印度塔尔万迪4×660MW超临界燃煤电站项目锅炉说明书(中英文版).doc
《印度塔尔万迪4×660MW超临界燃煤电站项目锅炉说明书(中英文版).doc》由会员分享,可在线阅读,更多相关《印度塔尔万迪4×660MW超临界燃煤电站项目锅炉说明书(中英文版).doc(90页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、【精品文档】如有侵权,请联系网站删除,仅供学习与交流印度塔尔万迪4660MW超临界燃煤电站项目锅炉说明书(中英文版).精品文档.山东电力基本建设总公司印度塔尔万迪4660MW超临界燃煤电站项目SEPCO ELECTRIC POWER CONSTRUCTION CORP.,PRC TALWANDI 4660MW SUPERCRITICAL THERMAL POWER PLANTHG -2140/25.4-YM16 BOILER锅炉说明书Boiler Instruction Volume Boiler Proper and StructureNo. : F0310BT001C411Project
2、control No. : TALW 1 HBCLD HA GN 0BT 0001 A编制:EDIT校对:CHECK审核:REVIEW审定:VERIFY中华人民共和国哈尔滨锅炉厂有限责任公司THE PEOPLES REPUBLIC OF CHINAHARBIN BOILER COMPANY LIMITED目 录Content1锅炉设计容量和参数Boiler design capacity and parameter12设计条件Design basis22.1 工程主要原始资料Main original materials22.2 煤种Coal32.3 点火及助燃用油Fuel oil for i
3、gnition and firing supporting42.4 锅炉给水及蒸汽品质要求Requirement of boiler feedwater and steam quality52.5 服务设施Service device62.6 锅炉运行条件及模式Boiler operation condition and mode73锅炉特点Boiler feature73.1 技术特点Technical feature73.2 结构特点Structural features84. 锅炉性能计算参数及结构数据Boiler performance calculation parameter an
4、d structure data134.1 锅炉性能计算数据表Boiler performance calculation data sheet134.2 锅炉主要界限尺寸Boiler main boundary size155系统说明System introduction155.1 烟风系统Air-gas system155.2 汽水系统Steam-water system165.3 汽温控制Steam temperature control205.4 启动系统Start-up system216 锅炉整体布置Boiler general arrangement296.1 炉膛及水冷壁Fur
5、nace and water wall306.2 启动分离器和贮水箱Start-up separator and storage tank326.3 过热器、再热器和减温器SH, RH and desuperheater326.4 省煤器Economizer356.5 燃烧设备Combustion Equipment366.6 空气预热器Air preheater386.7 阀门和管道Valve and piping396.8 炉顶密封和包覆框架Boiler roof sealing and enclosure frame396.9 热膨胀系统Thermal expansion system4
6、26.10 钢构架和平台楼梯Boiler steel structure and platform436.11 热结构Hot structure487 辅助设备说明Auxiliary equipment instruction577.1 安全阀Safety valve577.2 吹灰器Soot blower587.3 烟温探针Gas temperature probe607.4 锅炉疏水和放气(汽)Drainage and air (steam) vent618 水动力特性Hydrodynamic characteristic63图0101:锅炉总体布置图-纵剖视Drawing 01-01:
7、General Arrangement of Boiler Side View65图0102:锅炉总体布置图-前视图Drawing 01-02: General Arrangement of Boiler - Front View66图0103:锅炉总图布置图-顶视图Drawing 01-03: General Arrangement of Boiler Planform View67图0104:锅炉总图布置图-水平视图Drawing 01-04: General Arrangement of Boiler Plan View68图0105:锅炉汽水流程图(水冷壁系统)Drawing 01-0
8、5: Steam and Water Flow Diagram (Water Wall System)69图0106:锅炉汽水流程图(过热器系统)Drawing 01-06: Steam and Water Flow Diagram (SH System)70图0107:锅炉汽水流程图(启动系统)Drawing 01-07: Steam and Water Flow Diagram (Strat-up System)71图0108:锅炉汽水流程图(再热器系统)Drawing 01-08: Steam and Water Flow Diagram (RH System)72图0109:锅炉热膨胀
9、系统图Drawing 01-09: Thermal Expansion System of Boiler73图0110:燃烧器立面布置总图Drawing 01-10: Vertical General Arrangement of Burner74图0111:主燃烧器水平布置总图Drawing 01-11: Horizontal General Arrangement of Main Burner75图0112:SOFA燃烧器水平布置总图Drawing 01-12: Horizontal General Arrangement of SOFA Burner75图0113:EL17000平面布置
10、图Drawing 01-13: EL17000 Plan Arrangement76图0114:B0,B46立面布置图Drawing 01-14: B0, B46 Vertical Arrangement77图0115:BH立面图Drawing 01-15: BH Vertical Arrangement78图0116:锅炉基础负荷图Drawing 01-16: Boiler Steel Structure Load at Ground Level79图0117:冷态启动曲线Drawing 01-17: Cold Start Up Curve of Boiler80图0118:温态启动曲线Dr
11、awing 01-18: Warm Start Up Curve of Boiler81图0119:热态启动曲线Drawing 01-19: Hot Start Up Curve of Boiler82图0120:极热态启动曲线Drawing 01-20: Very Hot Start Up Curve of Boiler83哈尔滨锅炉厂责任有限公司(简称哈锅)为印度Talwandi电厂设计制造的660MW锅炉采用了哈锅自主开发的超临界锅炉技术。该锅炉为变压运行、一次中间再热、单炉膛、平衡通风、固态排渣、全钢架悬吊结构、露天布置的型超临界锅炉,采用不带再循环泵的大气扩容式启动系统,采用新型切圆
