余热锅炉基础专项施工方案.doc
《余热锅炉基础专项施工方案.doc》由会员分享,可在线阅读,更多相关《余热锅炉基础专项施工方案.doc(14页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、余热锅炉房基础专项施工方案Construction Scheme of HRSG Hall Foundation编制依据及说明Compilation Basis and Description 1.1 编制依据 Compilation basis 余热锅炉房基础施工图 F681ST030307; 图纸会审记录;电力建设施工质量验收及评定规程 第1部分:土建工程 DLT 5210.1-2005建筑地基基础工程施工质量验收规范 GB502022002混凝土结构工程施工质量验收规范 GB5020420021。1 Compilation basis“Construction Drawings of H
2、RSG Foundation Hall” F681ST030307;“Record of Counter-sign of Drawings”; “Quality Acceptance and Valuation Code of Electric Power Construction, Section 1, Civil Work Part” GB502022002“Quality Acceptance Specification of Building Subgrade and Foundation Work GB50202-2002“Quality Acceptance Specificati
3、on of Concrete Structure Work” GB50204-20021.2 编制说明 1.2 Description 1、2#、3余热锅炉基础总体布局相同,结构形式一样,功能也相近,故3个机组基础施工同时考虑,编写在同一方案中; The general plan layouts of 1、2# and 3# HRSG foundations are the same, as well as the structures and functions. So three HRSG foundations work will be considered into one const
4、ruction scheme. 余热锅炉基础包括垫层、基础承台、连系梁、短柱等几部分,本方案同时考虑,不另行编制方案; The HRSG foundation covers bedding course, foundation cushion cap, collecting beams and short columns etc which will be compiled in this scheme. 基础与上部框架采用螺栓连接,螺栓及固定架由厂家提供; Adopt Bolts connecting on the foundation and top frames, the bolts a
5、nd fixed frames will be supplied by manufacturer。 地基处理采用钢筋砼灌注桩,该部分已由打桩公司完成,基础土石方开挖已在工程桩交接前基本完成,本方案中均不再赘述。 The reinforced concrete caisson pile is used for sub-grade treatment。 This job has been finished by pile driving company, As earth and stone excavation of the foundation has been basically compl
6、eted before pile driving, so there is no other instruction about it in this scheme again。 2 工程概况 Summary of Work余热锅炉露天布置,分为1、2、3#基础,分别布置于燃机房区域轴线B-1413、B98、B-43,横向12.8m,纵向47。4m。锅炉基础轴线间相距48.5m。The outdoor arrangement of HRSG is separated by three parts, 1, 2 and # foundations, respectively set on the
7、axis line B1413、B-98 and B43 of GT hall area. The lateral length is 12。8m, longitudinal length is 47.5。 The space between HRSG foundation axis lines is 48.5m。 余热锅炉基础,承台型除了CT5、CT6为大体积基础,CT1CT-4为14个桩基基础,其余均为独立基础19个.基础间采用连系梁连成整体。基础承台底标高-4.0m。 The cushion cap is CT-5 and CT6 as big volume foundation, be
8、side that from CT1 to CT4 total quantity of piling foundations is 14, others are isolated foundations with 19 of the quantity. It is linked as a whole body by collar beams among foundations。 The bottom elevation of foundation cushion cap is -4。0m。 基础与上部框架采用螺栓连接,螺栓埋入基础短柱内。基础砼强度等级,垫层C10素混凝土,承台及连系梁C30,
9、基础柱段采用C40。砼保护层基础50mm,基础梁30mm,其余部位30mm。钢筋级为HPB235,级为HRB335. The foundation and top frames are connected by bolts which are embedded in foundation short column。 The strength grade of concrete is as following: C10 plain concrete is used for bedding course, C30 for cushion cap and connecting beams, C40
10、for foundation column section。 The protective layer of concrete, foundation girder and other places respectively are 50mm, 30mm and 30mm. Steel reinforcement grade is HP235, and grade is HRB335。 施工程序 Construction Procedure. 根据总体进度计划安排,余热锅炉基础施工顺序,总体先施工3余热锅炉基础,依次再进行2、1锅炉基础。1、2#、3#施工时可并行、交叉进行。 Accordin
11、g to the overall progress scheme of construction, The construction of HRSG foundation sequence is under hereby: Firstly construction for 3# HRSG foundation in generally, the following step is construction of 2#、1 HRSG foundation。 The construction of these foundations can be processed alternatively a
12、nd parallelly. 余热锅炉基础分三块区域施工,H6H1。3轴间桩基基础及系梁为第一区域,CT5、CT6大体积基础为第二区域,H1。3轴以南的独立基础为第三区域。It is divided in to 3 areas for HRSG foundation construction。 The pile foundation and conneting beam from axis line H6 to H1.3 is regarded as first area, the second area is large volume concrete foundation for CT-5
