定子安装方案(中英文对照版终稿).doc
《定子安装方案(中英文对照版终稿).doc》由会员分享,可在线阅读,更多相关《定子安装方案(中英文对照版终稿).doc(39页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、越南SONGBUNG4水电站机电设备安装工程VIETNAM SONGBUNG4 HYDROPOWER STATIONE&M EQUIPMENT INSTALLATION PROJECT水轮发电机定子安装方案Hydro-generator Stator Installation Program批准:李艺Approved by Mr. LiYi审核:张文红Checked by Ms. ZhangWenhong编制:谢荣新Written by Mr. XieRongxin广东省源天工程公司越南SONGBUNG4水电站项目部二一三年十月Guangdong Yuantian Engineering Co
2、mpanyVietnam SONGBUNG4 Hydropower Project DepartmentOct. 2013目 录Content1结构说明GENERAL DESCRIPTION22施工组织机构及人员安排CONSTRUCTION ORGANIZATION23施工准备 CONSTRUCTION PREPARATION33.1施工技术准备 Technical Preparation33.2施工设备工器具准备 Construction Equipment Preparation33.3 施工其它措施准备 Other Preparation64主要技术标准和规范MAIN TECHNICAL
3、 STANDARDS AND NORMS65施工程序及方法 CONSTRUCTION PROCEDURE AND METHODS65.1发电机定子组装程序图 Generator Stator Assembly Procedure Chart65.2定子组装 Stator Assembly85.3 定子的最终安装Final installation of stator215.4主要部件安装的质量控制点Main Components Installation Quality Control Points236施工工期 CONSTRUCTION PERIOD327质量管理措施QUALITY MANA
4、GEMENT MEASURES338安全文明施工 SAFETY & ENVIRONMENT-FRIENDLY MANNER349卫生环境保护 HEALTH ENVIRONMENTAL PROTECTION3610验收 ACCEPTANCE3838 / 391结构说明General Description定子由机座、铁心、线圈、基础板等部件组成。定子装配分3瓣结构,在厂内铁芯叠片、绕组下线。分瓣运输到工地,进行3瓣定子的组圆、现场下合缝线。定子机座由6个支脚、外环设置6组空气冷却器。Stator is made up of engine base, iron core, coil and sol
5、e plate, etc. Stator assembles divides into 3 clacks, while laminating iron core and winding inserting coil in the workshop, setting 3 clack-stator to a circle and inserting coil to the seams at site. Stator engine base is made up of 6 supporting feet, 6 sets of air coolers at outer ring.2施工组织机构及人员安
6、排Construction Organization现场负责人:李艺Site leader: Li Yi技术负责人:谢荣新Technical director: Xie Rongxin安全员:陈涛记EHS: Chen Taoji质检员:潘健强Quality inspector: Pan Jianqiang现场翻译/协调:陆昌龙Site translator/coordinator: Lu Changlong电气人员:3人Electric workers:3电气试验人员:2人Electric testers:2起重人员: 2人Lifting workers: 2 机械安装人员:4人Mechani
7、cal installation workers: 43施工准备 Construction Preparation 3.1施工技术准备 Technical Preparation1施工前熟悉厂家图纸、安装规程、规范和技术文件;Read drawings carefully before installation, also should know well with installation stand and technical documents.2由项目总工程师组织安装人员进行详细审核设计图纸,并作好审图、澄清问题以及设计技术交底记录;The general engineer shoul
8、d arrange the works check drawings and clairfy questions which raised by works, make statement of installation and keep the record. 3统计和核对设备和主要材料清单,制定到货计划和材料采购计划;Check the main equipment and material list then make a delivery and purchase plan.4制定重要设备安装和关键工序的安装方案和技术措施;Formulate the installation prog
9、ram and key process for main equipment. 5注意图纸提出的施工要求,设备部件的特殊安装工艺及对环境的特殊要求;Give more attention about technical request form the drawings, some parts have special techniques request as well as environment. 6机组安装前机坑已清理干净,满足安装条件。Workface have been clean well before installation and meet the request of e
10、rection.7安装前所需的设备及零、部件已到货齐全并检查合格。Check the elements needed which should be arrived site and the quality must be meet the drawings before installation.8安装所需的工器具满足要求,厂家提供的专用工具已到货。Erection tools must be meet the request and special tools form supplier have arrived site.3.2施工设备工器具准备 Construction Equipme
11、nt Preparation1备齐常用的起重吊具、绳索和安装工器具。Preparation of lifting, wire-rope, erection tools.2对所有的工具器具进行彻底检查和维护、保养,确保其工况良好,使用安全。起重设备的选择能满足设备最大起重量,达到吊装的安全要求。Check and maintenance carefully all the tools to ensure them in good behavior and safety for use, the lifting equipment capacity should cover the maximum
