项目管理PROJECTTEAMMEMBERWORKSHOP(1)htnu.docx
《项目管理PROJECTTEAMMEMBERWORKSHOP(1)htnu.docx》由会员分享,可在线阅读,更多相关《项目管理PROJECTTEAMMEMBERWORKSHOP(1)htnu.docx(35页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、DATACOM Information Technology LimitedWELCOMETO項目管理PROJECT TEAMMEMBER WORKSHOPA TWO DAY WORKSHOPThis workshop has been specifically designed to help you understand the essential principles of project management as a member of a project team and introduce you to a consistent process for managing any
2、type of Project in the Organization. The process is an integral part of the PROGRAM METHODOLOGY. Our objective is to ensure all programs and projects are effectively managed and reviewed to achieve success and delight our customers every time with on-time completion.The workshop includes a case stud
3、y to give you an opportunity to apply the techniques included in the methodology WORKSHOP OBJECTIVES工作室目的Understand Roles & Responsibilities明白職分及責任Understand team member role明白團體職分Learn the Methodology 學習方法l Project definition 項目定義l Project planning & scheduling 項目計劃及排程l Project execution 頂目實施l Proj
4、ect closure 項目完結Learn the techniques to use學習技術盡量利用Contributing to success達致成功ESTIMATING FACTORS估計因素TASK使命 SIZE EFFORT DURATION= WORK DAYS 大小 努力 期間=工作日數 CALENDAR TIME 日曆時間EFFORTDURATIONSCHEDULE努力期間進度表INPUTS輸入Historical data過往資料Experience & skills經驗及技巧Expert view專家意見BIAS? BIAS?偏見? 偏見? TASK任務 EFFORT努力
5、 SIZE 大小 PERSON DAYS個人日子DEFINE MEASUREMENTBASIS 估計定義基礎 其它?因素OTHER ? FACTORS EFFORT努力 ANALYSIS分析 CAPACITY 容量 WORKLOAD工作負擔DURATION日期 Critical Path Method PERT計劃評審技術-PERTFSSF邏輯基礎-依賴性BASED ON LOGIC-DEPENDENCY3 TYPES:三種類l Finish to Start完結到起始l Start to Start paired 起始到起始配對 l Finish to Finish paired完結到完結配
6、對CRITICAL PATH THE LONGEST PATH計劃評審-最長要徑-LEAST FLEXIBLE-最低靈活性Any slippage extends the Total Project Time TPT任何小疏忽加長總項目時間CAREFUL: Compressing the schedulecan change the Critical Path警告:壓縮排程能夠改變要徑CPM-PERT TERMSForward Pass- Early START and FINISH 前進-早開始及完成Backward Pass-Late START and FINISH 後退-開始及完成TO
7、TAL FLOAT-搖擺SPARE TIME IN AN ACTIVITY分配時間於各種活動INCLUDES FREE AND INDEPENDENT FLOAT包括自己反依賴性的搖擺CRITICAL ACTIVITY-ZERO FLOAT BY重要活動-零的搖擺DEFINITION-IT CAN BE FORCED!定義-能夠強行OTHER RELATIONSHIPS其他關係 4dLEG GAP- A forced delay between tasks 2dLEAD LEEWAY-A forced start of thesuccessor before completion of the
8、predecessorErrors in LogicBOTH BREAK THE LOGIC OF THE NETWORK錯誤使綱絡理論停止運作 THE LOOP 循環 THE DANGLE 搖擺不定REVIEW THE PROJECT DEFINITION檢討計劃的定義Does the plan: 計劃l meet critical dates for deliverables? 在重要日子傳遞訊息l clearly meet interface dates? 清楚相約其他日子OPTIMISATION INVOLVES: 理想計劃包括l understanding the conflicts
