1、21年项目管理师历年真题9篇21年项目管理师历年真题9篇 第1篇 127 Using the situation stated in the Special window, what is net present value of an annual income flow of $1600 at 14% over the next three years?A. $3713.60B. $0.68C. $1080.00D. $476.19E. $2.32正确答案:A 受雇于一个设计公司的一个建筑师被公司的CEO叫来向一个建筑承包商的项目管理团队解释一种圆顶屋的设计思想。虽然这家建筑承包公司没有做
2、过建筑师当前的项目,但这家建筑承包公司的老板是这家设计公司CEO的内弟。这各情况证明( )A组织、技术和人际关系对项目的相互作用经常同时发生B作为项目经理,沟通应按命令链发生C建筑师的介入是组织计划中的一个约束D你应该总是按照老板的意思工作正确答案:A Participative Management:A involves the solicitation of information from all team members.B assumes that members avoid work and responsibility.C suggests the sharing of powe
3、r and decision making.D employs a Theory X style. of leadership.E A and C正确答案:E Using the figure in the Special Window, what is the probability of success for Project B?A 0.3B 0.2C 0.35D 0.15E 0.12正确答案:C 118 A common way by which executives provide the project manager with written authority is throu
4、gh:A. A common job description for all project managersB. An appointment letterC. A project charterD. All of the aboveE. B and C only正确答案:E 33 In which of the following contract types is it easier to change the scope of the contract:A. firm fixed priceB. fixed price plus incentive feeC. cost plus pe
5、rcentage of costD. letter contractE. None of the above正确答案:C 134 Which of the statements regarding benefit-cost analysis in the Special window are true?A. 1 and 2B. 2 and 3C. 1 and 3D. 1, 2 and 3E. None of the above正确答案:C 64 An effective Project Manager does not share project _ with the team members
6、.A. VisionB. responsibilityC. solution to problemsD. accountabilityE. status正确答案:D21年项目管理师历年真题9篇 第2篇 您要确定全套结果的预期价值您会运用以下哪一种技术 ( )A决策树B鱼骨图C参数模型D非参数模型正确答案:A 在下列哪类网络图中不使用虚拟活动?( )ACPMBDetailedCPDMDPERT正确答案:C 质量管理计划没有对以下哪项进行描述?A、 执行质量政策的方法B、 项目质量系统C、 项目的质量控制、质量保证和质量改进计划D、 在成本、进度和质量之间做出权衡的步骤正确答案:D 质量似乎是你们
7、公司的追求。首先,公司通过了ISO9000认证。现在执行总裁想赢得MalColm BalDrige奖。每个项目都有一份与机构的远景目标一致的质量综述。对所有项目提供内部和外部的质量保证以便( )A确保项目满足相关的质量标准B监控特定的项目结果以确定它们是否符合相关的质量标准C找出排除不满意结果产生过程的方法D检查以排除过程中的错误正确答案:A 58 Which of the following communication media is least accepted by organizations?A. tactileB. audioC. extrasensoryD. visualE. o
8、lfactory正确答案:C 154 A Work Breakdown Structure:A. assures all work is identifiedB. subdivides the project into manageable segmentsC. provides the project sponsor with a time-phase task summaryD. both A and BE. All of the above正确答案:D 一个公司为改善沟通和团队协作可以选择使用一个紧密的矩阵。这种方法还能促进a. 快速追踪b. 协作工程c. 资源平衡d. 地理上分散或虚拟
9、团队的工作正确答案:Aa. 协作工程 紧密的矩阵一词的意思是说,所有的团队成员都在同一地点或彼此非常接近的地方工作。这一概念曾在建设项目、新产品开发和公共劳动之类的项目中得到有效地运用。一个紧密的矩阵能有助于协作工程是因为设计工程师像产品工程师一样也都在同一地点工作。这就确保了项目的设计和产品一样能节约成本。实施 In which of the following is the cost of risk hidden by the contractor?A Firm Fixed Price ContractB Fixed Price Plus IncentiveC Cost Plus Fixe
10、d PriceD Cost Plus Percentage of CostE A and B正确答案:D21年项目管理师历年真题9篇 第3篇 你正在负责一个面向全公司的项目管理培训的课程在这种情况下,你的无形工作成果是A、能有效应用培训内容的员工B、每一门课程的培训材料C、为完成培训的员工颁发的结业证D、你的培训课程目录正确答案:A 8 Researching, organizing and recording pertinent information is called:A. Alternative analysisB. Information gatheringC. Configurat
11、ion managementD. Post project analysisE. All of the above正确答案:B 86 Team members want to work for a project manager that can provide them with career path planning. In which organizational form. is career path planning difficult for project employees?A. MatrixB. Pure projectC. Project coordinatorD. P
12、roject expediterE. Classical/traditional正确答案:B 199 Which of the following is closest to Jurans definition of Quality:A. conformance to requirements.B. fitness for use.C. continuous improvement.D. customer focus.E. All of the above正确答案:B 在风险分析中标准差非常重要,因为它可以测量一个估算的可变性,因此,估算的标准差( ),其可变性和风险就( )。A越大、越大B越
13、大、越小C越小、越大D越小、为常态正确答案:A 104 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:A. 1.10B. 0.90C. 0.956D. 1.15E. 0.869正确答案:A The process of choosing/documenting the best approach to achieve the project objectives is part of:A.The scope baseline.
