2021PMP资格认证考试考试模拟卷(1).docx
《2021PMP资格认证考试考试模拟卷(1).docx》由会员分享,可在线阅读,更多相关《2021PMP资格认证考试考试模拟卷(1).docx(16页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、2021PMP资格认证考试考试模拟卷(1)本卷共分为1大题39小题,作答时间为180分钟,总分100分,60分及格。一、单项选择题(共39题,每题2分。每题的备选项中,只有一个最符合题意) 1.While reviewing the estimates from the functional managers assigned to your project you discover that one cost estimate is clearly higher than those submitted for previous projects. You should ().Areject
2、 the estimate and remove the functional manager from the projectBrequest the supporting details for the estimate to ensure it has been properly preparedCaccept the estimate and plan to use the additional funding as a reserveDquestion each functional manager for information about this estimate2.A pro
3、jects payback period ends when ().Aprofit maximum is realizedBunit profit is realizedCmonthly revenue exceeds monthly costsDcumulative revenue equals cumulative costs3.One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and ().Adivide it by the sched
4、ule performance indexBmultiply it by the schedule performance indexCmultiply it by the cost performance indexDdivide it by the cost performance index4.A generally accepted method to confirm accuracy of task progress is through ().Aearned valueBprobability v outcomeCmaximum ceilingDwork breakdown str
5、ucture5.You are getting project performance information as your project is being executed. Based on the performance information, forecasts are updated and reissued. Some factors that could change as forecasts are updated include ().Aestimate to completeBestimate at completionCestimate to complete an
6、d estimate at completionDnone of the above6.All the following are costs incurred to ensure compliance to requirements except ?()Aprevention costsBappraisal costsCquality planning costsDwarranty costs7.Cost control outputs include all of the following EXCEPT ().Aestimate at completionBbudget updatesC
7、revised cost estimatesDcost baseline8.Which of the following choices indicates that your project is 9% under budget ?()AThe cumulative AC was 100, and the cumulative EV was 110BThe cumulative PV was 100, and the cumulative AC was 110CThe cumulative AC was 110, and the cumulative EV was 100DThe cumul
8、ative EV was 100, and the cumulative PV was 1109.To define variance thresholds at designated time points over the duration of a project, you will use ().Aunits of measureBprecision levelCorganizational procedure linksDcontrol thresholds10.Earned value technique(EVT)can best be defined as ().Aanalysi
9、s of the value of the equipment that has been installed as of the dateBanalysis of the sum of the labor costs, which have been incurred on the project to dateCa method of project performance measurementDa method of measuring the amount of money that has been spent to date11.Your company has establis
10、hed a reward and recognition system for its project management professionals. Project cost performance is used as a criterion to determine rewards. What should you do to ensure that rewards reflect actual performance ?()AConsider overtime work as part of the joBPrepare a cost baselinCUse earned valu
11、e management to monitor performancDEstimate and budget controllable and uncontrollable costs separatel12.In the earned value technique, cost variance is computed as ().AEV minus PVBEV minus ACCAC minus EVDPV minus EV13.All of the following are examples of tools often used in estimate costs EXCEPT ()
12、.Aparametric modelingBanalogous estimatingCbottom-up estimatingDactivity duration estimates14.A project manager needs to analyze the project cost to find ways to decrease costs. It would be BEST if the project manager looks at ().Avariable costs and fixed costsBfixed costs and indirect costCdirect c
13、osts and variable costsDindirect costs and direct costs15.Who is responsive for determining the project cost variance acceptable range ?()AFunctional manageBUpper managemenCThe customeDThe project manage16.Which of the following is not estimate costs tool or technique ?()AHistorical relationshipBAna
14、logouCBottom-uDParametri17.While completing a project a project manager realizes be needs to decrease project costs. After researching his options, he comes up with the following choices. Which choice would DECREASE project costs ?()AChange to component A from component Component A costs more to pur
15、chase but has a lower life cycle cost thanBChange task A to be completed by resource B instead of Resource C, Resource B is a more experienced workeCMove tasks B and H to occur concurrently, and take the risk of a 30% increase in the need for five more resources lateDRemove a test from the project p
16、la18.As a project manager, you examine project results over time to determine how project is performing over time. This can be done through ().Aperformance reviewsBvariance analysisCtrend analysisDearned value management19.Analogous estimating ().Auses bottom-up estimating techniquesBuses the actual
17、 cost of previou similar projects as the basis for estimating the cost of the current projectCis used most frequently in the later stages of a projectDsummarizes estimates for individual work items20.What does cost of quality mean ?()AThe sacrifice of unessential project objectives to meet essential