9、 明白衝突的地方l analysing priorities 分析優先次序l deriving options 削去不必要選擇l selecting the best realistic option 選取最真實性的決擇l seeking stakeholder agreement 尋找投資者的同意書l revising plans 重溫計劃的內容l communicating to everyone 與其他人交換意見TRADE-OFFS & OPTIMISATIONTAKES TIME TO GET THE BESTSOLUTION選擇性及樂觀性用時間來獲取最好的方案OPTIMISING T
10、RADE-OFFS樂觀性的選擇POSSIBLE ACTIONS: 可行方法Re-evaluate dependencies 重新評估依賴性Review relationships 回顧各種關係Introduce Lags and Leads-with care! 小心地引申拉引行為Split activities for concurrency 分散工序,保持合作性Review duration 檢討各工作時間Review contingency time檢討一貫時間所需Re-assign resources 重新分配資源Utilise the Total Float times 盡量利用所有
11、空間時間Reduce peak loading levering 減少極大壓力-平衡Seek more resources? 尋找更多資源Increase resource capacities 增加資源地位Avoid re-invention 防止再發明其他選擇Reduce Scope/specifications? 減少分工合作EVALUATE THE IMPACT 評估影響所及Use what-if analysis 如果用作為分析Review Project Risks 檢討其冒險機會Customer acceptance 客人接受機會OPTIMISING & RECOVERY PLA
12、NNING INSIDE A KEY STAGE樂觀化及恢復計劃是一個重要階段 DEVELOP WHAT IFs 發展空間REDUCE THE OPTIONS 減少選擇機會RECOMMENDED ACTIONS 推介行動 SEEK PROJECT LEADERAPPROVAL計劃得到組長應允BEFORE YOU MODIFY THE PLAN在改變原定計劃之前COMMUNICATE THE PLAN CHANGES TO THOSE DOINGTHE PROJECT WORK向有關工作人員解釋新計劃的改變SECURE RESOURCE COMMITMENTS保障資源承諾The Key Stag
13、e Owner 重要階段的擁有人The Resource 資源The Functional Manager 功能組別經理ALL PARTIES MUST SIGN UPPROJECT LEADER APPROVES參與者必須簽署待組長審閱REVIEW THE RISK LOG檢討有危機的地方ASK: 問Have any changed rankling? 何種改變, 使人痛心Any ,moved to HIGH? 何事轉為高危事件Any risks identified from planning? 何種危機被計劃所確認Check the plan for areas of risk;檢查計劃
14、裹有危機的地方Tasks on the Critical path 重要關鍵時刻Tasks with long durations 長遠計劃Tasks dependent on third parties 依賴第三者Lags and Leads 落伍及前衛Complex tasks 繁複的工作Tasks using new technology 新科技應用Tasks with little float 搖擺不定Do not remove risks from the LOG, only remove the ranking不要將風險在日誌中除掉,只有除掉次序優先IDENTIFY ISSUES
15、PROMPTLYACTION TO RESOLVE IS A PRIORITY定時確認危機優先採取行動解決The Project Leader must recordall issues.計劃組長必須記錄所有論點ISSUES ARE RATED: 論點分類RED-MAJOR-Escalated to Project Members紅色-主要-擴大到項目人員YELLOW-SERIOUS-Escalated to Sponsor黃色-嚴重-擴大到資助人GREEN-MINOR-Escalated to Project Leader綠色-次要-擴大到組長ACTION PLANS ARE ESSENTI
16、AL行動的重要性Was it a RISK? 危機What is the consequence? 結果What options are available? 可供選擇What actions are recommenced? 建議採取行動Who is responsible for implementation?誰可執行SET THE BASELINE PLAN設定計劃的底線FIXES THE PLAN固定計劃BASIS OF PROGRESS量度工作MEASUREMENT進度底線ESTABLISHES CLEARLYVISIBLE TARGETS設立清楚可見的目標AGREES A MEET
17、INGSSCHEDULE同意會議時間表ESTABLISHES REPORTING & CHANGE PROCESSES建立報告及轉變程序REPORTING PROGRESS 進度報告COMMUNICATION IS VITAL TO SUCCESS人與人溝通是成功的因素KEY STAGE OWNER-REPORT STATUS AT FREQUENCYSET BY PROJECT LEADER.重要階段段的持有人週期性報告工作進度由組長設定FOCUS: 焦點MILESTONES ACHIEVED 里程碑建造MILESTONES DELAYED 里程碑延誤ACTIONS TO CORRECT S
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 项目 管理 PROJECTTEAMMEMBERWORKSHOP htnu
限制150内