1、2022年内蒙古PMP资格认证考试考试真题卷(6)本卷共分为1大题50小题,作答时间为180分钟,总分100分,60分及格。一、单项选择题(共50题,每题2分。每题的备选项中,只有一个最符合题意) 1.变更请求是以下哪个过程的输出?()A制订项目管理计划B实施整体变更控制C规划风险管理D规划采购2.You are in the process of developing options,and determining actions to enhance opportunities and reduce threats to the projects objectivesWhat should
2、 you be doing next ?()ADetermining which risks might affect the project and documenting their characteristicsBIdentifying,analyzing and planning for newly arising risksCDeciding how to approach and conduct risk management activities for the projectDAssessing the priority of identified risks using th
3、eir probability of occuring3.Due to lack of employee training and proper production controls, defects in a production run caused rework which cost the company $ 250000. How much of this cost is directly attributable to the employees on the production line ?()A$75000B$37500C$212500D$145004.What is th
4、e purpose of the work breakdown structure (WBS)?()AThe WBS allows the project managers to delegate responsibility of all of the project activitiesBThe WBS is a narrative description of the work required for the projectCThe WBS describes the total program as a summation of subdivided elementsDThe WBS
5、 is a statement of what will be made, how many units will be made, and when they will be made5.You are assigned to be the project manager in the middle of the project. The project is within tolerances for the baseline, but the customer is not happy with the performance of the project. What is the FI
6、RST thing you should do ?()ADiscuss it with the project teamBRecalculate baselinesCRenegotiate the contractDMeet with the customer6.Of the following conflict management approaches, which is believed to lead to the LEAST enduring positive results ?()AProblem solvingBAvoidanceCCompromiseDForcing7.You
7、are the project manager of a new project, which will construct a bridge on the River Nile in Egypt. Before initiating the project, you should ().Acreate a scope management plan to document:how the project scope will be defined, verified and controlledBdevelop a project management planCdetermine spec
8、ific activities that need to be performed to produce the various project deliverablesDfacilitate the formal authorization to start a new project8.Estimate at completion(EAC) is ().Aactual cost(AC)+budgeted cost(BC)Bactual cost(AC)+estimate to complete(ETC)Cbudgeted cost(BC)-actual cost(AC)Dactual co
9、st(AC)-planned value(PV)9.Which of the following is NOT an input to perform integrated change control ?()AProject management planBRequested changesCProject scope statementDWork performance information10.项目经理在会见员工时,不管自己多么忙,多么疲劳,都一定要聚精会神、一丝不苟地与员工交谈,使每个员工都感觉到自己被重视。根据上述内容,可以判断以下描述都是正确的,除了()。A项目经理的有效沟通可以
10、缩小上下级之间权力距离B清楚地了解每一个团队成员的需求和期望是项目经理的职责C项目经理在会见员工时应该充分使用自己的职位权力D项目团队成员可以跨越直接上级与项目经理直接沟通11.以下哪个方法涉及把本项目计划要采取的做法与其他项目的做法进行比较,来识别最佳做法,形成改进意见?()A实验设计B标杆对照C过程改进D统计抽样12.在下列哪一种组织结构中,项目成员在收尾阶段最感到忧心忡忡?()A职能型B矩阵型C项目型D弱矩阵型13.In your project, you have started doing human resource planning and are studying the in
11、terpersonal relationships among the candidates who are being considered for the project team. Some factors you consider include: What type of formal and informal reporting relationships exist amongst the candidates for the project team What are the candidates job descriptions What are the supervisor
12、-subordinate relationships What cultural or language differences will affect working relationship between team members What levels of trust and respect currently exist All this information will be available as part of ().Aenterprise environmental factorsBorganization hierarchyCinformal reporting rel
13、ationshipsDall of the above14.Your technical team leader, Ted, proposed an action that would overall project quality with a minor cost increase. The project control officer, Sun Ha, recommended an approach that would shorten the project schedule, but reduce product features. Increasing quality and a
14、ccelerating the schedule are critical form your point of view. Although you believe that Ted and Sun Ha could learn from each other, they typically like to agree to disagree. You need a conflict resolution method that provides a long-term resolution. You decide to use which one of the following appr
15、oaches ?()AConfrontingBProblem solvingCCompromiseDSmoothing15.All of the following is true for a project baseline EXCEPT ().Ait is the original approved planBit includes approved scope changesCit is useful in detecting project variancesDit is useful in preparing the WBS16.Due to cuts in funding, you
16、r project has been terminated. The scope verification process ().Ashould be delayed until the project is completedBshould determine the correctness of the work resultsCshould establish and document the level and extent of completionDwill form the basis of the project audit17.以下都是质量保证的目的,除了()。A提高项目干系
17、人对项目将要达到质量要求的信心B进行过程持续改进,减少非增值活动C消除导致质量不合格的原因D重新评价质量标准,确保质量标准的可行性18.None of the people on your 15 person project team have worked together before, and it really shows. The team cannot seem to get past the storming stage: each meeting is characterized by disagreements, debates, and long-winded exposi
18、tions some of the more verbose members of the group. Everyone seems to speak a different “language” even though they are all from the same country. Conflicts are rampant. You need to get this situation under control quickly. Therefore, the first action you should take is to ().Ahold periodic group m
19、eetingsBuse a group facilitator at the next meetingCperform careful project planningDenforce strict rules about meeting behavior19.What is sometimes referred to as global illiteracies ?()AThe ability to read reports written in many different languagesBThe ability to succeed in a cross cultural envir
20、onmentCThe ability to develop intenationally accepted contractsDThe ability to communicate using drawings and pictograms which are understood all over the world20.在项目即将进入收尾阶段时,你发现了一项原来没有考虑到的新风险。该风险一旦发生,可能给最终的可交付成果带来重要影响,甚至可能使其不能通过客户验收。你应该()。A把该风险的影响通知管理层和客户B进行定性风险分析C制定风险缓解措施D增加应急储备21.你所在的公司采用职能型组织结构