某厂区室外中压电缆敷设施工方案(中英文).pdf
《某厂区室外中压电缆敷设施工方案(中英文).pdf》由会员分享,可在线阅读,更多相关《某厂区室外中压电缆敷设施工方案(中英文).pdf(14页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、TDI train-Infrastructure Electrical System InstallationTDI train-Infrastructure Electrical System InstallationMV Cable Pulling Construction PlanMV Cable Pulling Construction PlanTDITDI 联合装置联合装置-基础设施电气系统安装基础设施电气系统安装中压电缆敷设施工方案中压电缆敷设施工方案BARev11/30/200911/26/2009DateDD/MM/YYISSUED FOR COMMENTSISSUED FOR
2、 COMMENTSSTATUSPREPARED BYDOCUMENT REVISIONSCHECKED BYAPPROVED BY目目录录ContentContent一一.概况概况 OVERVIEWOVERVIEW.3.31.11.1工程概况工程概况 PROJECT OVERVIEWPROJECT OVERVIEW.3.31.21.2施工范围施工范围 SCOPE OF WORKSCOPE OF WORK.3.3二编制依据二编制依据 COMPILATION BASISCOMPILATION BASIS.4.4三三 施工工艺流程:施工工艺流程:CONSTRUCTION PROCESSCONSTRU
3、CTION PROCESS.4.4四四.前期预备前期预备 PREPARATIONPREPARATION.4.44.14.1技术预备技术预备 TECHNICAL PREPARATIONTECHNICAL PREPARATION.4.44.24.2材料预备材料预备 MATERIAL PREPARATION.5MATERIAL PREPARATION.54.34.3主要机具预备主要机具预备 MAIN EQUIPMENT PREPARATION.5MAIN EQUIPMENT PREPARATION.54.44.4作业环境预备作业环境预备 WORK ENVIRONMENT PREPARATION.6W
4、ORK ENVIRONMENT PREPARATION.6五五.敷设施工敷设施工 WORK OF CABLE PULLING.6WORK OF CABLE PULLING.65.15.1电缆敷设施工工序电缆敷设施工工序 WORK PROCEDURE.6WORK PROCEDURE.65.25.2机具布置机具布置 LAYOUT OF TOOLSLAYOUT OF TOOLS.6.65.2.15.2.1 电缆的搬运及支架架设电缆的搬运及支架架设 CABLE REMOVCABLE REMOVAL AND CABLE TRAYAL AND CABLE TRAY.6.65.2.25.2.2卷扬机与滑轮的
5、布置卷扬机与滑轮的布置 WINCH AND PULLEY ARRANGEMENT.6WINCH AND PULLEY ARRANGEMENT.65.35.3电缆展放电缆展放 LAY-OFF CABLELAY-OFF CABLE.9.95.45.4电缆敷设、固定电缆敷设、固定 CABLE LAYING AND FIXINGCABLE LAYING AND FIXING.1 11 1六六.覆砂盖砖覆砂盖砖 SPREAD SAND AND COVER BRICKSSPREAD SAND AND COVER BRICKS.12.12七七.回填土回填土 BACKFILL EARTHBACKFILL EA
6、RTH.12.12八八.埋标桩埋标桩 BURYING STAKEBURYING STAKE.12.12九九.挂标志牌挂标志牌 HANGING SIGNS.12HANGING SIGNS.12十十.质量控制质量控制 QUALITY CONTROLQUALITY CONTROL.12.1210.110.1主控项目主控项目 MASTER ITEMSMASTER ITEMS.12.1210.210.2一般项目一般项目 GENERAL ITEMS.13GENERAL ITEMS.13十一十一.成品爱护成品爱护 FINISHED PROTECTION.13FINISHED PROTECTION.13十二十
7、二.质量记录质量记录 QUALITY RECORDQUALITY RECORD.13.1312.112.1 质量保证资料质量保证资料 QUALITY ASSURANCE INFORMATIONQUALITY ASSURANCE INFORMATION.13.1312.212.2 施工记录施工记录 CONSTRUCTION OF RECORD.14CONSTRUCTION OF RECORD.14十三十三.平安生产、文明施工要求和措施平安生产、文明施工要求和措施 SAFETY AND CIVILIZED CONSTRUCTION REQUESTS ANDSAFETY AND CIVILIZED
