1、外文翻译Rapid construction of the embankment dam1Overview Also known as the embankment dam dam local materials, the necessary soil in situ stone mining in general, but can also make full use of the excavated material, having to basic requirements, low deformation based on the character filling construct
2、ion and can be divided into RCC-grade. Fill-rockfill dam, directional blasting rockfill dam, the hydraulic fill dams hydro-filled dam and masonry dam in different ways. Parabolic which administered rockfill dam no longer, directional blasting rockfill dam late settlement exist, not be planted within
3、 the dam prototype observation equipment shortage, which are rarely used, hydraulic fill dams. Fill the water main in a special area of the lower dam height of the small and medium projects, the masonry dam strictly speaking belongs masonry dam category. At present, the extensive use of thin section
4、s and the hierarchical compaction roller compacted embankment dam.2 The need for rapid construction With the dam construction technology concrete gravity dam dam the technology continues to improve, while the rubber dam and other new dam-constant use there is a traditional embankment dam filling a l
5、arge quantity of a long time to build the shortcomings become extremely prominent, how to fully exploit the technology itself embankment dam low, right foundation adaptability, full use of local materials to the traditional advantages to speedup the construction schedule, as Pa-an important option.
6、Filling in ensuring the quality of construction and safe operation of the rapid construction premise is that the parties are concerned. 2.1 Based on the uncertainty the need to accelerate the progress of measures With the hydropower development progress in basic bad place to build a large embankment
7、 dams, in order to meet the capacity and infrastructure foundation impervious to the needs, often based on the completion of treatment can only be reclaimed after construction, however, foundation of a more complicated, especially in deep-cover construction projects, infrastructure projects are larg
8、e, unpredictable factors, often need cutoff Vibroflotation, curtain grouting, grouting consolidation of the foundation for the integrated treatment, handling difficult and complex examination. Based on the number of projects foundation treatment completion and handover of face time is often more wor
9、k plan by the time lag. Filling started causing delay and the next gate or the completion of water storage often not be adjusted, resulting in an effective filling time. Construction units have had to resort to quick construction of measures will be scheduled according to the contract (or even ahead
10、 of ) completion of the project.2.2 Hydro-meteorological filling intensity of the proposed new standards Embankment dam of the hydro-meteorological factors are extremely sensitive and in the rainy season, soil moisture greatly influenced, directly restricts dam reclamation, construction intensity wi
11、ll be affected; winter, the soil on the cold and if it does not take active measures is impossible to filling and filling winter rainy season, there is a high input, low output of the predicament. Construction units are often reluctant to assume, therefore, take full advantage of filling the “golden
12、 season,” try to avoid winter construction of the rainy season (or reduce the amount of filling winter rainy season), the construction unit is the first choice of the relative, the “golden season,” filling the quantity of work is often very substantial. Rapid construction can be avoided winter rainy
13、 season generous amount of filling the most important issue.2.3 New Construction equipment and materials massive expansion of the scope of application is the basis for rapid construction With the improvement in the degree of mechanization, large capacity of earth and equipment used in construction i
14、mproved ergonomics, thus laid for the rapid construction of the necessary material foundation for the formation of materials to expand the scope of application. The original dam material unsuitable materials can also be used as filling material, this rapid filling of the embankment dam with a new pi
15、llar.3 Field data mining Yard of the embankment dam importance is self-evident, it is also most likely to affect the smooth filling of the dam weaknesses, according to engineering practice. Generally, the material yard depth of geological exploration work is far less dam, especially the largest volu
16、me filling of rockfills. Several exploratory often alone or topographic survey conducted geological description of the venue ,and changes in the tender documents is a great possibility, or geological conditions undergone major changes, tender documents into useful information useless information, or
17、 mining area is smaller, to create large-scale mining (or stairs mining)is not conducive to large-scale mining machinery. Can directly control dam Regular filling, grading sound, but also can affect the dam fast filling the key In impermeable soil, the water level of the dam could also become the ke
18、y to rapid filling, therefore, sound and carefully reviewed for yard work and rehabilitation investigation it is particularly important to do a good job yard rechecking and reserve calculation, be aware of. If those conditions for the best in the dam filling part of the former reserves expected to p
19、eak lowering finished Pinggu.3.1 Road Construction To meet the need for rapid construction of a large number of machinery and equipment investment is inevitable. At present, more and more vehicles to transport large tonnage trends, the number of transport vehicles also require a corresponding increa
20、se on the road increasingly high demand, the practice has proven that better roads, transport vehicles higher attendance. Filling a corresponding increase efficiency the saying goes, “is the road repair, road construction is progress” is the reason, General projects have adopted the mud stone paveme
21、nt, if those conditions for the local traffic is heavy use lots of concrete pavement, will greatly improve transport efficiency on the road layout, as far as the actual layout of the Central Bank into a two-lane, vehicles to avoid interference and improve the efficiency of cycling.3.2 Rapid construc
22、tion of the main methods and attention to the matter Completed all the preparations have reclaimed conditions, the construction units, as planned dam filling. Strengthen the convergence process reduce intermediate links, is the rapid construction of the highest priority.3.2.1 Reasonable zoning routi
23、ne dam filling work is the key to rapid constructionBecause it was larger than the embankment dam for the dam surface area routine provided the necessary scenes, generally be divided into processes Shop filling materials, paving, watering and compaction quality control, etc. If impermeable soil surf
24、ace planning will be conducted hair, according to the actual situation, the Section will be divided into several processes with a few. If Section few equal to the number of manufacturing processes, people, machines, not idle; If the number is greater than Section several processes, people, planes id
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 土石坝的施工 毕业论文外文翻译 土石 施工 毕业论文 外文 翻译
![提示](https://www.taowenge.com/images/bang_tan.gif)
限制150内