1、本文档为独家精品文档尊重原创 切勿盗版以下资源均为最新版感谢您的支持铁路隧道工程施工承包合同CONTRACT OF RAILWAY TUNNEL ENGINEERING CONSTRUCTION翻译:张云军 签署日期: Date of Signature甲方:中铁集团以下简称甲方Party A: China Railway Group. ( hereinafter referred to as Party A)乙方:隧道工程公司以下简称乙方Party B: Tunnel Engineering Company (hereinafter referred to as Party B)条款目录 C
2、ONTENTS一、 组成合同的文件: Documents Constituted Contract二、 工程概况 General Review of Project三、 工期 Work Term四、 工程数量的核实和确认 Check and Confirmation of Work Quantity五、 承包工程造价 Project Cost六、工程质量标准与验收 Project Quality Standards and Acceptance七、隐蔽工程检查和签证 Inspection and Confirmation of Hidden Works八、材料的供给 Supply of Mat
3、erial九、工程变更 Alteration十、双方责任与权利 Responsibilities and Rights of Parties十一、平安施工 Safe Construction十二、进度方案 Progress Schedule十三、承包工程价款支付和结算 Settlement and Payment十四、履约担保 Performance Bond ( PB履约金 2-5%)十五、保修 Maintenance and Repair十六、违约责任 Liabilities十七、 其它约定 Miscellaneous 鉴于:甲方系铁路建设工程总承包商,因铁路建设需要并经过业主同意,通过招
4、标将一号隧道工程承包给具有隧道建设资质和能力的专业公司施工;鉴于:乙方系专业从事隧道工程建设的施工公司,具有相应的工程资质和能力,中标承包本合同工程;据此,甲方将一号隧道的洞身钻爆开挖、洞门修建、防排水设施、锚网喷支护、衬砌、洞内沟槽及洞室和相应的隧道施工附属工程承包给乙方施工,经双方协商一致,订立本合同,共同遵守。WHEREAS: Party A being general contractor of railway engineering will, for necessity of railway construction and gain employers consent, cont
5、ract through bidding No. One tunnel project to the professional company with qualification and capability of tunnel construction for execution;WHEREAS: Party B being the professional company of tunnel construction with corresponding engineering qualification and capacity has won bidding and been awa
6、rded the project hereof.NOW THEREFORE, Party, in accordance with the necessity of construction, consign the works of Tunnel No. 1 to party B for execution, including blasting excavation, tunnel portal construction, drainage facilities, bolting and shotcrete lining, lining, channel and ditch within t
7、unnel in addition to corresponding projects affiliated to tunnel engineering, for which parties by mutual agreement conclude and enter into this contract , parties hereby agree as follows:一、组成合同的文件: Documents Constituted Contract组本钱合同的文件包括:including the following:1、本合同协议书 Agreement hereof2、本合同条款 Ter
8、ms and conditions hereof3、本工程适用的标准、标准及有关技术文件Standards, norms and concerned technical documents applicable to this engineering.4、甲方技术交底图纸 Drawings delivered by party A, with explanation of technology.5、附件1?承包人承包工程工程一览表工程量清单?,以及双方有关工程的洽商、变更等书面协议或文件视为本合同的组成局部。Appendix One: The List, Bill of Quantity of
9、 Engineering contracted by contractor in addition to the agreements or files in writing relative to negotiation, alteration of engineering by parties hereto will be deemed as integral parts hereof.二、 工程概况 General Review of Project、工程名称:一号隧道。Project Name : Tunnel No. One、工程地点:DK 094+506 至DK095 +658;
10、Project Place:、工程规模:隧道总长1152m 。Project Scale: Total Tunnel Length : 1152 Meters、承包范围和内容包含: Contracted Scope and Contents including as follows:1、洞身开挖围岩级别分类情况见工程量清单。具体内容包括:临时设施建设、脚手架,测量,人工挖除整修,钻眼、爆破、通风、出碴、运料、照明,管线及排水,木支撑制作、安装、拆卸,整修边沟,超挖回填等为完成隧道开挖所需的一切工序施工、完成和缺陷修复工作弃碴运距从出碴洞口算起1 公里、弃碴场用地由甲方负责。Tunnel Exe
11、cution: The grade of surrounding rock refer to List of Quantity, particulars thereof include as follows: temporary facilities, scaffolding, measurement, artificial digging renovation, drilling, blasting, ventilation, ballast leaving, transport material, lighting, pipeline and drainage, the productio
12、n, installation, disassembly of wooden support, repair side ditch in addition to backfill for over excavation and other works which are necessity for execution, complement and defect repairs of tunnel project.2、支护 SupportA、砂浆锚杆、中空注浆锚杆。Mortar anchor, hollow grouting anchor.B、超前小导管-钢管加工制作、运输、脚手架、钻孔、顶管
