中英文施工组织设计(135页).doc
《中英文施工组织设计(135页).doc》由会员分享,可在线阅读,更多相关《中英文施工组织设计(135页).doc(134页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、-中英文施工组织设计-第 - 132 - 页Hansen Wind Energy Drives (Tianjin) Co.Ltd汉森传动(天津)有限公司CONSTRUCTION ORGARNIZATION DESIGN施工组织设计MCC TIANGONG CONSTRUCTION CO., LTD.中冶天工建设公司2008-9-15CONTENT目 录Brief introduction of the propsoal编制说明Construction Organization施工组织General Situation工程概况Sub-division item Construction meth
2、od主要分项工程施工方法Work Schedule plan施工进度计划Work Schedule Guaranty施工进度保证措施Quality Assurance / rol Plan 质量控制与质量保证计划Safety and Security Plan 安全生产与管理Construction Machine & Equipment Plan and Labor Plan主要施工机具计划和劳动力计划Construction echnology Management施工技术管理Winter construction measures冬季施工措施Construction Plan 施工平面布
3、置图Brief Introduction of the Proposal编制说明一 、Brief introduction of the Proposal编制说明 We arranged professional people to discuss and study the construction method and construction critical points as soon as we received the bid invitation. We have worked out construction organization desgin for your revi
4、ew.我公司根据招标文件和设计图纸的要求,对本项目的施工方案和施工难点进行了细致的探讨,精心编制了施工组织设计文件,供贵公司审阅。This constructional organization design is completed on the basis of your bids files combining our own construction experiences. During making process, we absorbed our advantages but forestalled defects so that we get this scheme impro
5、ved in many sides, such as full contents, reasonable economy, updated technique and workable measures etc. We also set a higher goal in construction period, quality and civilized construction.本施工组织设计是在贵公司提供的招标文件、施工图和我公司多年施工经验的基础上编制的。在编制过程中,我们认真总结了以往类似工程的经验和不足,使方案不断地完善,并力求做到方案切实可行、科学合理,技术先进可靠、措施得力,使本
6、工程在工期、质量、安全、文明施工上有明确的目标和可靠的保证。Our bid hereby is a general arrangement of the whole project designing. It may have difference with the actual situation on site. But we believe if we can get the project, we can do the necessary modifications when we get contract signed and drawings studied. Depending
7、on the advantages of talent wealth, scientific management, superior technique and up-dated equipment, we can provide you with and excellent constructional project prior to finish time.本施工组织设计是对该项目工程工作内容的总体部署和安排,本施工方案在编制过程中力求减少与现场实际情况的差距,在项目的实施过程中,针对施工现场的实际情况还需对施工组织设计进行更细致的修订和补充,不断加以完善。我们将依靠我公司在人才、管理
8、、技术、装备上的优势恪守合同、精心组织、确保工程质量达到优良并按期完成本项目施工任务。二Policies of Company公司政策 1. List it as a major project列入重点项目2. Project Safety工程安全和文明施工Try to realize our safety goal of zero accident. Strictly follow Construction Safety Produce Supervision Regulation, tighten up the management of safety, meet the owners r
9、equirement and follow TianJin” Construction Project Civilization Construction Management Temporary Regulation.确保施工零事故,严格遵循建设部颁发的建筑安全生产监督管理的规定,加强安全施工管理,严格按照业主的要求并遵循天津市建设工程文明施工管理暂行规定,项目执行过程中做好文明施工管理和交通管理的工作。3.Project Quality工程质量Construction should be conducted with strict standards put forward by the
10、owner. The qualified percentage of unit work must be 100% and for each work items we try to meet the qualified criteria.严格按照国家现行的建筑安装工程施工及验收规范和业主要求的质量标准施工,单位分项工程的质量评定合格率达到100%,单位工程的质量评定都达到合格标准。4. Project warranty工程保修Our company warrants to Owner that from the day of completed contract work, the warr
11、anty of this project shall follow related clause described in the biding document, the owner can not be influenced by our construction process or lack of material.我公司向业主保证,在完成本项目合同,办理完竣工验收之日起,对本项目的工程保修按照招标文件中要求的规定执行,业主不会受到由于我方施工工艺或所供材料的缺陷而出现的不良影响。5.Project term工程工期Construct as owners requirement und
