1、2021PMP资格认证考试考试真题卷(6)本卷共分为1大题50小题,作答时间为180分钟,总分100分,60分及格。一、单项选择题(共50题,每题2分。每题的备选项中,只有一个最符合题意) 1.A manufacturing project has a schedule performance index(SPI)of 0.89 and a cost performance index(CPI)of 0.91Generally,what is the BEST explanation for why this occurred? A) The scope was changed B) A su
2、pplier went out of business and a new one needed to be found C) Additional equipment needed to be purchased D) A critical path activity took longer and needed more labor hours to complete 2.During the completion of work packages,the sponsor asks the project manager to report on how the project is go
3、ingIn order to prepare the report,the project manager asks all the team members what percent complete their work isThere is one team member who has been hard to manage from the beginningIn response to being asked what percent complete he is,the team member asks,“Percent complete of what?”Being tired
4、 of such comments,the project manager reports to the team member's boss that the team member is not cooperatingWhich of the following is likely to be the real problem? A) The project manager did not get buy-in from the manager for the resources on the project B) The project manager did not creat
5、e an adequate reward system for team members to improve their cooperation C) The project manager should have had a meeting with the team member's boss the first time the team member caused trouble. D) The project manager does not have work packages 3.Which is not a goal in both project managemen
6、t and quality management? A) Prevention over inspection B) Customer satisfaction C) Management responsibility D) Triple constraint 4.Which of the following BEST describes the verify scope process? A) It provides assurances that the deliverable meets the specifications,is an input to the project mana
7、gement plan,and is an output of perform quality control B) It ensures that the deliverable is completed on time and gets customer acceptance,and shows that the deliverable meets specifications C) It ensures customer acceptance,shows that the deliverable meets specifications,and provides a chance for
8、 differences of opinion to come to light D) It is an output of perform quality control,occurs beforedefine scope,and ensures customer acceptance 5.A project has the following earned value data assessed:AC=$4000000;CV=$-500000;SPI=1.12;BAC=$9650000What is the earned value of the project? A) $3000000
9、B) $3500000C) $4480000 D) $5650000 6.At the beginning of project execution,you notice different opinions between team members relating to project work and deliverables and to the level of overall complexityWhat should you do right now? A) Give your team members some time to develop a common understa
10、nding of the project scope and product scopeUpcoming interface problems may be resolved later B) Use the risk management processes to identify and assess risks caused by misunderstandings and develop a plan with measures in order to respond to them C) Organize meetings to identify and resolve misund
11、erstandings between team members in order to early avoid interface problems,disintegration and costly rework D) Use interviews in private with each individual team member to inform them of your expectations and your requirements in an atmosphere of confidence 7.Being the project manager in a softwar
12、e project which is currently initiated,you want to assess high level risksWhat should you do? A) Develop a preliminary scope statement and document initially identified risks in this document B) Identify and analyze risk events using qualitative and quantitative techniques C) Develop contingency pla
13、ns and fallback plans in case the original plan proves Wrong D) Discuss the risks documented in your risk register with the project key stakeholders 8.What is not a reason for companies to organize lessons learned? A) Lessons learned databases are an essential element of the organizational process a
14、ssets B) Lessons learned should focus on identifying those accountable for errors and failures C) Lessons learned sessions should bring about recommendations to improve future performance on projects D) Phase-end lessons learned sessions provide a good team building exercise for project staff member
15、s 9.How should change management be planned for? A) Changes are generally not predictable,therefore planning for change management cannot be sensible B) Planning for change management should be done while the various change control processes are being applied C) Change management can be planned in a
16、 set of management plans or a specific change management plan D) Changes are a sign of bad planningOne should avoid changes during a project thus eliminating the need to manage them 10.Which of the following documents is not used as input for product acceptance? A) The project scope statement,it des
17、cribes the acceptance criteria B) The project scope management plan,it describes the acceptance process C) The work breakdown structure(WBS),it describes the deliverables for acceptance D) The RACI matrix,it describes accountabilities in case of product rejection 11.When should lessons learned be or
18、ganized? A) During the project life cycle and at the end B) At the end of the project during closing C) After the end of the project at a project post-mortem meeting D) Lessons learned can be organized when there is time available 12.Understanding of_characteristics of people is not part of understa
19、nding the cultural and social environment A) economic B) individual C) educational D) ethnic and religious 13.The concept of the_states that changes related to one requirement-scope,time or cost will at least influence one other element A) three-point estimation B) triple constraint C) three wise me
20、n D) three needs theory 14.What is the purpose of a project charter? A) To address and document the characteristics and boundaries of the project and its associated products and services B) To formally authorize the project and provide the project manager with the authority to apply organizational r
21、esources C) To link the project,which is going to be planned,executed,and monitored/controlled to the ongoing work of the organization D) To break down the scope of the project into smaller,better manageable components for further planning and estimating 15.At the end of the closing process group,_
22、A) it is verified that the defined processes are completed within all the process groups to close the project phase B) it is determined that the product of the project is completed satisfactorily C) project management plan is written off by the project sponsor D) new change requests are initiated as
23、 required 16.You have recently appointed a project manager to handle a critical project in your organizationYou want to provide the project manager with authority to apply organizational resources to project activitiesWhich document should you use? A) Resource authorization document B) Work breakdow