13、 and CT6, the third area is isolated foundation in south position of axis line H1。3。锅炉基础施工程序为:地基验槽 垫层支模 垫层浇筑C10 承台(或系梁)钢筋绑扎 支模 验收 浇砼C30 养护 拆模 回填 施工缝处理 螺栓施工 短柱钢筋绑扎 支模 浇筑砼C40 养护 拆模 回填The HRSG foundation construction sequence is as following: Inspection of foundation subsoil Formwork supporting for bed
14、ding course C10 Concrete pouring for bedding course steel bar binding for cushion cap (or conneting beam) support formwork inspection and acceptance C30 Concrete pouring curing demolition of formwork back filling treatment of construction joints Screw bolts working steel bar biding for short column
15、support formworks C40 concrete pouring curing removal of formwork backfilling。 3 主要分项工程施工方法 3。 Main Construction Methods of Subsection Work1、 测量放线 1. Survey and setting out1.1主要仪器:水准仪、RTS632全站仪、50m钢卷尺。1。1 Main Instruments: Level gauge, RTS632 total station and 50m steel measuring tape. 1。2根据现场原始定位点及
16、锅炉平面布置图,选择合适位置设置控制点,每次定位防线前对控制点进行复核。1。2 Select proper location to set control point according to site original position and plan layout of HRSG, recheck the control point prior to locating and setting out. 1。3 工作流程1。3 Work Flow:轴线用极坐标法测设.C10素砼垫层施工后,用全站仪从控制点引出,定出基础轴线,并在轴线两端及交叉点用红油漆进行标注。根据轴线确定基础承台、短柱及
17、连系梁边框线。Survey and set out the axis line by Polar Coordinate Methods. After finishing C10 plain concreting for bedding course, set the foundation axis line by total station from control point and mark the ends of axis line and cross point with red paint. The frame lines of foundation cushion cap, sho
18、rt column and conneting beam can be confirmed according to axis line. 高程用水准仪测量,从控制点引出,先确定出垫层底标高;模板支设加固完成后,在模板四角划出标高线,并用红油漆标识。Measure the elevation by level gauge; first confirm the elevation of bedding course leading from control point; The elevation line can be marked on the four corners of formwor
19、ks and marked with red paint after completion formwork supporting 2、钢筋工程 2. Steel Reinforcement Work。 2.1原材料 2.1 Raw Materials:本工程所用钢筋均采用大厂的钢材,经监理工程师现场见证取样进行复检,经试验合格后方可使用。 All of steel bars used in this project should be manufactured by large steel plant and final determination is depended on the en
20、gineers approval after material sampling and qualification of inspection.2。2 钢筋加工:2。2 Machining of Reinforcement bar在钢筋加工场地集中下料,统一配制。配制好的钢筋按进行码垛、保护,使用拖拉机运至锅炉现场绑扎。Unload steel reinforcement in the machining work shop and distribute them well. Stacking etc. protective measures must be taken after dist
21、ribution of steel bars, and then use tractors deliver to HRSG site area for assembling. 严格按照设计图纸及钢筋配料单进行加工成型,其规格、尺寸、质量应满足设计图纸要求。Strictly follow the design drawing and steel bar distribution sheet to machine them. The specification, dimension and quality should conform to the requirements of design d
22、rawings。2.3 钢筋绑扎 2.3 Steel Bar Assembling 基础钢筋网绑扎时,四周两行钢筋交叉点应每点扎牢,中间部分的交叉点可相隔交错扎牢,但必须保证受力钢筋不位移。绑扎时注意相邻绑扎点的丝扣要成八字形,以免网片歪斜变形。 The cross section point of two rows steel bars must be tightened well when assemble steel bars, the cross section point can be fixed staggeringly, however, non-movement of stre
23、ssed reinforcement must be warranted. Take notice that thread connection in adjacent of the assembling point should be splay-shaped to avoid distortion of mesh while assembling mesh reinforcement. 梁箍筋弯钩应错开绑扎,并保证转角处钢筋绑扎到位。 The stirrup hooks for the beams should be assembled staggeringly to make sure
24、the assembling of steel bar on cornerin correct place 插筋位置必须准确,采用钢筋井字架定位柱筋,利用承台面钢管双向固定柱插筋,以免造成保护层超标。 The position of steel dowel must be accurate, the groined steel frame is adopted to locate column reinforcement, use steel pipes on the surface of cushion cap to fix column steel dowel in two directi