1、文献翻译Traditional Construction Procedures As mentioned before, construction under the traditional construction procedure is performed by contractors. While they would like to satisfy the owner and the building designers, contractors have the main objective of making a profit. Hence, their initial task
2、 is to prepare a bid price based on an accurate estimate of construction costs. This requires development of a concept for performance of the work and a construction time schedule. After a contract has been awarded, contractors must furnish and pay for all materials, equipment, power, labor, and sup
3、ervision required for construction. The owner compensates the contractors for construction costs and services. A general contractor assumes overall responsibility for construction of a building. The contractor engages subcontractors who take responsibility for the work of the various trades required
4、 for construction. For example, a plumbing contractor installs the plumbing, an electrical contractor installs the electrical system, and an elevator contractor installs elevators. Their contracts are with the general contractor, and they are paid by the general contractor. Sometimes, in addition to
5、 a general contractor, the owner contracts separately with specialty contractors, such as electrical and mechanical contractors, who perform a substantial amount of the work require for a building. Such contractors are called prime contractors. Their work is scheduled and coordinated by the general
6、contractor, but they are paid directly by the owner. Sometimes also, the owner may use the design-build method and award a contract to an organization for both the design and construction of a building. Such organizations are called design-build contractors. One variation of this type of contract is
7、 employed by developers of groups of one-family homes or low-rise apartment buildings. The home builder designs and constructs the dwellings, but the design is substantially completed before owners purchase the homes. Administration of the construction procedure often is difficult. Consequently, som
8、e owners seek assistance from an expert, called a professional construction manager, with extensive construction experience, who receives a fee. The construction manager negotiates with general contractors and helps select one to construct the building. Managers usually also supervise selection of s
9、ubcontractors. During construction, they help control costs, expedite equipment and material deliveries, and keep the work on schedule. In some cases, instead, the owner may prefer o engage a construction program manager, to assist in administrating both design and construction. Construction contrac
10、tors employ labor that may or may not be unionized. Unionized craftspeople are members of unions that are organized by construction trades, such as carpenter, plumber, and electrician unions, Union members will perform only the work assigned to their trade. During construction, all work should be in
11、spected. For this purpose, the owner, often through the architect and consultants, engages inspectors. The field inspectors may be placed under the control of an owners representative, who may be titled clerk of the works, architects superintendent, engineers superintendent, or resident engineer. Th
12、e inspectors have the responsibility of ensuring that construction meets the requirements of the contract documents and is performed under safe conditions. Such inspections may be made at frequent intervals. In addition, inspections also are made by representatives of one or more governmental agenci
13、es. They have the responsibility of ensuring that construction meets legal requirements and have little or no concern with detailed conformance with the contract documents. Such legal inspections are made periodically or at the end of certain stages of construction. One agency that will make frequen
14、t inspections is the local or state building department, whichever has jurisdiction. The purpose of these inspections is to ensure conformance with the local or state building code. Following is a description of the basic traditional construction procedure for a multistory building.After the award o
15、f a construction contract to a general contractor, the owner may ask the contractor to start a portion of the work before signing of the contract by giving the contractor a letter of intent or after signing of the contract by issuing a written notice to proceed. The contractor then obtains construct
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 传统的施工程序 毕业论文外文翻译 传统 施工 程序 毕业论文 外文 翻译
![提示](https://www.taowenge.com/images/bang_tan.gif)
限制150内