1、21年项目管理师模拟冲刺试题集5节21年项目管理师模拟冲刺试题集5节 第1节 121 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:A. The project is operating at a favorable cost efficiency ratio.B. the project is spending more t
2、han plannedC. the project is behind scheduleD. the project is ahead of scheduleE. B and C正确答案:C 144 Project cash reserves are often used for adjustment in escalation factors which may be beyond the control of the project manager. Other than possibly financing (interest) costs and taxes, the three mo
3、st common escalation factors involve changes in:A. Overhead rates, labor rates and material costs.B. Overhead rates, schedule slippages, and rework.C. Rework, cost-of-living adjustments, and overtime.D. Material costs, shipping cost, and scope changes.E. Labor rates, material costs, and cost reporti
4、ng正确答案:A 项目的“健康检查”发现你的项目面临无法按时完成的风险。几个项目在竞争相同的资源,出现了严重的资源冲突。因而,你对项目的风险进行了量化分析,确定需要什么样的时间表应急措施以及会发生什么成本。你运用蒙特卡罗分析方法进行时间风险分析。你进行的时间表分析的基础是:A、工作分解结构B、甘特图表C、优先序图作出的进度表D、概率/影响风险分级矩阵正确答案:C 185 In general, attempts to smooth out period to period resources will _ the scheduled time and _ project costs.A. In
5、crease, decrease.B. Increase, increaseC. Increase, increase or decrease.D. Decrease, decrease.E. Decrease, increase正确答案:B 质量控制通常是由谁来实施的 ( )AQA人员B项目团队C操作人员D项目管理部E以上都不是正确答案:C 最常用的用来确定项目收益率的技术包括_技术( )A净贴现值NPVB投资回收ROIC折算的现金流DCFD支付时间及风险敏感度分析E以上都是正确答案:E 如果一个任务的最乐观估算为12天,最悲观估算为18天,那么最可能估算为多少?A、15天B、13天C、16
6、天D、以上都不是正确答案:D 54 Historical records during close-out are useful to _ and _ for future projects.A. Predict trends, highlight problems.B. Analyze successes, shortfalls.C. Analyze strengths, document results.D. Support litigation, defend claims.E. Justify results, set standards正确答案:A 30 Work packages
7、are used to:A. Represent units of work at a level where work is performed.B. Clearly distinguish one work package from all others assigned to a single functional group.C. Limit the work to be performed to relatively short periods of time.D. All of the above.E. A and B only正确答案:D21年项目管理师模拟冲刺试题集5节 第2节
8、 175 Response Planning is the responsibility of the functional areas and considersA. mitigation.B. deflection.C. contingency planning.D. unforeseen occurrences.E. All of the above正确答案:E 在风险分析中标准偏差的概念很重要,因为它测量估计值的可变性,因此一个估计值的标准偏差越_ ,其可变性和风险越_ 。a. 大, 大,b. 大,小c. 小,大d. 小,正常正确答案:Aa Frame, 新项目管理, 79页。估价的标
9、准偏差 (SD) 越大,它的可变性和风险发生或同时发生的可能性就越大。例如,如果行为完成任务的成本是 $1,000 标准偏差SD 是 $100,行为 Y 花费同样的成本完成 $1,000,但标准偏差 SD 是$750;则行为 Y 比行为有更多的可变性和风险关联。 Using the situation the the Special window:A Productivity will increaseB His decisions will promote high satisfaction among his teamC His decisions will require less ti
10、meD All of the aboveE A and C only正确答案:B 62 The purpose of a dummy activity in an activity-on-arrow diagram is to:A. Identify a task that could be replaced by another.B. Take the slack time into account.C. Show a task that is not necessarily needed.D. Denote a milestone.E. Show a dependency relation
11、ship正确答案:E 你被任命为一个项目的项目经理。在你曾经参加过的项目中,整个团队的成员在项目动员大会之后就很少再碰面,你对这种做法比较失望。因为在整个项目进展过程中项目团队成员看不到项目进展的整体情况,有时你也看不到呈报给高层管理者的鲜明进展报告。因此你相信与项目团队成员分享信息是非常重要的。作为项目经理,你最先采取的行动就是建立一套信息检索系统。而下列哪一项不属于信息检索系统的一部分?( )A受动归档系统B项目管理软件C项目内部网D电子数据库正确答案:C 进度计划控制不考虑以下哪一项?A、 对造成进度计划变更的因素施加影响,保证变更是有利的B、 确定进度计划已经变化C、 管理实际发生的变
12、更D、 根据客户需求变更进度计划正确答案:D 历时估算是:( )A活动的预算历时B使用资源的时间C活动完成的时间D活动开始的时间正确答案:A 保证书的主要功能是( )A为提供的质量级别提供保证B提供对延期付款的保证C提供一种在项目接收后增加时间以纠正缺陷但又不增加成本的方法D保证购买的东西满足其使用目的正确答案:A 广泛使用( )沟通很可能有助于解决复杂问题( )A口头B书面C正式D管理信息系统正确答案:B21年项目管理师模拟冲刺试题集5节 第3节 36 Quality management deals with all of the following except:A. conforman
13、ce to requirements/specificationsB. satisfying the needs of the customerC. making products more desirable and luxuriousD. A and C.E. B and C正确答案:C 在一个最近的项目状态评审会议上,一名团队成员非常不满,而且贬低别人在团队中的地位。这个人属于下列哪项提及的破坏性团队角色?A寻求赞誉者B阻挡者C攻击者D独断者正确答案:B In preparing a good project definition, experienced project manager
14、s will:A Concentrate mainly on the end product rather than costs or benefits. These come later.B Realize that only the tip of the iceberg may be showing. As a project manager, you must get beneath it.C Understand that a project definition/plan is a dynamic rather than static tool, and thus subject t
15、o change.D Try to convert objectives into quantifiable terms.E All of the above正确答案:E Smoothing out resource requirements from period to period is called resource _.A.Allocation.B.PartitioningC.Leveling.D.QuantificationE.None of above.正确答案:CC 8 Fixed-price contracts place more risk on the _ .A. owne