1、 Contract for Exporting Mining Equipment Contract No. _ This Contract is made and entered into on the 15th,Oct. in Sulaiminiyh by and between Mass Iraq Cement Co,Ltd ( as the Buyer) and China Jiangsu Grand Economic Devolpment Co.,Ltd. a company incorporated under the laws of China(hereinafter referr
2、ed to as the seller). Whereas, the Buyer desires to engage the Seller to provide the Mining Equipment, all related design, technical document, technical service and technical training and to obtain from the Seller a license of know- how and other technical information in relation with the Equipment
3、s design, erection, commissioning, operation and maintenance. Now it is hereby mutually agreed as follows: Article 1 Definitions1.1 “ Acceptance ” means the Buyer accepted the Equipment in accordance with Article xx. 1.2 “ Commissioning” means the operation of the Equipment in accordance with Articl
4、e 9.4 for the purpose of carrying out Performance Test.1.3 “ Contract” means this Contract signed by and between the Buyer and the Seller, including Appendices attached which shall form an integral part of this Contract.1.4 “ Effective Date of the Contract” means the date when the Contract enters in
5、to force upon fulfillment of all the conditions stated in Article 16.1.1.5 “ Equipment ” means the equipment, machinery, instruments, spare parts and materials supplied by the Seller as listed in Appendix 3.1.6 “ Erection” means the installation of the Equipment including placing and connecting part
6、s to their positions according to the design drawing.1.7 “ Job Site” means the site where the Equipment shall be located and/or erected, namely Mass Iraq Cement Plant.1.8 “ Last Shipment ” means the shipment with which the accumulated invoice value of shipped goods has reached 100 percent of the tot
7、al the Equipment price.精选学习资料 - - - - - - - - - 名师归纳总结 - - - - - - -第 1 页,共 19 页1.9 “ Performance Test ” means the tests for examining whether the Equipment is able to meet guarantee figures . 1.10 “ Technical Document ” means the technical indices, specifications, drawings, manual and instructions
8、related to the design, erection, test-run, commissioning, acceptance, operation and maintenance of the Equipment to be provided by the Seller.1.11 “ Technical Service” means the technical instruction, assistance and guidance rendered by the Seller. 1.12 “ Technical Training ” means the training rend
9、ered by the Seller.1.13 “ Test Run ” means the initial run of a single machine or the whole system of the Equipment without materials.1.14 “ Warranty Period ” means the period of the warranty given by the Seller as specified in Article 10.2, during which the Seller is responsible for the defects of
10、the Equipment as per Article 10.Article 2 Scope of the Contract2.1 The Seller s Obligation2.1.1 The Seller shall supply the Equipment and spare parts, provide the design, Technical Document, and conduct the Technical Service and Technical Training, and grant a non-exclusive and non-transferable righ
11、t to use the know-how and other technical information related to the Equipment s design, Erection, Commission, operation and maintenance. 2.1.2 The Seller shall procure and supply the Equipment and spare parts which is listed in Appendix , the specification is detailed in Appendix . 2.1.3 The Seller
12、 shall provide design in respect to the Equipment and submit to the Buyer the Technical Document .2.1.4 The Seller shall conduct the Technical Services at the Job Site.精选学习资料 - - - - - - - - - 名师归纳总结 - - - - - - -第 2 页,共 19 页2.1.5 The Seller shall conduct the Technical Training of the Buyer s traine
13、es as per Appendix .2.1.6 The Seller agrees to grant non-exclusive and non-transferable right to use the know-how, other technical information related to the Equipment s design, Erection, Commission, operation and maintenance free of charge, which the Seller provides and discloses to the Buyer durin
14、g the implementation of the Contract period.2.2 The Buyer s Obligation2.2.1 The Buyer shall at his own costs and expenses, provide the Seller with all information and data concerning the design as per Appendix. The Buyer shall ensure the correctness and exactitude of all such information and data.2.
15、2.2 The Buyer shall at his own costs and expenses, obtain all necessary import permits, undertake customs clearance, take delivery of the Equipment to be supplied by the Seller and transport them from port to the Job Site in time.2.2.3 The Buyer shall at his own costs and expenses, perform all the c
16、ivil works, construction, Erection, Test Run and Commissioning in accordance with the Technical Document and under the Technical Services rendered by the Seller.2.2.4 The Buyer shall at his own costs and expenses, perform necessary administration and security guard at the Job Site.Article 3 Price 3.
17、1 The Buyer agrees to pay the total Contract price to the seller, Technical Training and Service fee is free .3.2 The total Contract price, including price of the Equipment, design and Technical Document, shall be _. The breakdown is as follows: The price for Equipment is _. Fee for design is _. Fee
18、 for Technical Document is _.3.2.1 The total Contract price for the Equipment is for delivery CIFShanghai. CIFterm is in 精选学习资料 - - - - - - - - - 名师归纳总结 - - - - - - -第 3 页,共 19 页accordance with INTERNA TIONAL RULES OF THE INTERPRETATION OF TRADE TERMS (INCOTERMS), 2000 edition, issued by the INTERNA
19、TIONAL CHAMBER OF COMMERCE (ICC).3.2.2 The total Contract price includes the price for spare parts listed in Appendix . However, the total Contract price also cover the supply of any other spare parts used in the Mining construction . At the Buyer s request, the Seller may provide with any other spa
20、re parts. A separate agreement will be signed between two parties.3.2.3 The above price is fixed and firm.3.3 The total Contract price cover the Technical Service fee and Technical Training fee.Article 4 Payment 4.1 Down PaymentAfter signing the Contract, the Buyer shall pay 30% percent of the each
21、equipment Contract price by T/T to the Seller when the seller is finished the indent with the factor and inform the Buyer.4.2 The balance of the total Contract price amounting _ ( says _ only ) shall paid by a confirmed irrevocable Letter of Credit at sight, issued within 20 days after signing the C
22、ontract by a reputable bank and acceptable to the Seller s Bank in favor of the Seller. The Letter of Credit shall be available upon the presentation of the following documents:4.2.1 For 70 percent of the total Contract price amounting _ (say _ only) at delivery: (a) Bill of Lading in one original.(
23、b) Commercial Invoice in three originals (c) Packing list in one original(s) and two copies (d) Certificate of Origin in one original(s) and two copies (e) Insurance Policy in one original(s) and two copies4.3 All the banking charges incurred in the Seller s bank shall be born by the Seller while th
24、ose incurred outside the Seller s bank shall be born by the Buyer.精选学习资料 - - - - - - - - - 名师归纳总结 - - - - - - -第 4 页,共 19 页Article 5 Delivery 5.1 The Delivery of the Equipment 5.1.1 The delivery of the Equipment listed in Appendix shall be completed within _ ( ) months from the Effective Date of Con
25、tract.5.1.2 With in _ ( ) months after the Effective Date of the Contract, the Seller shall send to the Buyer a preliminary delivery schedule by Email. Not later than _ ( ) days before the first shipment, the Seller shall submit to the Buyer the final delivery schedule in three (3) copies indicating