1、精品资料APQP(全英文版).Advanced Product Quality Planning1 PurposeIn order to develop and produce a new product that meets the customers quality requirements, systematic advanced quality planning is required. The Advanced Product Quality Planning procedure (APQP) accompanies the development of a product and
2、is intended to ensure that the supplier meets all of the customers requirements on time. 2 ResponsibilityThe supplier is fully responsible for the timely planning, execution and documentation of all activities carried out within the framework of Advanced Product Quality Planning (APQP). He specifies
3、 persons in his organization who are responsible for the individual activities and stipulates the corresponding deadlines. On the customers side, the technical departments (depending on their area of responsibility) or designated project supervisors are responsible for cooperation with the supplier.
4、 In order that development activities can be carried out, it is necessary to define the targets for the project and the communication channels between the parties involved (customer, supplier and subcontractors). To ensure continuous monitoring of the project and adherence to the deadlines specified
5、 by the customer, the supplier must set milestones at which the defined activities must be completed. 3 Project classification and requirementsThe demands on Advanced Product Quality Planning are divided up into three different project classifications (PE) by the customer, based on the risk involved
6、:Standard requirement Simplified project work (e. g. time scheduling) Project discussion(s) where required Sampling Process review/process audit on site, where requiredMedium requirement Project work in acc. with APQP method APQP Status Reports Project discussion(s), where required Sampling Process
7、review/process audit on site, where requiredMaximum requirement Project work in acc. with APQP method APQP Status Reports (increased number) Project Review(s) Sampling Process review/process audit on-sitePE 3Standard productPE 2Medium riskPE 1Increased riskThe supplier is informed of the project cla
8、ssification when the order is issued, at the latest. The customer may change the project classification during the course of the project as a result of unforeseen circumstances. Should any requirements change during the course of the project, all affected documents, e. g. Control Plan, FMEA, process
9、 flow diagram etc., must be changed accordingly. 3.1 Project classification PE 1 Increased riskThe supplier reports to the designated customer contact on his own responsibility using the APQP Status Report (see QAA Part 1, Appendix 3): No later than four weeks after order confirmation At initial mas
10、s production sampling In good time in the event of problems (APQP status of an element is yellow“ or red“) On additional dates which have been agreed between customer and supplier on an individual basis within the framework of the project work.The customer checks the progress of the project during p
11、roject reviews held at either the suppliers premises or the customers premises. Documents such as the Control Plan, FMEA, process flow chart etc. must be submitted as evidence. The customer releases the mass production process after carrying out a process review/audit at the suppliers premises and,
12、where necessary, at the subcontractors premises. The date and scope of the on-site inspection are agreed between supplier and customer within the framework of the APQP. 3.2 Project classification PE 2 Medium riskThe supplier reports to the designated customer contact on his own responsibility using
13、the APQP Status Report (see QAA Part 1, Appendix 3): No later than four weeks after order confirmation At initial mass production sampling In good time in the event of problems (APQP status of an element is yellow“ or red“)The customer can check the progress of the project during project reviews hel
14、d at either the suppliers premises or the customers premises. Documents such as the Control Plan, FMEA etc. must be submitted as evidence. The customer can release the mass production process after carrying out a process review/audit at the suppliers premises and, where necessary, at the subcontract
15、ors premises. The date and scope of the on-site inspection are agreed between supplier and customer within the framework of the APQP.3.3 Project classification PE 3 Standard productThe supplier reports to the designated customer contact on an informal basis (without the use of the APQP Status Report
16、): In good time in the event of problemsThe customer can check the progress of the project during project discussions held at either the suppliers premises or the customers premises. Documents such as the Control Plan, FMEA etc. must be submitted as evidence.4 Monitoring project progressThe supplier
17、 must monitor the progress of the project independently and report to the customer on the basis of the project classification. In order to plan the project and monitor dates, the target dates for the individual APQP elements must be entered in the APQP Status Report at the start of the project. The
18、actual dates are entered to document the completion of the elements. If the date or individual elements are at risk of not being fulfilled, the supplier must introduce suitable corrective measures and monitor these on his own responsibility. A further course of action must be agreed jointly with the
19、 customer. The status of the individual elements must be indicated in the APQP Status Report using the following colour codes: StatusMeaningeen Date / quality of the element are not at risk Start of production is not at riskYellow Date / quality of the element are at risk Start of production is not
20、at risk Appropriate corrective measures and responsible persons must be definedRed Date / quality of the element will not be observed Start of production is at risk Appropriate corrective measures and responsible persons must be defined and agreed with the customer5 Product development processThe pr
21、oduct development process (PEP) consists of consecutive phases that are separated by milestones. The current status of the project is reviewed when a milestone is reached. Additional activities must then be defined where necessary. The procedure proposed by the customer is shown in Appendix 1 and re
22、presents the foundation for handling the project on a joint and structured basis.In specific cases, e. g. in the case of complex systems or at the request of the end customer, the customer can take the procedure VDA (Verband der Automobilindustrie) volume New Part Maturity Level Assuredness as a bas
23、e and agree this with the supplier.6 Applicable documentsApplicable appendices to S 296001 Part 1 (see www.Schaeffler.de / Suppliers / Quality / Production Material)Appendix 1 Product Development ProcessAppendix 2 APQP ElementsAppendix 3 APQP Status ReportAppendix 4 Feasibility ConfirmationAppendix 5 Capacity ConfirmationApplicable customer-specific standardS 102012-1 Classification of characteristics / Special required documentation