土石坝的评估和修复毕业设计外文翻译.doc
《土石坝的评估和修复毕业设计外文翻译.doc》由会员分享,可在线阅读,更多相关《土石坝的评估和修复毕业设计外文翻译.doc(12页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、附录一 外文翻译英文原文Assessment and Rehabilitation of Embankment DamsNasim Uddin, P.E., M.ASCE1Abstract: A series of observations, studies, and analyses to be made in the field and in the office are presented to gain a proper understanding of how an embankment dam fits into its geologic setting and how it in
2、teracts with the presence of the reservoir it impounds. It is intended to provide an introduction to the engineering challenges of assessment and rehabilitation of embankments, with particular reference to a Croton Dam embankment.DOI: 10.1061/(ASCE)0887-3828(2002)16:4(176)CE Database keywords: Rehab
3、ilitation; Dams, embankment; Assessment.Introduction Many major facilities, hydraulic or otherwise, have become very old and badly deteriorated; more and more owners are coming to realize that the cost of restoring their facilities is taking up a significant fraction of their operating budgets. Reha
4、bilitation is, therefore, becoming a major growth industry for the future. In embankment dam engineering, neither the foundation nor the fills are premanufactured to standards or codes, and their performance correspondingly is never 100% predictable. Dam engineeringin particular, that related to ear
5、th structureshas evolved on many fronts and continues to do so, particularly in the context of the economical use of resources and the determination of acceptable levels of risk. Because of this, therefore, there remains a wide variety of opinion and practice among engineers working in the field. Ma
6、ny aspects of designing and constructing dams will probably always fall within that group of engineering problems for which there are no universally accepted or uniquely correct procedures.In spite of advances in related technologies, however, it is likely that the building of embankments and theref
7、ore their maintenance, monitoring, and assessment will remain an empirical process. It is, therefore, difficult to conceive of a set of rigorousassessment procedures for existing dams, if there are no design codes. Many agencies (the U.S. Army Corps of Engineers, USBR, Tennessee Valley Authority, FE
8、RC, etc.) have developed checklists for field inspections, for example, and suggested formats and topics for assessment reporting. However, these cannot be taken as procedures; they serve as guidelines, reminders, and examples of what to look for and report on, but they serve as no substitute for an
9、 experienced, interested, and observant engineering eye. Several key factors should be examined by the engineer in the context of the mandate agreed upon with the dam owner, and these together with relevant and appropriate computations of static and dynamic stability form the basis of the assessment
10、. It is only sensible for an engineer to commit to the evaluation of the condition of, or the assessment of, an existing and operating dam if he/she is familiar and comfortable with the design and construction of such things and furthermore has demonstrated his/her understanding and experience. Reha
11、bilitation Measures The main factors affecting the performance of an embankment dam are (1)seepage; (2)stability; and (3) freeboard. For an embankment dam, all of these factors are interrelated. Seepage may cause erosion and piping, which may lead to instability. Instability may cause cracking, whic
12、h, in turn, may cause piping and erosion failures. The measures taken to improve the stability of an existing dam against seepage and piping will depend on the location of the seepage (foundation or embankment), the seepage volume, and its criticality. Embankment slope stability is usually improved
13、by attening the slopes or providing a toe berm. This slope stabilization is usually combined with drainage measures at the downstream toe. If the stability of the upstream slope under rapid drawdown conditions is of concern, then further analysis and/or monitoring of resulting pore pressures or modi
14、cations of reservoir operationsmay eliminate or reduce these concerns. Finally, raising an earth ll dam is usually a relatively straightforward ll placement operation, especially if the extent of the raising is relatively small. The interface between the old and new lls must be given close attention
15、 both in design and construction to ensure the continuity of the impervious element and associated filters. Relatively new materials, such as the impervious geomembranes and reinforced earth, have been used with success in raising embankment dams. Rehabilitation of an embankment dam, however, is rar
16、elyachieved by a single measure. Usually a combination of measures, such as the installation of a cutoff plus a pressure relief system, is used. In rehabilitation work, the effectiveness of the repairs is difficult to predict; often, a phased approach to the work is necessary, with monitoring and in
17、strumentation evaluated as the work proceeds. In the rehabilitation of dams, the security of the existing dam must be an overriding concern. It is not uncommon for the dam to have suffered significant distressoften due to the deficiencies that the rehabilitation measures are to address.The dam may b
18、e in poor condition at the outset and may possibly be in a marginally stable condition. Therefore, how the rehabilitation work may change the present conditions, both during construction and in the long term, must be assessed, to ensure that it does not adversely affect the safety of the dam. In the
19、 following text, a case study is presented as an introduction to the engineering challenges of embankment rehabilitation, with particular reference to the Croton Dam Project.Case Study The Croton Dam Project is located on the Muskegon River in Michigan. The project is owned and operated by the Consu
20、mer Power Company. The project structures include two earth embankments, a gated spillway, and a concrete and masonry powerhouse. The earth embankments of this project were constructed of sand with concrete core walls. The embankments were built using a modified hydraulic fill method. This method co
21、nsisted of dumping the sand and then sluicing the sand into the desired location. Croton Dam is classified as a high-hazard dam and is in earthquake zone 1. As part of the FERC Part 12 Inspection (FERC 1993), an evaluation of the seismic stability was performed for the downstream slope of the left e
22、mbankment at Croton Dam. The Croton Dam embankment was analyzed in the following manner. Soil parameters were chosen based on standard penetration (N) values and laboratory tests, and a seismic study was carried out to obtain the design earthquake. Using the chosen soil properties, a static finite-e
23、lement study was conducted to evaluate the existing state of stress in the embankment. Then a one-dimensional dynamic analysis was conducted to determine the stress induced bythe design earthquake shaking. The available strength was compared with expected maximum earthquake conditions so that the st
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 土石坝的评估和修复 毕业设计外文翻译 土石 评估 修复 毕业设计 外文 翻译
限制150内