 150KW.架空线电缆采纳 50-70mm2 地铝铰线 .2施工用电措施总配电屏中安排电路为动力照明混合系统 .总配电屏地分路支线各到达固定安装地安排电箱中,由各安排电箱分路到达各单机开关 .各级配电箱中地匣刀、漏电爱护开关必需标明送电目标或所掌握地范畴 .各级配用电源必需设置漏电爱护开关 .3支线架设变压器引线时开头视为埋地临时用电线路 .施工现场地全部线路均必需架空设置、采纳木质电杆,直径必需符合要求,并且埋设稳 .转角杆采纳双横担,双绝缘子地十字横担,并置双向线杆接线,杆上地接线高于地面 2.5M 处,装设紧绝缘子 ,拉线与电杆地夹角在 30°45°之间 .拉线截面不小于 3×.40 ,拉线锚固物埋设深度不少于 1m.名师归纳总结 小于固定安装地电设备线路必需用绝缘套设过路爱护.第 5 页,共 16 页架空导线与各种金属物如招牌、铁闸等地距离不得小于0.2M ,与各种不良导体地距离不得0.1M ,通过门窗上方时最小距离约0.15M ,通过门窗下方最小垂直距离约0.5M ,导线平行- - - - - - -精选学习资料 - - - - - - - - - 通过门窗地最小水平距离为 0.7M.3.4 施工临时用水.本工程用水从建设方指定地地点接出,铺设一路输水管道或者用水车运水到工地3.5 施工临时道路由于怀新高速大路此路段地路基建设已初步成型,交通便利.4、施工总体部署 4.1 劳动力组织方案 本工程采纳工程治理法施工,由工程经理全面组织施工,确保高速、优质、安全完成本工程 施工任务 .现场指挥部由技术素养好,工作才能强地治理人员组成施工技术、质量安全、材料设 备、财务劳资、防火保卫、生活福利、总包和谐等组织齐全地施工现场治理机构,对工程施工全过程实行统一方案,统一指挥、统一治理、统一和谐.指挥部定期召开内部和谐会,检查当天工作完成情形,解决存在问题,解决落实其次天地生产任务.现场组织机构设置见下图.工程经理工程技术负责人 工程安全负责人工程技术部综合办公室 含后勤 质量安全部钻岗位组织机构设置图备放孔坡注施浆工施劳动力支配方案表组工 序号人数注名师归纳总结 1工程经理1第 6 页,共 16 页2技术负责人13安全负责人14施工技术员25测量员16安全员17试验员1- - - - - - -精选学习资料 - - - - - - - - - 8材料员19钻机操作工810灌浆操作工811设备修理员112电工113其他人员3共计304.2 主要材料供应方案(1)开工前需联系好水泥供应厂家,确保有充分地货源,每天按时按量将水泥供应到工地 .(2)备料进场前取样做水泥和钢筋原材料等试验名师归纳总结 (3)依据施工组织设计地施工进度方案和施工预算中地工料分析,编制工程所需地材料用量第 7 页,共 16 页方案, 做好备料、供料和确定仓库、堆场面积及组织运输地依据.(4)依据材料需要用量方案,做好材料地订货和选购工作. 使方案得到落实.(5)组织材料按方案进场,并作好保管工作.(6)水泥仓库、堆料场至少储备1-2 天地材料用量 .4.3 主要施工机械设备使用方案主要施工机械装备表名称规格型号 X-100 型 钻机T600-功率单数备注工程90KW台2柴油动力空压台2搅拌7.5KW台21 台备用搅拌个2泥浆TBW-15015KW台31 台备用发电30KW台2电焊BX1-500500A台2水 泵 QY10-35-2.2台2全站 运输 车台1不含水泥 运输车台2砂轮切割机DE32台1- - - - - - -精选学习资料 - - - - - - - - - 潜孔钻QK-100台台35 工期方案及工期保证措施5.1 工程量主要工作量估算序号工程内容工程量1注浆孔施工(共246 个孔)2210m22210m插钢筋 25(共 246 根)3M7.5 浆砌片石护坡脚430m34截水沟 C20 砼预制块29.7m35截水沟砂砾垫层43.2m36截水沟现浇C15 砼4.5 m35.2 工期方案该滑坡治理工程总工期定为3540 天.详见施工进度方案表如下:施工进度方案表工期第第第第第第第156101115162026303135工程名称2125 天天天天天天天人员、设备进 场钻孔注浆施工放坡施工截水沟施工5.3 工期保证措施5.3.1 施工组织机构(1)参阅以工程为核心地责、权、利关系,定岗、定人、授权,各负其责 .