1、【精品文档】如有侵权,请联系网站删除,仅供学习与交流履带吊组装作业指导书.精品文档.CSPC NANHAI PETROCHEMICALS PROJECTCSPC 南 海 石 化 项 目THE ASSEMBLY OF CC1000 CRAWLER CRANECC1000履带吊组装作业指导书WORKING INSTRUCTION: WI-8710-8100-2012作业指导书:WI-8710-8100-2012SEPCO Electric Power Construction Corporation山东电力基本建设总公司REV 版次DATE日期REASON OF ISSUE发布原因BY编制CHKD
2、审核REVIEW审查APPR批准A26NOV 03ISSUED FOR REVIEWZJZFZXSDPB02DEC 03ISSUED FOR APPROVALZJZFZXSDP目 录TABLE OF CONTENTS1 PURPOSE目的 2 SCOPE范围 3 RESPONSIBILITIES职责 4 PROJECT SUMMARIZATION工程概述 5 WRITING REFERENCE编制依据 6 CONSTRUCTION PREPARATION施工准备7 THE CONSTRUCTING MACHINES AND TOOLS 施工机械及工器具8 ORGANISE LABOUR FOR
3、CE劳动力组织9 CONSTRUCING PROCESS AND METHOD 施工工序和施工方法10 THE PROTECTION MEASURE OF ENVIRONMENT境保护措施11 JOB SAFETY ANALYSIS安全工作分析1 PURPOSE目的 To provide the working instruction for the assembly of CC1000 crawler crane in CSPC Nanhai Petrochemicals Project, Steam & Power Plant Project to ensure the project t
4、o complete on time and with good quality.在于制订南海石化汽电联产项目的CC1000的组装的作业指导,确保工程高质量的按期完工。2 SCOPE范围This instruction complies to the assembly of CC1000 crawler crane in CSPC Nanhai Petrochemicals Project, Steam &Power Plant Project 本指导书适用于南海石化汽电联产项目起重机械CC1000履带吊的组装。3 RESPONSIBILITIES职责3.1 SEPCO2 is respons
5、ible for the assembly and adjusting of CC1000 crawler crane. SEPCO2负责CC1000履带吊的组装与调试。3.2 SEPCO is responsible for the interface coordination and acceptance.SEPCO 负责接口协调和质量验收。4 PROJECT SUMMIRUZITION 工程概况 As the project needs, CC1000 will be transported from Yunhe project to Huizhou to lift the boiler
6、 steel structures. According to the requirement of the project, the working rate is 48m+36m.因工程需要,CC1000由运河工地运至惠州工地,用于锅炉钢架的吊装,根据工程需要其作业工况为48m+36m塔式工况。5 REFERENCE编制依据1.1 Site condition施工现场条件1.2 The manual of CC1000 crawler craneCC1000履带吊使用说明书6 CONSTRUCTION PREPARATION施工准备6.1 Constrution location smoo
7、th and temper 施工现场平整夯实6.2 Good separate measure on the site现场作好隔离措施6.3 The construction machines and tools are available.施工机械及工器具准备到位 6.4 Make a good orginazation of construction personel作好人员的组织工作7 THE CONSTRUCTING MACHINES AND TOOLS 施工机械及工器具7.1 Crawler crane QUY50A and crane 30tQUY50A履带吊和50t汽车吊各一台
8、7.2 Big hammer ,wrench and other common tools大锤、扳手及其他常用工具7.3 Steel wire,tach ect,should meet the requirement钢丝绳、卡扣等应符合使用要求7.4 Pulling rope enough准备好揽风绳数量8 ORGANISE LABOUR FORCE 劳动力组织Commpany principal:1 Technical principal:1 HSE:1 Rigger:3 Electrician:2 Overhauling personel:3 Operator :3 Fitter:2公司负
9、责人:1 技术负责人:1安全员:1 起重工:3电工:2 检修工:4操作工:3 安装工:29 CONSTRUCTING PROCESS AND METHOD 施工工序和施工方法9.1 The width of the assembly area is about 20m and length 100m, and there are should be no barriers. The working ground is smooth, and separated by guard-rope.组合场地宽度约20米,长度约100米,且无障碍物。该工作场地平整,用警戒绳隔离。9.2 Transport
10、 CCI000 to the assembly area. Use the QYU50A and 50t crane to unload it。将CCI000运至组装现场,用QUY50A和50t汽车吊将其卸下。9.2.1 The front adopts a 6 37 36.5 20m rope, whose broken force is P=85.6t, the steel wire rope rolled to 4 twists. It can bear the weight of 39t. QUY50A is the main arm 16m,whose rated load is 4
11、4.95t and working radius is 4m.85600sin78.79439000Safety factor:n= =6 = 8.3 3900044950Load ratio: K= 100%=86.7%前头采用63736.520m绳扣一根,其破断拉力为:P=85.6t,钢丝绳绕成4股,其承重为39t。QUY50A为16米主臂工况,额定负荷为44.95t,作业半径为4米。85600sin78.79439000其安全系数: n= =8.33900044950负荷率: K= 100% =86.7%9.2.2 The front adopts two 63721.516m rope
