实施SAPR3软件中项目管理(1).docx
《实施SAPR3软件中项目管理(1).docx》由会员分享,可在线阅读,更多相关《实施SAPR3软件中项目管理(1).docx(98页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、Project Management with SAP R/3Teaching Material for the Department ofProduction ManagementVienna University of Economics andBusiness AdministrationAndreas MildAlfred TaudesV.1.01Introduction32Basics & Keywords43Getting ready for the workshop74Case Study134.1Case description134.2Data for Project Rea
2、lization145Planning the project structure155.1General155.2Implementation in SAP176Scheduling266.1General266.2Basic calculations296.3Implementation306.4The project planning board417Cost planning & Controlling477.1General477.2Implementation488Looking up the costs619Capacity Planning649.1General649.2Im
3、plementation in SAP6510Earned Value Analysis6910.1General6910.1.1Measurement techniques6910.1.2Calculation of Earned-Value and Deviation Analysis7310.1.3Aggregation7410.2Implementation7411Execution7711.1Implementation7711.1.1Confirming network activities7711.1.2Invoices7911.1.3Material8312Informatio
4、n System8612.1Implementation8612.1.1Cost reports8612.1.2Earned-Value Analysis9213Literature981 IntroductionThis script serves as a basis for the workshop Project Management with SAP R/3. This workshop is part of a series of SAP-related workshops which are held by the Department of Production Managem
5、ent of the Vienna University of Economics and Business Administration, headed by Prof. Dr. Alfred Taudes. The workshop was developed by Andreas Mild. The goal of this Project Management Workshop is that, after having attended it, each student should be familiar with the theoretical backgrounds and b
6、e able to plan and control a project. The project manager has the task of ensuring that the project is executed efficiently, on time, and within the budget - which he/she achieves by making certain that the required resources and funds are available when needed. Every student should then be able to
7、put his/her SAP knowledge into action.To make the continuous improvement of this script possible, please report mistakes found or ideas for further development to andreas.mildwu-wien.ac.at.2 Basics & KeywordsSAP R/3 is an integrated and industry-independent standard software which covers, integrates
8、 and connects all functional areas in a business. SAP AG defines integration as defined communication. AFOS (Hrsg.) SAP Arbeit, Management. Braunschweig/Wiesbaden 1996 p.59 Although R/3 is designed for complete integration, it can also be used for a couple of business areas. Computerwelt No. 13 of 1
9、3. 3. 1998, p. 20 SAP is the abbreviation for “Systeme, Anwendungen, Produkte”, the German words for “Systems, Applications, Products”. AFOS (Hrsg.) SAP Arbeit, Management. Braunschweig/Wiesbaden 1996 p. 59 Information about the company can be found at: .Projects are tasks with special characteristi
10、cs. Attributes of a project are the following issues: complexity, non-repetitivity, high risk detailed goals to be achieved time restrictions high cost and capital expenditure quality requirements often strategic significanceTo be able to plan, monitor, control, and carry out a project as a whole, t
11、he project goals must be precisely described and the activities to be performed have to be structured. A project can be described as follows: according to how it is organized, i.e. by explaining the project structure, according to the processes involved.A project starts out as a statement of work wh
12、ich is either a written description of the objectives to be achieved and the desired rough schedule like start and end dates. In the description one could include also performance metrics and budget constraints.A project is further subdivided into meaningful pieces, referred to as tasks. Tasks take
13、usually less than a few months. The task can be further subdivided into subtasks.A work package can be defined as “a group of activities combined to be assignable to a single organizational unit.” Chase R./Aquilano N./Jacobs R. Production and Operations Management: Manufacturing and Services, p.48 T
14、he project tasks, subtasks, and work packages are brought into a hierarchy by defining a work breakdown structure.The individual elements represent activities within the work breakdown structure and are called work breakdown structure elements (WBS elements). WBS elements can be: tasks partial tasks
15、 which are subdivided further work packagesWBS can be structured according to object function phaseWhich kind of structuring is used depends on the focus of the project. Objects orientation is often used, if the main part of the project is a physical object like a power plant. Functional organisatio
16、n is preferred, if many different parts of an organisation or many organisations are involved.In practice, all three kinds of structuring are used within one WBS.“Project Management can be defined as planning, directing, and controlling resources (people, equipment, material) to meet the technical,
17、cost and time constraints of the project.” Chase R./Aquilano N./Jacobs R. Production and Operations Management: Manufacturing and Services, p.48 The primary reason why projects fail is insufficient effort in the planning phase. Chase R./Aquilano N./Jacobs R. Production and Operations Management: Man
18、ufacturing and Services p. 69 Project Management thus is considered as very important.The SAP Project System enables close and constant monitoring of all aspects of a project by having constant access to data in all the departments involved.Project management can be subdivided into project planning,
19、 i.e. the task which will be undertaken before the project starts, and project controlling during the implementation of the project.Planning must include: organization service process dates costs capacityThere are many possible project goals such as, for example, to realize a positive net present va
20、lue, to achieve a high imputed interest, to minimize costs, to cover costs, to maximize gross profit, or simply to finish as early as possible. However, it is important, that goals are defined operationally, thait is when it is possible to measure to which extent the goal has been achieved. The proj
21、ect manager breaks the project down into a set of activities. Then he also defines the relationships among these activities. The outcome is a guideline regarding the activities that can be performed in parallel and those that have to be done in a sequential order. This task is done via planning by n
22、etwork.Now, there are activities that require capacities and resources like personnel and material. Such resources are limited and these requirements have to be considered in order to be able to develop a feasible, sound plan. Information from other modules as e.g. the material planning module is re
23、quired.The system calculates the material requirements for each step of the project and organizes that materials are bought in time to avoid delays. When purchasing material, the system takes into account order sizes, inventory policies as well as other information. To prepare the financial statemen
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 实施 SAPR3 软件 项目 管理
限制150内