13、等全部制安过程;Advanced small pipe - pipe manufacture, transport, scaffolding, drilling, pipe, jacking and all other process of manufacture and installation.3、衬砌,包括正洞衬砌、仰拱及其钢筋、仰拱填充、铺底、大小避车洞衬砌。Lining, including tunnel, inverted arch and reinforcement, the inverted arch filling, bedding in addition to lining
14、 of refuge holes of various sizes.三、工期 Work Term开工日期: ,竣工日期为: 。Commencement date is , completion date is . 四、 工程数量的核实和确认 Check and Confirmation of Work Quantity1、乙方向甲方施工技术人员提交已完工程量计算单或签证,以便甲方对乙方进行验工计价。Party B will submit party As technical personnel with List of Completed Quantity or Certificate of
15、Quantity for party As acceptance and calculation of party Bs works.2、工程量验收方法:Means of Quantity Acceptance隧道开挖数量以隧道设计开挖断面计算;衬砌数量按照图纸设计厚度及尺寸计算;排水沟、电缆槽按照设计图纸尺寸及附表清单单价计量;隧道砂浆锚杆、超前锚杆支护数量按乙方依照甲方技术交底施工的实际数量计算。Tunnel excavation quantity is calculated pursuant to excavated section in tunnel design; lining qu
16、antity is calculated pursuant to the thickness and size of drawings design; quantity of drainage ditch and cable trough are calculated under the design size in drawings and unit price in appendix list; quantity of tunnel mortar anchor and ahead of the bolt support, subject to Party B actual worked n
17、umber are calculated in accordance with party As technical explanation.3、乙方应按照甲方技术人员的技术交底进行施工。工程量以乙方按照甲方技术交底完成的实际施工数量为依据。乙方完成的结算工程量须由甲方施工技术、质量检验工程师审核签证,且须经工程总工审批后才能作为验工计价的依据。Party B should, pursuant to the technical direction by party As technical personnel, carry out execution. The quantity is the
18、same which are actual completion by party B in accordance with party As technical direction. The settlement of quantity of party Bs completion should, prior to being deemed as the basis of the acceptance and cost calculation, be determined by the check and confirmation of party As engineers of techn
19、ician and quality in addition to the exam / approval of projects general engineer.五、 承包工程造价 Project Cost各分项工程承包单价为:见附件一?工程量清单?, 结算工程数量根据实际完成的合格工程量计量。乙方根据甲方提供的施工图纸,以下述的承包单价即?附件1:承包人承包工程工程一览表工程量清单?, 完成隧道工程所有工程内容施工、竣工和缺陷修复工作。Unit price of sub-project refer to Appendix One BILL OF QUANTITY on which the
20、settlement quantity will be calculated on the qualified quantity completed actually by party B. Party B will, in accordance with party As execution drawings and subject to the unit price, viz. Projects List and Quantity List, make completion of any and all items of tunnel construction including exec
21、ution, completion and defects repair.六、工程质量标准与验收 Project Quality Standards and Acceptance1、乙方必须严格按照甲方技术交底、现行铁路验收标准和铁路施工标准组织施工。乙方所承包的工程,必须到达国家或本行业现行的工程质量验收标准。Party B should, in strict conformity with party As technical direction and existing railway acceptance standard / norm, carry out execution her
22、eof. The project contracted by party B should satisfy to the acceptance standard which are stipulated by state or industry.2、凡因乙方原因造成的施工质量不合格的工程,乙方应在规定的时间内无偿进行返工,如果返工后仍达不到验收标准的,甲方有权委派其它单位或个人进行整修,费用由乙方承当。Provided that any defect / unqualified work in project execution due to party B, rework should be
23、 carried out by party B in free, where the rework is still not satisfy acceptance standard, party A is entitle to dispatch other contractor or individual to conduct repair for which the cost will be on party Bs account.七、隐蔽工程检查和签证 Inspection and Confirmation of Hidden Works1、甲方质检人员在对隐蔽工程检查前,乙方应进行严格的
24、自行检查。Respect to hidden work party B should conduct self-strict exam before the inspection by party As quality inspector.2、乙方每进行一道工序施工前,必须及时通知甲方,对上道工序完成工程量确实认。Party B should, prior to conduct next work procedure, give notice timely to party A for confirmation of the completion quantity in ahead proce