12、 weight of part of the equipment which to be erected.3指定有关安全负责人,检查安装用防护用品的配备是否齐全、到位。Specified full-time security staff to check all the tools needed to ensure safety during erection.名称 Tools Name单位 unit数量 quantity备注 remark耐压试验装置Withstand voltage testing apparatus套Set1感应器Inductor套Set1绝缘测试装置Insulation
13、 tester套Set1套液压设备Hydraulic press equipment套Set1分瓣定子吊具Lifting tools for stator section套Set4经纬仪或水准仪Theodolite or Optical level套Set1搅拌设备Mixing equipment套Set1套绕线设备Round packing device套Set1套高精度天平Precision scale 0 10 kg套Set1套灭火器Fire extinguisher套Set4清洁设备C lean Zone equipment套Set4线棒缠绕设备1pcs Round packing d
14、evice套Set1彩笔Coloured pencil套Set2上胶工具Paint gluer套Set1环形吊带Round endless slings套Set2木线棒及临时固定楔) Wood bars and temporary fitting wedges套Set1加热设备Heating equipment套Set1木榔头或塑料榔头 Wood hammer or plastic hammer套Set调整工具Alignment tools套Set2中频铜焊机Medium frequency brazing unit套Set1铜焊感应线圈Brazing inductor套Set2力矩扳手Tor
15、que wrench 套Set2焊接设备Welding equipment套Set1气焊装置Gas welding units 套Set2夹紧装置Clamping device套Set1球心器、中心架、水平梁及钢琴线等Centering tools, center frame, horizontal beam, piano line 件pc1红外线焊条烘干箱Infrared ray drying box of welding rod台set1焊条保温筒 Electrode dryer个pcs2交流电焊机 AC arc welder台set1直流电焊机 DC arc welder台 set1磁力
16、钻 Magnetic drill machine台set1千斤顶Jack根据实际情况配备足够Qty should be in accordance with the practical situation手拉葫芦 Chain hoist根据实际情况配备足够Qty should be in accordance with the practical situation角磨机Angle Grinder台set2磨光机Grinding machine台set1内径千分尺(规格:L=3m) Inside caliper套set1框式水平仪 Square level个pcs1调水平Adjust to l
17、evel塞尺(规格:L=300mm)Filler gauge 把pcs1M2442专用扳手 Special spanner套set2活动扳手 Adjustable wrench套set1梅花扳手 Box spanner套set15m卷尺 Measuring tape把pcs2水准仪Optical level 部set1打压泵 pressure pump台set1厂家提供的专用工具 Special tools 套set13.3 施工其它措施准备 Other Preparation 1施工平台准备 Construction platform preparation 定子安装前搭设防护棚。 Prot
18、ective shed should be prepared before stator installation.2施工用电准备 Construction power supply preparation在安装间或设备安装现场适当位置布置开关箱约3个,电焊机、磨光机、照明等施工设备用电取自各开关箱上。Three electrical distribution box were set off on erection bay and work area. Tools like as weld machine, grinding machine, lighting take power from
19、 the reasonable box.3施工消防准备 Fire fighting preparation在安装现场各适当位置布置手提式干粉灭火器约3个。Three hand dry powder fire extinguisher lay on suitable position.4施工通信准备Communication preparation安装现场配备对讲机约2对,保证安装现场通信。Prepare two walkie-talkies for site communication smoothly.4主要技术标准和规范Main Technical Standards and Norms1
20、厂家资料 Manufacture Data定子装配Stator Assembly H757300MKB100000FTB定子机座Stator Frame H757300MKB110000FTB定子铁芯Stator Core H757300MKB120000FTB定子接线图Stator Winding Drawing H757300MKB100000FTB铜环引线Stator Parllel Ring H757300MKB130000FTB定子起吊工具Stator Lifting Tool H757300MKB820100FTB2国家标准、部颁或行业标准National Standards or
21、 Industrial Standards根据合同规定的规范 Be in accordance with the contract.5施工程序及方法 Construction Procedure and Methods5.1发电机定子组装程序图 Generator Stator Assembly Procedure Chart进行定子组装准备Preparing for the stator assembly 将定子基础板把紧在机座脚板上Bolting the stator foundation on stator frame feet搭设定子下线平台Preparing for stator w
22、ingding patform下层定子线棒安装Inserting the bottom bars下层定子线棒试验High-voltage test for bottom bars下层定子线棒绑扎Wrapping for sator bottom bars上层定子线棒和槽楔的安装Inserting the top bars and wedging the slot wedges定子端箍的涂漆、注胶Painting and injecting for surge rings分瓣定子在安装间进行组圆Assemble the stator sections to circle in erection
23、bay上层定子线棒绑扎Wrapping for stator top bars上、下层定子线棒试验High-voltage test for bottom bars and top bars in stator joints把地脚螺栓装在定子基础板上install anchor bolts on the stator foundation plates将定子吊入机坑lifting stator into pit 定子总体试验High-voltage test for stator winding定子总体喷漆The whole stator painting焊接引线、装配定子绝缘盒Brazing