12、er the prerequisite of safety construction and project quality. We guarantee that we will fulfill the project on schedule without the influence of unpredictable weather.在确保施工安全和工程质量的前提下,严格按照业主的工期要求进行施工在不受自然现象的影响下,保证按工期要求完成。三、Working-out Basis编制依据1 Working-out Basis of Construction Organization Desig
13、n施工组织编制依据This construction organization design is worked out according to current national specification, code & quality procedure documents compiled by our company in conformity with quality criteria system ISO9002, administration standard for venture and successful management experience of CTMCC a
14、nd tendering documents and drawings provided by the project owner. 本施工组织设计依据国家现有规范、标准,及我单位按照ISO9002质量体系标准编制的质量体系程序文件,企业管理标准和成功的管理经验,业主提供的本工程招标文件和施工图纸编制。2 Major current national construction criteria & code quoted is as follows:主要引用国家现行施工规范和标准如下:Quality Acceptance Specification for Architectural Sub
15、Grade Construction建筑地基基础工程施工质量验收规范 GB50202-2002Quality Acceptance Specification for Underground Waterproofing Engineering地下防水工程质量验收规范 GB50208-2002Uniformed Quality Acceptance Specification for Architectural Construction建筑工程施工质量验收统一标准 GB50300-2001Construction of Concrete Structure Works and Acceptanc
16、e Specification混凝土结构工程施工及验收规范 GB50204-2002Steel Rebar Welding and Acceptance Specification 钢筋焊接及验收规范 JGJ18-96Test & Evaluation Criteria of Concrete Strength混凝土强度检验评定标准 GBJ107-87Quality Acceptance Specification for Roof Works屋面工程质量验收规范 GB50207-2002Quality Acceptance for Architectural Ground Floor Wor
17、ks建筑地面工程施工质量验收规范 GB50209-2002Quality Specification for Architectural Drainage & Heating Construction建筑给排水及采暖工程施工质量验收规范 GB50242-2002Safety Specification for Temporary Electric Power in Construction Site 施工现场临时用电安全技术规范 JGJ46-88Safety Test Specification for Architectural Construction建筑施工安全检查标准 JGJ59-99
18、Quality Test & Evaluation Criteria for Engineering Decoration Project建筑安装工程质量检验评定标准 TJ303-88Industrial Metal Pipe Construction and Acceptance Codes工业金属管道工程施工及验收规范 GB50235-97Industrial Devices and Pipe Insulation Construction and Acceptance Codes工业设备及管道绝热工程施工及验收规范 GBJ126-89General Situation工程概况一、Gene
19、ral 工程概述The project is located in the crossing of Hi-Tech Road and Jingtong Road in BEDA, main workshop is 31204 m2 including production area, logistic area, public and office area, with pre-stressed pipe pile base, foundation of concrete C30, bedding course of concrete C10. The column foundation is
20、 sole reinforcement concrete and connect with steel structure column by embedded hold-down bolts. The workshop is single layer and 5 spans of 30.00m, 25.50m, 14.00m, 3x24.00m, and total length is 237.25m, width 142.20m. basic distance between column is 4.5m and several 24m, with roof of dual slope d
21、rainage, the max top level of column is 17.2m, main structure members include steel column, solid steel plate girders, solid bracket beams, and crane girders. The main steel structures should be connected with high strength bolts, the max weight of column is 5.5 tons, the max truss of roof 9.5 tons,
22、 total weight is 4250 tons, the cladding panels will be applyed to roof and walls. 本工程位于天津北辰科技园高新大道和景通路交口,主厂房建筑面积31204平方米,包含生产区,物流区,公用站房区和办公区,预应力管桩地基,基础采用C30砼,垫层采用C10砼,车间厂房柱基础为钢筋砼独立基础,钢结构柱与基础为预埋螺栓联接。 为单层连续五跨(跨度30.00m、25.50m、14.00m、3x24.00m)钢结构厂房,厂房全长237.25m,宽度142.20m,基本柱距4.50m(个别约24.0m),屋面为双坡有组织排水系统
23、,最大柱顶标高17.20m,主要构件包括:钢格构柱、实腹钢板梁,实腹托架梁及吊车梁等。主要构件之间连接采用高强螺栓,最大格构柱重量约5.50t;最大屋架重量约9.50t,钢结构总量约4250t。厂房围护结构屋面及墙皮采用夹层保温彩钢板。Currently the nature level is about -0.8m, the site is plane after completion of piles construction.目前场地自然标高约为-0.8m。桩基已施工完毕,场地开阔平坦。 The lay out and section sketch of workshop see 1-1