毕业论文外文翻译-桥梁工程(箱梁).doc
《毕业论文外文翻译-桥梁工程(箱梁).doc》由会员分享,可在线阅读,更多相关《毕业论文外文翻译-桥梁工程(箱梁).doc(20页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、 毕业设计外文资料翻译 第20页外文资料原文:13Box girders13.1 GeneralThe box girder is the most exible bridge deck form. It can cover a range of spans from 25 m up to the largest non-suspended concrete decks built, of the order of 300 m. Single box girders may also carry decks up to 30 m wide. For the longer span beams,
2、 beyond about 50 m, they are practically the only feasible deck section. For the shorter spans they are in competition with most of the other deck types discussed in this book.The advantages of the box form are principally its high structural efciency (5.4), which minimises the prestress force requi
3、red to resist a given bending moment, and its great torsional strength with the capacity this gives to re-centre eccentric live loads, minimising the prestress required to carry them.The box form lends itself to many of the highly productive methods of bridge construction that have been progressivel
4、y rened over the last 50 years, such as precast segmental construction with or without epoxy resin in the joints, balanced cantilever erection either cast in-situ or coupled with precast segmental construction, and incremental launching (Chapter 15).13.2 Cast-in-situ construction of boxes13.2.1 Gene
5、ralOne of the main disadvantages of box decks is that they are difcult to cast in-situ due to the inaccessibility of the bottom slab and the need to extract the internal shutter. Either the box has to be designed so that the entire cross section may be cast in one continuous pour, or the cross secti
6、on has to be cast in stages.13.2.2 Casting the deck cross section in stagesThe most common method of building box decks in situ is to cast the cross section in stages. Either, the bottom slab is cast rst with the webs and top slab cast in a second phase, or the webs and bottom slab constitute the rs
7、t phase, completed by the top slab.When the bottom slab is cast rst, the construction joint is usually located just above the slab, giving a kicker for the web formwork, position 1 in Figure 13.1. A joint in this location has several disadvantages which are described in 11.7.1Figure 13.1 Alternative
8、 positions of construction jointAlternatively, the joint may be in the bottom slab close to the webs, or at the beginning of the haunches, position 2. The advantages of locating the joint in the bottom slab are that it does not cross prestressing tendons or heavy reinforcement; it is protected from
9、the weather and is also less prominent visually. The main disadvantage is that the slab only constitutes a small proportion of the total concrete to be cast, leaving a much larger second pour.The joint may be located at the top of the web, just below the top slab, position 3. This retains many of th
10、e disadvantages of position 1, namely that the construction joint is crossed by prestressing ducts at a shallow angle, and it is difcult to prepare for the next pour due to the presence of the web reinforcement. In addition, most of the difculty of casting the bottom slab has been re-introduced. The
11、 advantages are that the joint is less prominent visually and is protected from the weather by the side cantilever, the quantity of concrete in each pour is similar and less of the shutter is trapped inside the box.Casting a cross section in phases causes the second phase to crack due to restraint b
12、y the hardened concrete of the rst phase. Although the section may be reinforced to limit the width of the cracks, it is not desirable for a prestressed concrete deck to be cracked under permanent loads. Eliminating cracks altogether would require very expensive measures such as cooling the second p
13、hase concrete to limit the rise in temperature during setting or adopting crack sealing admixtures13.2.3 Casting the cross section in one pourThere are two approaches to casting a box section in one pour. The bottom slab may be cast rst with the help of trunking passing through temporary holes left
14、in the soft form of the top slab. This requires access for labourers to spread and vibrate the concrete, and is only generally possible for decks that are at least 2 m deep. The casting of the webs must follow on closely, so that cold joints are avoided. The uidity of the concrete needs to be design
15、ed such that the concrete will not slump out of the webs. This is assisted if there is a strip of top shutter to the bottom slab about 500 mm wide along each web. This method puts no restriction on the width of the bottom slab, Figure 13.2 (a).Alternatively the deck cross section may be shaped so th
16、at concrete will ow from the webs into the bottom slab, which normally has a complete top shutter, Figure 13.2 (b). This method of construction is most suitable for boxes with relatively narrow bottom anges. The compaction of the bottom slab concrete needs to be effected by external vibrators, which
17、 implies the use of steel shutters. The concrete may be cast down both webs, with inspection holes in the shutter that allow air to be expelled and the complete lling of the bottom slab to be conrmed. Alternatively, concrete may be cast down one web rst with the second web being cast only when concr
18、ete appears at its base, demonstrating that the bottom slab is full. The concrete mix design is critical and full-scale trials representing both the geometry of the cross section and density of reinforcement and prestress cables are essential.Figure 13.2 Casting deck in one pourHowever the section i
19、s cast, the core shutter must be dismantled and removed through a hole in the top slab, or made collapsible so it may be withdrawn longitudinally through the pier diaphragm.Despite these difculties, casting the section in one pour is under-used. The recent development of self-compacting concrete cou
20、ld revolutionise the construction of decks in this manner. This could be particularly important for medium length bridges with spans between 40 m and 55 m. Such spans are too long for twin rib type decks, and too short for cast-in-situ balanced cantilever construction of box girders, while a total l
21、ength of box section deck of less than about 1,000 m does not justify setting up a precast segmental facility. Currently, it is this type of bridge that is least favourable for concrete and where steel composite construction is found to be competitive.13.3 Evolution towards the box formChapters 11 a
22、nd 12 described how solid slabs evolve into ribbed slabs in order to allow increased spans with greater economy. The principal advantage of ribbed slabs is their simplicity and speed of construction. However this type of deck suffers from several disadvantages, notably: the span is limited to about
23、45 m; live loads are not efciently centred, resulting in a concentrated load (such as an HB vehicle) being carried approximately 1.7 times for a deck with two ribs, requiring additional prestress force; the section has poor efciency, leading to the requirement for a relatively larger prestress force
24、; the deck cannot be made very shallow; the piers need either multiple columns to carry each rib, or a crosshead that is expensive and visually very signicant.Box section decks overcome all these disadvantages.13.4 Shape and appearance of boxes13.4.1 GeneralA box section deck consists of side cantil
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 毕业论文 外文 翻译 桥梁工程 箱梁
限制150内