1、精选优质文档-倾情为你奉上项目采购管理练习题1、While completing a project, a worker strike in the sellerscity has resulted in the required deliverable being late. What is generally the BEST thing for the project manager to do? A. Extend the contract for the length of the delay. B. Remind the seller that they are under con
2、tract to complete the project by the due date or be in default on the project. C. Investigate ways to shorten other parts of the project in order to meet the sellersproject completion date. D. Tell the seller to stop work on the project until the strike is settled. 1、实施项目过程中,卖方城市发生了工人罢工,导致可交付成果延期交货。
3、为此,项目经理通常的最佳做法是什么?A 延期合同B 提醒卖方他们有义务按照合同在规定的日期内提交产品,否则就是违约C 寻找可以削减项目其它活动工期的方法,以符合卖方完工日期D 告诉卖方停止工作,直到罢工得以解决2、The work breakdown structure has the LEAST impact on which process? A.Plan Human Resources. B.Estimate Costs. C.Develop Schedule. D.Plan Procurements. 2、工作分解结构对以下哪个过程影响最小?A 规划人力资源B 估算成本C 制定进度D
4、规划采购3、Although your company is not the lowest bidder for a project, the client has come to expect good performance from your company and wants to award the contract to you. To win the contract, the client asks you to eliminate your project management costs. The client says that your company has good
5、 project processes, and project controls unnecessarily inflate your costs. What should you do under these circumstances? A.Eliminate your project management costs and rely on experience. B.Remove costs associated with project team communications, meetings, and customer reviews. C.Remove meeting cost
6、s but not the project managers salary. D.Describe the costs incurred on past projects that did not use project management. 3、你公司参与了一个项目的投标,尽管你们的报价不是最低的,但客户还是希望跟你公司合作,并期待你公司做出好的绩效。为了赢得合同,客户要求你公司删除项目管理成本,理由是认为你公司有很好的项目管理过程,没有必要使用项目控制来增加不必要的成本。在这种情况下,你应该怎么做?A 删除项目管理成本,并凭借经验做事B 删除与项目团队沟通、会议及客户评审相关的成本249
7、专心-专注-专业C 删除会议成本,而不是削减项目经理工资D 告诉客户以前没有运用项目管理反而增加了项目成本的例子4、Source selection criteria are an output of which process? A.Plan Quality. B.Plan Risk Responses. C.Plan Procurements. D.Estimate Costs. 4、供方选择标准是以下哪项的输出?A 规划质量B 规划风险应对C 规划采购D 估算成本5、While completing work for your project, the sellers subcontra
8、ctor suffers a major fire. The fire destroys the heating system they were building for your project. What is the BEST thing to do? A.Stop payment on invoices for the heating system until work begins again. B.Check to ensure the subcontractor was covered by insurance. C.Be prepared to extend the deli
9、verable due date. D.Tell the seller to stop work on the part of the project that involves the heating system until their subcontractor can recover from the fire. 5、在项目实施过程中,供方的一家承包商发生了一场大火。火灾摧毁了将要供货给你项目的供热系统。你应该怎么做?A 工作重新开始前停止为供热系统支付费用B 确认承包商是否购买了保险C 延长可交付成果的交付日期D 告诉供应商,在承包商没有恢复之前停止涉及供热系统的活动into the
10、 companys strategic plan, but will require some of the best resources the company has in order to meet the quality objectives. Management is excited because the project represents the opportunity to generate good profits for the company and will put all their company expertise to the test. The prosp
11、ective team members are also excited because the client is prestigious. In order to meet the schedule objectives for the project, you need to start committing jobs to new and critical project resources now, while the contract is still under negotiation. What should you do? A. Wait until the last min
