1、2022内蒙古PMP资格认证考试考试真题卷(9)本卷共分为1大题50小题,作答时间为180分钟,总分100分,60分及格。一、单项选择题(共50题,每题2分。每题的备选项中,只有一个最符合题意) 1.The method of constructing a project schedule network diagram that represents activities and connects then to show the all dependencies is known as_ A) precedence diagramming method B) activity list C
2、) arrow diagramming method D) schedule network templates 2.Which of the following activities is not concerned with developing the project charter? A) Project justification B) Collecting output of the planning processes C) Current understanding of the customers need D) Documenting the business needs
3、3.Which of the following is not a tool of the activity definition process? A) Rolling wave planning B) Control account C) Decomposition D) Templates 4.What is the process for aggregating the estimated costs of individual activities or work packages to establish a cost baseline known as? A) Cost asse
4、ssment B) Determine budget C) Plan contracting D) Cost estimating 5.Out of the following definitions of a project stakeholder,which one do you think is most appropriate? A) An enterprise whose employees are directly involved in doing the project work B) An entity whose interest may be affected as a
5、result of the project execution C) An entity that performs activities to accomplish objectives D) One who is responsible for managing the project 6.In which of the following organizational structures,do project managers have high or total authority? A) Functional organization B) Balanced matrix orga
6、nization C) Matrix organization D) Projectized organization 7.Which of the following is not a tool technique of the develop project charter process? A) Earned value method B) Project selection methods C) Project management information system D) Project management methodology 8.In which phase of the
7、project life cycle,are cost and staffing levels high? A) Intermediate stage B) Final stage C) Pre-intermediate stage D) Initial stage 9.Who is responsible for completing the lessons learned documentation? A) Project team B) Sponsor C) Project architect D) Project manager 10.To manage a project inclu
8、ding_ A) identity the request and make sure the clarity and achievable aim B) balance the request of quality,scope,time and fee C) make the technology regulation explaination,plan and means befit for different requests and expectation of all kinds of stakeholders D) all of above 11.Executing process
9、es are concerned with_ A) recognizing that a project or phase should begin B) coordinating people and other resources to carry out the plan C) devising and maintaining a workable method to accomplish the business need that the project was undertaken to address D) ensuring that the project objectives
10、 are met by monitoring and measuring progress and taking corrective action when necessary 12.For an activity,the optimistic,most likely and pessimistic estimates are 12,16 and 18 respectivelyWhich of the following statement is correct? A) There is 68.26% chance that the activity will be completed in
11、 15 to 17 days B) There is 95.44% chance that the activity will be completed in 15 to 17 days C) There is 68.26% chance that the activity will be completed in 14.67 to 16.67 days D) There is 93.73% chance that the activity will be completed in 15 to 17 days 13.Calculate the standard deviation of a t
12、ask if O=4,P=10,M=6 A) 1 B) 1/3 C) 2/5D) 2/3 14.You are looking at the following dataProject A has a CPI of 0.8 and SPI of 1.2 and EV of 450Project B has CPI of 1.2 and SPI of 0.8 and EV of 650Which of the following statement is true? A) Project B is performing better because it has a higher earned
13、value B) Project A has schedule slippage and project B is ahead of schedule C) Crashing project A is a good option D) Crashing project B is a good option 15.Which of the following is NOT a method for progress reporting for work packages? A) Percent complete B) Fast tracking C) 20/80 ruleD) 50/50 rul
14、e 16.You are the project manager of a large software development projectThere is a conflict between two module leads on where the changes have to be madeYou intervene and tell them the importance of getting the project on time and ask them to find a solution which is acceptable to both of themWhich
15、conflict resolution technique are you using here? A) Confronting B) CompromisingC) Smoothing D) Forcing 17.Based on the net present value(NPV),which project you will choose?The NPV of project A:$25000,project B:$65000,project C:$40000,project D:$35000 A) Project A B) Project B C) Project C D) Projec
16、t D 18.which of the following is the BEST tool for showing the team the project schedule status during project execution? A) Milestone chart B) Gantt chart C) Work breakdown structureD) Network diagram 19.An organization structure that involves various organizational types at various levels is calle
17、d a_ A) strong matrix B) balanced organization C) composite D) balanced matrix 20.Who has the highest cost risk in case of a fixed price contract? A) Buyer B) Seller C) Sponsor D) Team 21.You are in the development phase of a software project and meeting the development team to collect the statusYou
18、 want to show the team members the actual dependencies of different tasksWhich scheduling tool you will be using to explain them(choose the best answer)? A) Milestone chart B) Flow chart C) Network diagram D) Gantt chart 22.Which of the following is NOT an input to monitor and control project work?
19、A) Project management plan B) Enterprise environmental factors C) Change requests D) Performance reports 23.You are the project manager for software development projectThe feasibility study can start any time and takes 1 week and requirement gathering takes 2 weeks which can start only after feasibi
20、lity studyThe design and test plan development can start in parallel after the requirements gatheringTest plan preparation takes 8 weeks followed by a review by the customer and the time estimated for review is 1 weekAfter the review,Test data preparation takes 6 weeksDesign takes 6 weeks and it is
21、followed by development and unit testing,for one module it takes 2 weeks and for the other module it takes 2 weeksThere are no dependencies between modules and they can be developed simultaneouslyAfter test data preparation and development and unit testing of both the modules,there is 2 weeks system
22、 testingWhat is duration of the critical path? A) 14 weeks B) 15 weeks C) 20 weeksD) 19 weeks 24.You are working on a software development project and there is 60% probability that development will be completed by the planned date and 70% probability that testing will be completed by the planned dat