电动葫芦施工方案_secret.doc
《电动葫芦施工方案_secret.doc》由会员分享,可在线阅读,更多相关《电动葫芦施工方案_secret.doc(10页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、Construction Plan For Electrical Hoist电动葫芦施工方案Contents目 录. Project description工程概况. Process characteristics. 工艺特点. Construction preparation施工前准备. Construction sequence and technical requirements施工程序及技术要求. Trial operation试运行. Safety measurements安全措施1. Project description工程概况As per design requirements
2、, there will be one set of electrical hoist for 9902 storm water pump house and 9950 FF pump house of china dragon (PMMA6) project separately, and see parameter as followings:根据设计要求9902雨水泵房、9950消防泵房各设有一电动葫芦,参数如下:No序号Unit单体Type型号Specs规格19902 storm water pump house 9902雨水泵房CD12T 9m29950 FF pump house
3、9950消防泵房CD15T 6m2. Process characteristics:工艺特点:Electrical hoist is a special set and during assembly, no damage of every part shall be followed; construction and acceptance shall be performed strictly according to equipment technical regulations and code GB50278-98 Code for construction and accepta
4、nce of crane installation engineering. 电动葫芦属于特种设备,其组装时应以不得损伤任何零部件为原则,并应严格按照设备技术文件规定及起重机设备安装工程施工及验收规范GB50278-98组织施工与验收。3. Construction preparation施工前准备3.1 After electrical hoist is delivered to jobsite, first check to see is there is any damage during transportation and if there is, it shall be repai
5、red immediately and then cane be used. 电动葫芦到达安装地点后,首先应先检查在运输途中有无损坏情况,若发现有损坏情况,应及时修复方可使用.3.2 Check technical documents for equipment to see if types and specs comply with design requirements and technical safety explanation shall be carried out according to construction plan.清点设备技术文件,核查设备型号是否符合设计要求,并
6、按施工方案进行安全技术交底。4. Installation sequence and technical measurements:安装程序及技术措施:4.1Installation sequence: construction preparationcheck as per packing list and acceptanceinstallation of electrical hoistinstallation of electrical equipmentstrial operation and acceptance安装顺序:施工准备设备开箱清点与检查验收电动葫芦安装电气设备安装试运验
7、收。4.2Open-box check and acceptance: check type, specs and quantity of parts and components of equipment according to packing list to se if they comply with design and technical documents requirements and bear with qualification certificates; there shall be no distortion, damage or rust, especially f
8、or wire no rust, damage, bend, twisting, cracks and breaking etc.设备开箱检查验收:按装箱清单检查设备零、部件材料及附件的型号、规格、数量,符合设计与设备技术文件的要求,且有出厂合格证,机电设备应未变形、损伤与锈蚀,尤其是钢丝绳不得有锈蚀、损伤、弯折、打环、结扣、裂嘴、松散与断丝现象。4.3Track acceptance: difference to practical central line of tracking against elevation position of installation datum line s
9、hall be no more than 5mm; limit device and retarder shall be set on track to prevent digression.轨道验收:轨装的实际中心线对安装基准线的水平位置的偏差不得大于5,轨道上应有限位装置及缓冲装置,以防止葫芦脱轨。4.4 Installation of wire and hook shall comply with requirements of technical documents. Fixing of wire head, rolling canister and hook and fixation
10、 of fasteners shall strictly comply with requirements of technical documents. 钢丝绳与吊钩的安装应按设备技术文件规定缠绕方法进行,其钢丝绳头与卷筒体及吊钩的固定方法,紧固件拧紧度均应严格按技术文件标准执行。4.5A whole stage inspection shall be performed after completion of installation as followings:在安装完毕后应进行一次全面检查,检查内容如下:4.5.1Electrical position can meet electri
11、city types and operation voltage requirements at installation point.电动葫芦的电气装置是否适合于安装地点的电流种类与工作电压4.5.2 Reliable electrical connection.电气线路连接是否正确可靠4.5.3Limit device shall be correct, flexible and reliable. 限位装置动作是否正确、灵活、可靠4.5.4 All lubricant needed is set.所有润滑部份是否分别加足润滑油4.5.5 Reliable biting between w
12、heel and track.车轮与轨道接合是否可靠4.5.6When selecting power supply cables, make sure that power at inlet end of motor is no less than 90% of rated voltage.选择供电电缆时必须保证电机进线端电源不低于额定电压的90%5. Trial operation试运行:5.1Prior to trial operation of electrical hoist, following conditions must be reached:电动葫芦试运行前应确认下列准备工