12、s, whose broken force is P=5.3t. The steel wire rope rolled to 8 twists. It can bear the weight of 17.5t.The rated load of crane is 22.9t,whose working radius is 4m.后边采用63721.516m绳扣2根,其许用拉力为:P=3.3t,钢丝绳绕成8股,其承重为17.5t。汽车吊额定负荷为29.50t,作业半径为5m.17.5 8sin75.52安全系数: n= =2.36t3.3t1750029500负荷率: k= 100%=59.3%
13、17.5 8sin75.52Safety factor :n= =2.36t3.3t1750029500Load ratio : k= 100%=59.3%9.2.3 Unload and assembly the crawler by 50t crane,and the weight of crawler is 23t, adopts a 6 37 36.5 20m rope,.The steel wire rope rolled to 4twists,so the safety factor of the steel wire rope is:n=856004/23=14.9用50t汽车吊
14、将履带卸车并组装,履带重23t,起吊绳用63736.520m钢丝绳一根,4股起吊,则钢丝绳的安全系数为:n=856004/23=14.9 50t crane adopts the main arm 10.4m, and limit the radius 50t is 5m,whoserated load is 30t,then the load ratio of crane is:K=(23+0.56)/30=78.5%汽车吊采用10.4米主杆,半径控制在5米,其额定负荷为30t。则吊车负荷率为K=(23+0.56)/30=78.5%9.2.4 When use two cranes to l
15、ift at the same time, lift to leave ground about 10 cm and stop over 10 minutes. Check the condition of each part of foundation machine. After sure nothing ,truck remonve stack up wood and put down the main machine. First assembly one crawler, then remove the wood when assembly the other,finally loa
16、d equilibrator .两车同时抬吊时,抬离托盘约100mm,停留10分钟,检查地基机械的各部件状况,确认无问题后将拖车开走垫上道木,高度800mm,将主机放下。先穿上一条履带,然后穿另一条履带时将枕木撤去,并连接好四根斜撑杆,最后根据说明书的要求装上配重。9.3 The assembly of the boom and rigging 臂杆、拉索的组装 6.3.1 Assembly the arm pole and rigging according to the relevant requirements of the manual. After they are assemble
17、d, connect moment limiter and the cable of height limiter,load the pull sensor in term of the request and pull on the rising rope.按说明书的有关要求进行臂杆、拉索的组装,待其组合好后,按要求安装好拉力传感器,并穿好起升绳。 9.3.2 Use the assistant crane to lift the secondary arm。Raise the main arm about 10. Adjust the top limiter and the lower l
18、imiter when pulling up the main arm,and the angel error can not be over 0.5.Continue to pull up main arm after adjusting the limiter,the top block of the assistant arm should roll down the ground to reduce the pulling moment. The top assistant arm dont leave the ground until the inclusion angle betw
19、een the main arm and the ground isnt over 35. 扳杆时用辅助吊车吊起副臂,将主杆扳起约10时,调整副杆上、下限位,其角度误差不得大于0.5。限位调整好后,继续扳起主杆,副杆头部滑轮应沿地面滚动,以减少扳起力矩,当主杆和地面夹角大于35时,副杆头部方可离地。 9.3.3工况组装后的检查 Check after the assembly9.3.3.1 Whether the crane is placed on the level place.起重机是否放置在水平位置9.3.3.2 Whether the equilibrator meets the r
20、equirement.配重是否符合要求9.3.3.3 Whether the erection of the boom is correct.臂杆的安装是否正确 9.3.3.4 Whether all the limiting switchs are installed correctly and work normally.所有的限位开关是否正确安装和全部正常9.3.3.5 Check the flexibility of the mechnization tiliting preventation support within the swing scope.扳起前,检查机械式防后倾支撑在
21、整个摆动区域内动作是否灵活 9.3.3.6 Whether the system of the hydraulic pressure is natural.液压系统是否正常9.3.3.7 Whether the pin connection is safe and reliable.所有的销连接是否安全可靠9.3.3.8 Whether the indication of the instrument is normal.仪表指示是否完全正常10 THE PROTECTION MEASURE OF ENVIRONMENT 环境保护措施10.1 Make the oil leakproof me