14、B.Scope authorizationC.Scope definitionD.Scope planning.E.All of the above.正确答案:DD 项目范围/章程的基准包括 ( )A确定项目时所需的背景条件的概括B组织权利及职责的关系C包括时间估算在内的资源需求计划D以上都正确正确答案:D21年项目管理师历年真题9篇 第4篇 By which means is a contractor able to control cost overruns due to changing requirements?A Project data reviewB Change orderC
15、Purchase order amendmentD Change controlE None of the above.正确答案:D 项目经理可能意识到不能满足某些合同条款和项目目标,要达到某些规范既费成本又花时间。这时项目出现风险可能性较高,同客户协商降低风险可能性这种手段:A、 可以消除所有项目和客户风险而不需要任何成本B、 可以重新定义风险对客户发生的可能性C、 可以使项目范围减小并改进交付给客户的产品D、 可能减少支付罚金的成本并且满足修订过的规范达到客户的最低要求正确答案:D “直到软件产生了,我才能对它进行测验。”这句话描述了下面那一种依赖A、 随意性B、 理性C、 偏好性D、 强
16、制性或者强硬性正确答案:D 在完成项目工作多少百分比后,累计成本纯净指数相对稳定?( )A5% to 10%B15% to 20%C25% to 35%D50% to 75%正确答案:B 一个汽车设计团队应该熟悉最新的自动化装配技术。这个团队可以从多种途径获得这些技术:他可以雇佣一个这方面的全职专家,也可以聘请一个顾问,还可以派一个设计工程师去参加机器人技术的高级研讨会,甚至可以请一些制造部门的职员加入到项目团队中来。每个方法的饿相关成本都必须作为项目计划的一个因素被考虑到。这说明了下列哪项的重要性?( )A在行为定义前完成资源计划的编制工作B准备一个资源分配矩阵,并将其作为一个控制工具使用C
17、将资源计划与成本估算紧密结合在一起D把资源计划作为挣值管理的一个输入项。正确答案:C 项目执行期间,进度绩效和成本绩效均令人满意,这时重新委任了一个项目经理,他正出席见面会,什么是是最重要的?A、 设定目标B、 向项目干系人人介绍小组成员C、 检查沟通D、 项目章程正确答案:C 以下哪项不是风险审计的目标A、确认在项目生命周期内始终执行了风险管理B、确认项目得到了良好管理,风险得到了控制C、帮助确认项目在早期的潜在价值损耗的情况D、确保每个识别和确认的重大风险的预期价值得到计算正确答案:D Using the WBS in the Special window, an instance of
18、a work package is:A Build houseB ExcavateC Prepare FoundationD B and CE None of the above正确答案:E21年项目管理师历年真题9篇 第5篇 89 The utility of a risk seeker is:A. negatively exponentialB. positively skewedC. increasingD. decreasingE. symmetrical正确答案:C 3 Project management/project planning is most closely align
19、ed with:A. Long range/strategic planning (5 years or more).B. Intermediate range planning (1 to 5 years)C. Short range/tactical planning (1 year or less).D. All of the above.E. B and C正确答案:E 以下哪项是集中式签署合同的好处A、 便于使用签订合同专门技术B、 提高公司签订合同的专门知识C、 更忠于项目D、 合同人员没有家正确答案:B The cost of a quality program should b
20、e budgeted at _ of the total project.A . 10-12%B . 2-3 %C . 6-8%D . 3-5%E . more than 15 %正确答案:D 81 The degree to which a company accepts and utilizes project management is often dependent upon the _ and _ of the project.A. Competition, dollar valueB. Type of industry, manpower requirementsC. Size,