烟囱滑模施工技术、烟囱施工措施(The construction technology of chimney sliding mode and the construction measures of chimney).doc
《烟囱滑模施工技术、烟囱施工措施(The construction technology of chimney sliding mode and the construction measures of chimney).doc》由会员分享,可在线阅读,更多相关《烟囱滑模施工技术、烟囱施工措施(The construction technology of chimney sliding mode and the construction measures of chimney).doc(19页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、【精品文档】如有侵权,请联系网站删除,仅供学习与交流烟囱滑模施工技术、烟囱施工措施(The construction technology of chimney sliding mode and the construction measures of chimney).精品文档.烟囱滑模施工技术、烟囱施工措施(The construction technology of chimney sliding mode and the construction measures of chimney)The construction technology of chimney sliding mod
2、e and the construction measures of chimneyI. project overview and characteristicsThis project for the valley of god biological technology group co., LTD. Power plant chimney project, the project, the chimney height of 120 meters, exit diameter of 3.5 meters, the cushion layer for the C10, basis for
3、C30, drum as a C30, lining for refractory brick acid-proof daub masonry.This project belongs to the high altitude, the difficulty is big, tall buildings construction and construction technology is complex, but my company has a group of experienced, theory and practice of battle-hardened chimney prof
4、essional construction team, both in management and the construction technology need to be able to do this project.Ii. Construction objectives1. Target: the total calendar works for 120 days, completing the total amount of work.2. Quality objectives: the acceptance rate of the subsection is 100%, the
5、 optimal rate is greater than 90%, and the engineering perception is greater than 85%.3. Cost objective: ensure the quality and safety of the project, and plan to save 17% of the project cost by means of effective management.4. Security objectives: adhere to the principle of safety first, prevention
6、 first, ensure that the general frequency of accidents is less than 1.5 , and the rate of death rate is zero, and the major and major safety accidents are eliminated.5. Environmental protection goal of civilized construction: strengthen the scientific management of construction site, meet environmen
7、tal requirements, establish humanistic engineering image, and create municipal construction site.6. Technical progress goal: the project is listed as a technical demonstration project of the enterprise, and the efficiency rate of scientific and technological progress reaches 1.5 .7. Service goal: to
8、 establish the owner to meet the construction process, and to track the quality of the project for three years.Construction and deployment1. Main construction techniques1.1 the overall template construction is adopted by using the shaft frame.1.2 construction of concrete pouring and construction of
9、reinforced concrete tube with inner lining.2. Construction processConstruction preparation - digging - cushion to equipment assembly, foundation of the whole board to backfill, concrete casting tube body and lining concrete casting pouring each paragraph (1.25 m) - thermal insulation masonry each pa
10、ragraph (1.25 m) - shell concrete castingInstallation of the signal platform, installation of the climbing ladder, the installation of the lightning protection electrical installation, the application of the air sign painting, the removal of the equipment, the construction of the smoke barrier wall,
11、 the clearance.Iv. Main construction technology plan1. Installation of internal derrick, platform and lifting systemThe overall construction process is as shown in figure 1.1.1 construction of derrick installationInternal vertical height of 1.25 m, the adoption steel pipe scaffold erection, standing
12、 pole level interval of 1.5 m, the level of rail vertical interval of 1.15 m, according to the diameter of chimney set-up, than the degree of its diameter reduced gradually along with the lining size (into the frame after checking see attachment 1). When setting up the steel pipe frame, insert the e
13、nd of the steel tube into the lining brick masonry, and place it on the brick masonry (see the figure below:). In the height direction, every 10 m bracket must be around four pole elongation, until both ends of the anchor into the wall concrete 50 mm, with reinforced concrete wall, guarantee and fra
14、me strength and stability, in extreme when installation package on isolated cement concrete, so as to avoid the future couldnt open the steel tube (see image below: detailed B).Chimney construction shaft frame is increased with the chimney wall construction, installation height is beyond + / - 0.000
15、 for the first time in 3 5 m, the bottom of the derrick bearing based on the concrete floor, foundation concrete surface of the steel plate should be related to cushion flat. When the cage is mounted on the derrick,Place in a specified silo beforehand. All personnel must be equipped with safety belt
16、 and skid insulated shoes when setting up. When the pipe is up, it must be hoisting.1.2 operation platform constructionThe operating platform has two floors, the lower layer is the brickwork binding, the upper layer is the lifting plate, the supporting plate is set, the concrete is used. On the oper
17、ating table spread 50 x 300 wooden board, wood board and derrick steel pipe with strong brown or 8 wire binding and firm, not a blind leap, should tightly, board with board between seam, wooden plank with large gap between the steel tube with a narrow strip or a metal block. The operating table rise
18、s with the derrick, and the board is used to prepare three sets of turnover.In the middle of the well frame, set apart the square hole of 0.9 x 0.0.9 m, and the loading port of the drum, and a 0.2 by 0.2 m hole in the center position, as the hole of the center line of the cylinder in the constructio
19、n process. Make 1.2 m * 1.2 m sealing plate. After the bucket is up to the platform, it is used to seal the hole and place the wheelbarrow when unloading, and the normal personnel walk to ensure the safety.There is no outer ring platform on the derrick, and the people who tighten the wire fly only t
20、ighten at the outside. When the die and the lifting template, each person is standing in the ring wall of the ring, not outside construction. If the surface quality problem of concrete is needed to be dealt with, the personnel on the external ladder will be processed.Corresponding position, outside
21、the chimney so we have set up a 3.8 m high external gym, can facilitate the relevant personnel security through the chimneys of the ladder, the ladder up to the platform in the plugin, for the construction and quality inspection. This is shown in the figure below.Description:1. The platform and the
22、platform of the platform and the protection platform4. Corner pulley 57. Place all kinds of power distribution boxes and tools in the tent, and cover with asbestos tiles to prevent rain, sun protection, andSet the lightning rod to connect with the steel tube frame lightning protection system to prev
23、ent lightning.Operating platform and external ladder diagram1.3 internal and external lifting system constructionThe vertical lifting device in the chimney USES 5t hoist, with a diameter of phi 14 wire rope, through the bucket. The bucket is round, welded with 6mm thick steel plate, high 700mm, the
24、bottom diameter of 650mm, the outer diameter of 750mm, the base plate is fixed with pin shaft, can turn up and down the sealing material or open the unloading material up and down. During the construction process, check the flatness of the base plate regularly, and put the steel bars, steel pipes an
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 烟囱滑模施工技术、烟囱施工措施The construction technology of chimney sliding mode and the measures chimney 烟囱 施工 技术
链接地址:https://www.taowenge.com/p-17259259.html
限制150内