1、PMP认证考试题库PMI-001 Project Management Professional QUESTION NO: 1 The inputs of the Performance Reporting process include all of the following except for which one? A. Performance reviews B. Work performance information C. Forecasted completion D. Performance measurements Answer: A Explanation: Perfor
2、mance reviews are not an input of the Performance Reporting process. The remaining inputs of this process are quality control measurements, project management plan, approved change requests, and deliverables. QUESTION NO: 2 You are a project manager for Pizza Direct, which is a retail pizza delivery
3、 store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity. What is the most ap
4、propriate response? A. You decide to participate in the initial meetings with the foreign business partners because any information you gain now will help you when you make the move to the new company. B. You inform the foreign business partners that youre going to be working with a new company and
5、that you know the deal theyll receive from the competing company is better than the one this company is proposing. C. You decline to participate in the initial meetings with the foreign business partners because of a conflict of interest. D. Youve not yet received an official offer from the competin
6、g company for your new job opportunity, so you choose to participate in the initial meetings with the foreign business partners. Answer: C Explanation: The most appropriate response is to decline to participate because of a conflict of interest. QUESTION NO: 3 The most effective team motivator is: P
7、MI PMI-001: Practice Exam Pass Any Exam. Any Time. - www.P 2 P A. understanding the importance of the project B. the satisfaction of meeting a challenge C. All of the other alternatives apply. D. the visibility of the teams contribution E. the individuals professional challenge Answer: D QUESTION NO
8、: 4 Complete final contract performance reporting and verify product is done in _ . A. Conduct Procurements B. Close Procurements C. Plan Procurements D. Administer Procurements Answer: B Explanation: Complete final contract performance reporting and verify product is done in Close Procurements. QUE
9、STION NO: 5 Continually measuring and monitoring the actual cost versus the budget is done to _. A. None of the other alternatives apply . B. analyze the reasons for variances C. establish the variances D. identify the problems E. All of the other alternatives apply. Answer: E QUESTION NO: 6 You are
10、 a project manager for Giraffe Enterprises. Youve recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition. Which of the following could happen if you dont correct this? PMI PMI-001: Practice Exam
11、Pass Any Exam. Any Time. - www.P 3 P A. The project costs could increase, there might be rework, and schedule delays might result. B. The project management plans process for verification and acceptance of the deliverables needs to be updated as a result of the poor scope definition. C. The poor sco
12、pe definition will adversely affect the creation of the work breakdown structure, and costs will increase. D. The stakeholders will require overtime from the project team to keep the project on schedule. Answer: A Explanation: Option A might seem like a correct answer, but option D is more correct.
13、There isnt enough information to determine whether stakeholders will require overtime. We do know that poor scope definition might lead to cost increases, rework, schedule delays, and poor morale. QUESTION NO: 7 You are a project manager working in a foreign country. You observe that some of your pr
14、oject team members are having a difficult time adjusting to the new culture. You provided them with training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following statements is true? A. This condition is kno
15、wn as culture shock. B. This is the result of jet lag and travel fatigue. C. This is the result of working with teams of people from two different countries. D. This condition is known as globalculturalism. Answer: A Explanation: When people work in unfamiliar environments, culture shock can occur.
16、Training and researching information about the country youll be working in can help counteract this. QUESTION NO: 8 Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project member is responsible for each activity B. Defines responsibilities for each WB
17、S component C. Defines all people associated with each activity D. Text description of roles, responsibilities, authorities Answer: D PMI PMI-001: Practice Exam Pass Any Exam. Any Time. - www.P 4 P Explanation: The Responsibility Assignment Matrix (RAM) details the different tasks for the people lis
18、ted in the matrix chart. QUESTION NO: 9 The erection of foundation formwork before the placement of foundation concrete would be an example of a _ dependency. A. Soft logic B. Subcontracted C. Mandatory D. Discretionary E. External Answer: C QUESTION NO: 10 You are the project manager of a project .
19、You have just completed the Collect Requirements and Define Scope. What should you do next? A. Control Scope B. Create WBS C. Value analysis D. Verify Scope Answer: B Explanation: Create the WBS is the process that follows Collect Requirements and Define Scope. QUESTION NO: 11 Which of the following
20、 is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project member is responsible for each activity B. Defines all people associated with each activity C. Defines responsibilities for each WBS component D. All of the other alternatives apply PMI PMI-001: Practice Exam Pass Any
21、 Exam. Any Time. - www.P 5 P Answer: D Explanation: The Responsibility Assignment Matrix (RAM) details the different tasks for the people listed in the matrix chart. QUESTION NO: 12 Giving a part of project work to a contractor is an example of: A. risk assumption B. risk assignment C. risk delegati
22、on D. risk deflection E. risk mitigation Answer: D QUESTION NO: 13 Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average? A. 6.1 B. 6.3 C. 6 D. 4 Answer: B QUESTION NO: 14 Management reserves are normally defined as a % of the
23、 total budget. As a project progresses, the project manager wants the $ value of management reserve to _, whereas the customer wants the management reserve to _. A. Increase, increase. B. Increase, decrease. C. Remain the same, return to customer. D. Decrease, increase. E. Decrease, decrease. PMI PM