12、ute to do so. B. Ask the customer for a letter of intent. C. Only start to collect resumes and do not commit any funds. 6、为了赢得一个新的、重要的项目,你公司正在谈判过程中。此项目非常适合公司的战略规划,但需要用到公司最优秀的资源,以便达到质量要求。管理层对此很兴奋,因为这个项目会给公司带来丰厚的利润,同时会锻炼一下公司的专家。潜在的团队成员也很兴奋,因为这个客户是个知名企业。为了满足进度目标,在合同还在谈判过程中就需要你开始为新的、关键的资源安排工作内容。你应该怎么做?2
13、50A 等到最后一分钟再开始B 向客户要一份项目目标信函C 只开始搜集简历,但先不要动用任何资金D 向管理层解释,这不是一个好的想法7、Two team members are currently documenting and verifying the product, while two other team members are updating records, performing an audit, and archiving lessons learned. What activity are the team members engaged in? A. Administe
14、r Procurements. B. Close Procurements. D. Conduct Procurements. 7、两名团队成员正在归档文件、核实项目产品,另外两名团队成员正在更新项目记录、实施审计、归案经验总结。这些团队成员正在从事哪项活动?A 管理采购B 结束采购C 结束项目或阶段D 实施采购8、You are trying to decide whether to lease or buy an item for your project. The daily lease cost is US $150. The investment cost to purchase t
15、he item is US $2,000, and the daily cost is US $50. In how many days will the lease cost be the same as the purchase cost? A. 10. B. 15. C. 20. D. 25. 8、你正在对项目的某一工作进行自制或外购分析。制止的日均成本为 150 美金。外包此项工作的投资成本为 2,000 美金,日均成本为 50 美金。多少天之后自制成本和采购成本相同?A10 B15 C20 D25 9、Under a contract, formal, written corresp
16、ondence with the seller is required when: A. A change to the project is issued. B. A meeting with the sellersmanagement is held. C. The seller is asked for supporting information. D. There is a follow up to a conversation. 9、在合同条款下,在以下哪种情况下需要和供方进行正式的、书面信函?A 当项目发生变更B 当与供方管理层开会时C 当需要供方提供支持信息时D 谈话内容需要后
17、续跟踪时25110、You are managing procurement for a project and have arranged a bidder conference with the potential proposers. All of the following are appropriate for a bidder conference EXCEPT: A. A walkthrough of the project scope. B. An explanation of why particular teams and conditions are in the con
18、tract. C. A request for bidders to offer their thoughts on problems with the scope of the work. D. Working with the bidders to determine alternative solutions for the project.10、你正在管理项目的采购,已经安排了一个潜在供应商投标人会议。以下均适用于投标人会议,除了:A 了解项目范围B 解释合同中规定特殊条款的原因C 要求投标人就工作范围问题给出意见D 和投标人一起确定项目的替代解决方案11、Your contract
19、states that the maximum charge for services from the seller will be US $50,000/month. However, the actual invoices have been US $100,000 for the past three months. Stopping the sellersservice will impact the project schedule. Under these circumstances, the BEST thing to do is to review the: A. Contr
20、act change control system. B. Scope control system. C. Performance reporting system. D. Cost change control system. 11、合同规定,支付供应商的服务费最高每月 50,000 美金。然后,过去三个月的实际发票金额为 100,000 美金。如果停止供应商的服务将会影响项目进度,在这种情况下,最好是评审以下哪项内容?A 合同变更控制系统B 范围控制系统C 绩效报告系统D 成本变更控制系统12、The sellers project manager is managing a fixed
21、 price (FP) contract. She thinks that a large customer-requested change might impact the schedule of the project. What should she do FIRST? A. Meet with the stakeholders. B. Meet with the team. C. Renegotiate the remainder of the contract. D. Follow the contract change control system. 12、供应商的项目经理正在管
22、理一个固定价格合同。她认为客户发起的一项变更会对项目的进度产生影响。她首先应该做什么?A 会见干系人B 会见团队C 就合同剩余部分进行谈判D 遵循合同变更控制系统13、A company and its seller are in the middle of a long dispute over the costs of terminating the 252heard and resolved by a neutral party. To accomplish this, the project manager should us a(n): A. Functional resource