12、燃烧方式、低NOx燃烧器,24只燃烧器分6层布置。采用直吹式制粉系统,配上海重型机器厂有限公司制造的6台BBD4760双进双出磨煤机。锅炉在BMCR工况下,5运1备。(总体布置图见图01-0104)The 660MW boiler which designed and manufactured by Harbin Boiler Company Ltd (HBC) for India Talwandi power plant adopts the supercritical boiler technology developed by HBC itself. The boiler is type
13、 outdoor arrangement supercritical boiler with variable pressure operation, single intermediate reheat, single furnace, balanced draft, dry ash removal and total steel frame suspending structure. It has atmospheric flash type startup system without recirculating pump and adopts tangential firing, lo
14、w NOx combustion burners, 24 burners are arranged in 6 layers. The boiler is equipped with 6 BBD4760 double-ended ball mills direct-fired system of Shanghai Heavy Machinery Co.Ltd, under BMCR condition, 5 mills are in operation 1 mill is standby. (the general arrangement drawing is showed in 01-0104
15、)锅炉以最大连续出力工况(BMCR)为设计参数。在任何5台磨煤机运行时,锅炉能长期带BMCR负荷运行。Boiler takes maximum continuous rating (BMCR) as design parameter. When any 5 mills are operating the boiler can operate with BMCR load for long time. 1、锅炉设计容量和参数 Boiler design capacity and parameter单位UnitBMCR工况BMCR LoadTMCR工况TMCR Load过热蒸汽:Superheat
16、ed steam过热蒸汽流量Superheated steam flowt/h21402003.1过热器出口蒸汽压力SH outlet steam pressureMPa.g25.425.24过热器出口蒸汽温度SH outlet steam temperature571571再热蒸汽:Reheat steam再热蒸汽流量Reheat steam flowt/h1732.991630.07再热蒸汽进口压力Reheat steam inlet pressureMPa.g4.8154.529再热蒸汽出口压力Reheat steam outlet pressureMPa.g4.6054.332再热蒸汽
17、进口温度Reheat steam inlet temperature330.9324.3再热蒸汽出口温度Reheat steam outlet temperature569569主给水压力Main feedwater pressureMPa.g29.0028.46给水温度Feedwater temperature293.4289注:1.BMCR工况表示锅炉最大连续出力工况,对应于汽轮机在阀门全开时(VWO工况)的进汽量参数;2.TRL工况对应于汽轮机TRL负荷参数;3.压力单位中“g”表示表压。“a”表示绝对压(以后均同)。Note: 1. BMCR condition is boiler m
18、aximum continuous rating, corresponding to the inlet steam parameter when turbine valves are totally open (VWO).2. TRL condition is corresponding to the load parameter of turbine TRL.3. “g” in pressure unit is gauge pressure. “a” is absolute pressure (be the same hereinafter).2、设计条件 Design basis2.1
19、工程主要原始资料 Main original materials2.1.1环境条件 Environmental condition本工程建设场地所处区域具有高温高湿气候特征。The construction site of this project is in the area with climate features of high temperature and high humidity.The Site address: Village Banawala,District Mansa, IndiaThe Site elevation: upper MSL 208.5m2.1.2气象特
20、征Climate featurei. TemperatureMean daily maximum : 41.2 (June)Mean daily minimum : 4.5(January)Mean yearly maximum : 31.8 Extreme maximum : 48.2 Extreme minimum : - 3.9 ii. Wind SpeedMean minimum : 2.1 km/hrMean maximum : 6.2 km/hrWind direction : North west to SoutheastWind loading will be in accor
21、dance with Indian Standard Code IS875 for a basic wind speed of 47m/sec. up to a height of 10 metres above mean ground level. Appropriate probability factor, terrain, height and structure size factor, and topography factor shall be considered as per IS-875/UBC-1997iii. RainfallMaximum annual : 693 m
22、miv. Relative HumidityMaximum : 76%Minimum : 33%Seismic Zone : Zone III as per seismic zone classification IS1893/latest version2.2 煤种 Coal 电厂以印度煤为锅炉主要燃料。锅炉在燃烧设计煤质和校核煤种的条件下运行时,均能实现保证的性能,如出力等。The power plant takes India coal as the boiler main fuel. The boiler can achieve guarantee performance when f