(2)选取优秀地治理人员组成工程经理部,对工程实行方案治理,组织、和谐、掌握、监督 和指挥职能,同进派出技术过硬、吃苦耐劳地施工队伍,确保高标准、高速度地完成本工程地施工任务 .名师归纳总结 - - - - - - -第 8 页,共 16 页精选学习资料 - - - - - - - - - ( 3)在开工前各方面地人员要落实到位,凡被选调入工程组地治理人员、专业工长随时候命,工程一开工即进驻工程现场开展工作 .( 4)坚持每天一次地工作调度会,做到当天问题当天处理,并让每个生产者清晰明天地工作,并准时布置支配 .(5)定期召开每周一次各部门负责人参与地和谐会,准时和谐各部门之间地关系,合理调整机械设备、物资和人力,准时解决生产中显现地问题,并积极参与和谐好工程施工外部关系 .(6)建立严格工程施工日志制度,并每日具体记录工程进度、质量、设计修改等问题,以及施工过程中必需记录地有关问题 .( 7)建立奖罚严明地经济责任制,每月进行一次总结,对提前完成任务地施工人员进行奖励;未能按时完成任务地按拖延地天数进行罚款,谁拖延谁受罚 .5.3.2 机械设备投入为保证工期目标地实现,我司将对预备投放到本工程地机械设备进行全面地检修保养,以保证机械设备进场完好,正常运作 ,备足备用件 .5.3.3 材料供应开工前制定材料进场方案,特殊材料和设计指定地材料尽早落实,准时组织进场,并提前进行原材料检验工作和混凝土及砂浆地试配 .5.3.4 施工治理( 1)在施工过程中以总工期为目标,以阶段掌握为保证.将总体地工期目标分解为具体地月、旬、周方案,通过分阶段方案地落实来确保总工期地实施 .(2)坚持每月方案报表地编制、落实,以便甲方能依据报表地情形拨付工程款项,落实资金,满意施工需要 .(3)组织好劳动力队伍,合理编排班组,以便在施工高峰期组织连续地流水作业 .(4)建立健全各级责任制,实行重奖重罚(5)建立文明卫生治理小组,加强对食堂和住宅卫生监督检查和治理,削减病员,确保正常地 施工劳动力队伍(6)建立甲、乙双方联席例会制度,检查方案实施情形,讨论解决影响工程进度地关键问题,支配下一步工作5.3.5 技术措施(1)认真、认真熟识图纸,准确明白工程地各项内容、技术质量指标,在此基础上认真做好图 纸会审工作,通过会审把图纸中不够明确地部分以及错漏部分明确解决,以免贻误工期( 2)进一步编制具体地施工组织设计,准时编制主要地分项施工作业方案,并向各级治理人 员、工人传达交底(3)肯定要支配好不同工种之间地交叉作业次序 .(4)雨水是影响施工进度地一个重要因素.为此,我们特殊提出了雨季期施工措施,主要是做好名师归纳总结 防排水工作,以尽量削减雨水由滑裂缝渗入护坡体内.第 9 页,共 16 页- - - - - - -精选学习资料 - - - - - - - - - 6 工程质量6.1 质量目标本工程质量目标:工程一次验收合格率100%,工程优良率95%以上,确保优质.6.2 质量保证措施6.2.1 质量保证、掌握体系建立(1)建立高于国家验评标准地企业内部创优标准,以此标准实施考核、检查工程施工.严格按照公司质量保证地要求开展工作,使质量工作贯穿于各个部门、各个环节、各道工序(2)抓好质量预控和质量意识训练.组织施工人员学习施工规范、操作规程和质量验评标准,进行技术交底和质量通病防治训练,使施工人员明白工程简况,把握工程要领及质量要求,做到人人心中有标准,个个干中求质量 .(3)严把质量关 .创优良工程要选用优质地材料和设备,对工程中使用地各种材料、设备把住选购和验收两个关,材料员对进入现场地原材料、半成品、构配件、器具等对比样品全数检查验收,并检查有无符合国家地质量标准质保书和合格证,杜绝“ 无质保书、无合格证、无检测标准”地三无材料和产品进场 .(4)坚持三级检查验收制度 ,严把分项工程验收关 .分项工程地优良率是创优地重点,在每个分项或工序施工过程中 .认真执行操作班组自检、施工员全面检、质量员核验检三道关,达不到质量要求地必需返工重做 .加强质量跟踪和检查,对特殊工序和材料加强质量跟踪和检查 ,保证产品质量地可追溯性 .(5)施工中搞好工程技术档案资料地收集和整理工作.工程竣工前,先进行自检,并全部合格后,再进行整体工程地细致预检,全部达到验收标准后,再进行正式竣工验收 .(6)工程工地成立质量小组,对易发生质量通病地环节进行攻关,确保工程成为无质量通病地优良工程 .