机电安装质量计划.docx
《机电安装质量计划.docx》由会员分享,可在线阅读,更多相关《机电安装质量计划.docx(48页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、Summary of QA/QC program 质量保证/控制程序1 Quality target质量目标l Engineering quality yield rate 100%.工程质量合格率100%。l Contract performance rate 100%.合同履约率100%。l Manufactured product primary inspection yield rate 98%.制造产品一次检验合格率98%。2 Quality policies质量方针Meticulous construction, quality assurance, and striving fo
2、r fine project; Untiring service, continual improvement and keeping the Customers Satisfied精心施工,确保质量,创精品工程。竭诚服务,持续改进,让顾客满意3 Quality assurance system质量保证体系General system of project quality assurance is established on site by Project Management Office. Project manager is general principal for project
3、quality, and project chief engineer is quality assurance director. According to specific content of this project, according professional quality assurance system shall be established for heavy equipment lifting, compressor unit installation, pipe welding, installation and cleaning, antiseptic, elect
4、ronic control system, and control &instrument system etc, and various engineers of different work type shall be professional quality assurance personnel. Personnel name list of on-site quality assurance system shall be submitted to client and on-site quality supervised unit. 项目部在本工程现场建立工程质量保证总体系。项目经
5、理是工程质量总负责人,项目总工为总质保师。根据本工程的具体工作内容,对大件设备吊装、压缩机机组安装、管道焊接、安装和清洗、防腐、电控系统、仪控DCS系统等重要分部工程,应建立相应的专业质量保证体系,各有关专业工程师为相应的专业质保师。现场质量保证体系人员名单应报业主和现场质量监检单位。3.1 Organization chart of project quality system项目质量体系机构图Construction managerMaterial manager IInstrument engineerWarehouse keeperQuality inspectorEquipment
6、EngineerElectrician Engineer Quality managerProject managerE&I teamPiping teamEquipment TeamInsulation teamProcess Engineer 3.2 Quality management responsibilities质量管理职责l Project manager项目经理Project manager is a fully fledged member of our company on site, who will take a lead in formulating project
7、quality plan, supervising and guaranteeing implementation of quality plan. Project manager shall hold on-site quality meeting, attend quality meeting of client, lead, supervise and guarantee effective operation of quality system, so as to ensure the fulfillment of quality target. Project manager sha
8、ll assume primary responsibility for project quality. 项目经理是我公司在现场的全权代表。领导制定本工程质量计划,监督并保证质量计划的实施。主持现场质量会议,参加业主的质量会议,领导、监督并保证质量体系的有效运行,确保质量目标的实现。项目经理对工程质量负第一责任l Deputy project manager/construction manager项目副经理/施工经理Deputy project manager is the assistant of project manager, who takes part in formulatio
9、n of project quality plan, reasonably allocate various construction resources, and organize construction according to contract. Deputy project manager is responsible for organizing effective operation of quality assurance system, strictly performing construction procedures, and ensuring to construct
10、 according to design drawing, standards, norms as well as approved technology file. Besides, he will assume responsibility for project quality.项目副经理是项目经理的助手。参与本工程质量计划的制定,合理调配各种施工资源,按合同组织施工。具体组织质保体系的有效运行,严格执行施工程序,保证按照设计图纸、标准、规范及批准的工艺文件进行施工。项目副经理对工程质量负执行责任。l Quality manager(project chief engineer )质量经
11、理(项目总工程师)Quality manager (project chief engineer) is an assistant of project manager, who is quality assurance director for on-site quality assurance system. Under leadership of project manager, project chief engineer is responsible for formulation and performance of project quality plan. He leads a
12、nd supervises the effective operation of quality assurance system, approves technical proposal and quality assurance measures, and organizes quality management activities on site as well as supervision and inspection. Quality manager (project chief engineer) reports work to project manager and corpo
13、rate quality management department, and assume management and technical responsibility in terms of work quality质量经理(项目总工程师)是项目经理的助手,是现场质保体系的总质保师。项目总工程师在项目经理的领导下,组织制定本工程质量计划,负责质量计划的执行。领导并监督质量保证体系的有效运行,审批技术方案及质量保证措施,组织实施现场质量管理活动,组织对工程质量的监督及检查。质量经理(项目总工程师)向项目经理和公司质量管理部汇报工作,对工作质量负管理及技术责任。l Project manag
14、ement department工程项目管理部Work is conducted in Project Management Department under the leadership of deputy project manager and quality manger (project chief engineer). Project management department is responsible for formulating design of project construction organization plan and organizing design in
15、terpretation and drawing review, in charge of specific implementation of general quality plan in terms of technical work and on-site procedure control, solution of technical problems, personnel training, so as to ensure operation of quality assurance system .etc.工程项目管理部在项目副经理和质量经理(项目总工程师)领导下开展工作。负责编
16、制项目的施工组织设计、组织设计交底与图纸会审、负责技术工作和现场工序控制、解决技术问题、人员培训等项目的整体质量计划的具体实施,以及确保质量保证体系运转等。l Quality department and quality engineer质量部和质量工程师Quality department and quality engineer is the assistant of quality manager (project chief engineer) and deputy project manager. He is to ensure quality management on const
17、ruction site is performed according to requirement as stipulated in corporate quality manual and quality procedures and documents as approved by client, to report to quality manager (project chief engineer) the quality system operation and project quality on site, to handle with quality problems on
18、site within his authority, and to fill in quality records and sign within his authority, in charge of quality statistical work.质量部和质量工程师是质量经理(项目总工程师)和项目副经理的助手。确保施工现场的质量管理按照公司质量手册及经业主批准的质量程序和文件的要求执行,负责向质量经理(项目总工程师)汇报质量体系运行情况及现场工程质量状况,同时在其授权范围内处理现场质量问题,填写质量记录并按其授权范围签字,负责质量统计工作。l Quality inspector质量检查员
19、Quality inspector is the performer of on-site project quality inspection, who is responsible for self-inspection of operation of on-site project quality management as well as contact work of internal and external audit. He is responsible for the inspection of quality of on-site project entity accord
20、ing to norm, standard as well as related technology file, to supervise and urge rectification of items failing to satisfy requirements and to promote overall quality management over undertaken project and conduct quality awareness education, in charge of related quality activities at the same time.质
21、量检查员是本工程现场质量检查的具体执行者。负责对本工程现场的质量管理运行情况的自查,负责内、外审核的联络工作。具体负责按规范、标准及相关工艺文件对现场工程实体质量进行检查,督促对发现的不符合要求的项目进行整改,在所承担的项目上推行全面质量管理和进行质量意识教育,并负责相关的质量活动。l QA personnel of professional engineering company(specialized engineer)专业工程公司质保师(专责工程师)Quality assurance personnel of professional engineering company shall
22、review construction drawing prior to construction, formulate construction technology document and ensure technical measures for quality, so as to eliminate quality hidden danger during late period of project to the greatest extent. He is responsible for controlling of construction drawing, document
23、and outside materials, raising requirements regarding personnel qualification and equipment property of special technology procedure, and conducting improvement and controlling for key working procedures by use of statistical techniques.专业工程公司的质保师在施工前应对施工图纸加以会审,制定施工工艺文件和保证质量的技术措施,尽可能消除工程后期的质量隐患。对本专业
24、工程公司的施工图纸、文件及外来资料进行控制,负责对特殊工序的人员资格及设备性能提出要求,应用统计技术对本工程关键工序进行质量控制和改进。l Equipment &materials director设材部主任Equip &materials director is to work under the guidance of deputy project manager, who is responsible for supply and management of project materials. He is to guarantee the supplied project materi