1、卸煤沟平安技术交底(最新版)编制人:审核人:审批人:编制单位:编制时间:年 月 日序言下载提示:该文档是本店铺精心编制而成的,希望大家下载后,能够帮助大 家解决实际问题。文档下载后可定制修改,请根据实际需要进行调整和使用,谢谢!并且,本店铺为大家提供各种类型的平安管理制度,如通用平安、交通运输、 矿山平安、石油化工、建筑平安、机械平安、电力平安、其他平安等等制度,想了 解不同制度格式和写法,敬请关注!Download tips: This document is carefully compiled by this editor. I hope that after you download
2、it, it can help you solve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you!In addition, this shop provides you with various types of safety management systems, such as general safety, transportation, mine
3、 safety, petrochemical, construction safety, machinery safety, electrical safety, other safety, etc. systems, I want to know the format and writing of different systems ,stay tuned!卸煤沟平安技术交底施工单位:中国十五冶金建设集团编号:ZY-001工程名称重庆石柱发电厂新建工程分项工程名称汽车卸煤沟及T1转 运站土方开挖作业内容土方开挖石方爆破 施工交底部门工程部交底人接受交底班组或人员:交底主要内容:一、施工技术交
4、底:1、汽车卸煤沟与T1转运站相距较近,采用总体开挖方案,总体开挖长度为 120. 8m,基坑开挖工程主要为石方爆破施工。2、施工顺序为:开挖定位控制线测量一表层土清理一第一层石方预裂面爆破 一爆破第一层石方一基坑围护一爆破第二层石方一基坑验槽一垫层施工。3、基坑土石方开挖采用分层分梯段开挖,分段主要分二段开挖,第一层土质 主要为回填石渣及粘土,开挖坡度为1: 0. 70,第二层为泥岩,分两次爆破,一次 爆破深度23川,开挖坡度为1: 0. 40,基坑底部四周留0.75m宽工作面,在接T1 转运站地道位置留汽车坡道。基地设300mm宽排水沟及每隔45m设置 800 X 800 X 800mm
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 卸煤沟 安全技术 交底
![提示](https://www.taowenge.com/images/bang_tan.gif)
限制150内