(7)制定经济措施对治理人员和施工班组人员进行进度和质量考核制度,实行奖优罚劣 .6.2.2 生产要素养量保证措施1 人员质量保证措施a、选派组织才能强,工作作风严谨地技术负责人,参与过我公司组织地多个滑坡注浆加固治理工程施工,具有施工治理名师归纳总结 - - - - - - -第 10 页,共 16 页精选学习资料 - - - - - - - - - 体会丰富地治理人员担任工程经理,从治理上供应人力资源方面地质量保证 .b、工地施工员、技术员、测量工程、质检员、安全员、预算员、试验、检验人员等都是具有多个类似工程体会地从业人员,理论与实践相结合,能很好地处理工程中遇到地各种技术难题 . c、全部重要岗位均持证上岗,并保证人员相对稳固 .2机械设备地质量保证措施 本工程选用地钻机、搅拌机、注浆泵等机械设备都处于完好状态,适合本项工程地施工,从 硬件上供应施工地质量保证,(具体资料见主要施工机械装备表),从而保证了机械设备有 良好地出勤率和最优地安全保证,同时配备肯定机械修理工跟班作业,确保工程设备处于正确运 行状态 .6.2.3 技术措施(1)水泥浆不得离析:水泥浆要严格按协作比配置 机中不断搅动 .为防止水泥浆发生离析,可在灰浆拌制(2)严格依据设计文件要求布置好钻孔位置,严格依据规范规程及公司制定地操作规程作业.(3)按设计针对不同施工情形配制适当协作比地浆液,施工用水量由水表计量掌握(4)加强边坡地表位移监测和滑坡体深部位移监测,发觉反常情形准时反馈建设单位和设计单位,以便实行补救措施 .(5)认真做好原材料检验 .另外我们仍设立自检机构,施工中严格按设计及施工组织方案进行施工以及质量自检,质检员须认真负责每一个施工环节地质量监督,确保整个工程质量,发觉问题准时解决 .与业主、监理亲密协作,常常汇报协商讨论工程质量和相关技术问题,努力创建优质工程 .7 施工安全7.1 安全目标本工程安全目标为“ 三无 ” 、“创建 ” . “三无 ” 即无工伤事故,无交通事故,无质量事故. “创建 ”即名师归纳总结 创建文明施工工地.第 11 页,共 16 页- - - - - - -精选学习资料 - - - - - - - - - 7.2 安全保证措施(1)工地设置安全生产领导小组,下设质安员,班组设兼职质安员,明确各级安全岗位责任人,健全安全治理体系 .(2)坚持三级安全训练制度,对特殊工种工人坚持持证上岗 .(3)坚持技术交底地同时进行安全技术交底,使参与操作人员明确安全操作规程和防患要领,严格遵守各种机具操作规程 .(4)按有关规定做好“ 三宝 ” 四器地防护,挂安全警示牌,坚持定期安全检查制度,发觉事故苗头准时排除,确保安全施工 .(5)坚持防火安全训练,防火及消防材料要符合省、市防火规范 .(6)施工开头前工程安全领导小组应针对现场实际和施工组织方案,编写安全生产方案及措施,并在施工中认真落实 .(7)建立安全治理网络:工程经理部设专职安全员1 名,在施工现场巡回检查,对各种担心全因素,准时提出改进看法,将担心全隐患毁灭在萌芽状态之中 .施工人员必需遵守操作规程,严禁违章作业,玩忽职守 .做好安全训练,安全交底和安全检查,委派工地安全员专职安全检查工作 .施工队再设 1 名兼职安全员,负责安全督促检查工作 .(8)对全部参与地施工设备进行开工前检查,检修、设备完好率达 100%.(9)设立专职安全员,负责施工中日常地安全施工检查,发觉隐患,准时督促整改 .建立施工安全档案 .(10)施工现场必需设置各种警示标志,保证施工安全 .(11)季节性施工措施 雨季施工措施雨季施工前,对施工现场地物料存放区域、构件存放区、临建、现场施工区域进行完全检查,做好防雨措施;雨季施工时,应依据当地气象信息做好防洪防汛防雷电工作,遇有暴风雨时,应临时停止工作.切断设备电源,并疏散到安全地点,确保施工安全 .a 雨季施工前,要疏通整个场地地排水系统,并明白该地区地常年雨水量和积水情形,编制名师归纳总结 好具体地雨季施工措施.30cm.第 12 页,共 16 页b 进入雨季,水泥库要加强防范,地坪要高出该地区积水线- - - - - - -精选学习资料 - - - - - - - - - c 雨期施工,室外配电板、配电箱应有防雨设施,斜道应设置防滑道,确保安全施工 .d 下雨施工前,就预备充分地防雨材料,并在施工期间派人昼夜值班,以防意外事情发生