8、CONSTRUCTION REQUESTS ANDMEASURES.14MEASURES.14一一.概况概况 OverviewOverview1.11.1工程概况工程概况 Project OverviewProject Overview项目名称:TDI 联合装置厂区中压电缆敷设施工。Project name:TDI Train Plant Medium VoltageCable Pulling Work.本工程涉及三个变电站,分别是现有的220/35kV A472 变电站、现有的 35/10kV B301S 变电站以及新建的 35/10kV C581 变电站,工作内容为三个变电站之间和从三个变
9、电站接至MV 用户的电力电缆、控制电缆、接地电缆的敷设。The project involves three substations,namely the existing220/35kV A472 substation,the existing 35/10kV B301S the 35/10kV C581 substation and a newsubstation.This is the power,control and grounding cable pulling among three substations and for MVusers connected to the thr
10、ee substations.1.21.2施工范围施工范围 Scope of WorkScope of Work1)1)A472A472 建筑(建筑(220/35kV220/35kV 变电站)出线回路:变电站)出线回路:A472 Building(220/35kV substation)outlet circuitA472 Building(220/35kV substation)outlet circuit由 A472 变电站引出 3 路 35kV 出线。其中:一路引至 B301S 建筑(35/10kV 变电站)原1#主变,原1#主变电缆将抽出,与新增4#主变连接;另两路引至 35/10kV
11、 C581变电站 1#主变和 2#主变。回路接受FS-YJY-26/35kV-1*300mm2单芯电缆,直埋敷设。去C581 的两路 35kV 线路,敷设时沿不同路径,以避开两回线路同时受损。Pullthree 35V outgoings from A472 substation.Of which:The first outgoing is led to B301S Building(35/10kV substation)the original one#main transformer,pull the original one#main transformer cableout,and c
12、onnect to the adding 4#main transformer;the other two outgoings are led to 35/10kV C581#1 and substation 2#main transformer.Use FS-YJY-26/35kV-1*300mm2single-core cables for Loopand buried pulling.Two 35kV lines to C581 are laid along different paths to avoid damage of the twoloops.2)2)B301SB301S 建筑
13、(建筑(35/10kV35/10kV 变电站)出线回路:变电站)出线回路:B301S building(35/10kV substation)outlet circuit:B301S building(35/10kV substation)outlet circuit:由 B301S 变电站引出 7 路 10kV 出线。全部引至 B399 中心制冷站。回路接受 10kV 截面为 95mm2的三芯铠装电缆,由 B301S 南面现有的电缆井引出直埋至装置。Pull 7 10kV outgoings from B301Ssubstation to B399central refrigeration
14、station.Loop uses 10kV three-core armored cable withcross-section 95mm2 and pull out from the existing cable well in the south of B301S then buried lay tothe device.3)3)C581C581 建筑(建筑(35/10kV35/10kV 变电站)出线回路:变电站)出线回路:C581 building(35/10kV substation)outlet circuit:C581 building(35/10kV substation)ou
15、tlet circuit:由 C581 引出 10 路 10kV 线路,分别为 A507 的四台变压器,B551 的两台变压器,B553TDA 装置氢气压缩机 2 台,C521 盐酸装置氯气压缩机 1 台,盐酸压缩机 1 台提供电源。其中,变压器回路接受 10kV 截面为 185mm2的三芯铠装电缆,马达回路接受 10kV 截面为 95mm2的三芯铠装电缆。以上电缆线路均沿规划路径埋地敷设。10 10kV lines led from C581 are used to supply power toA507s four transformers,B551 two transformers,B5
16、53TDA 2 sets of hydrogen compressor unit,C521hydrochloric acid chlorine gas compressor unit,and hydrochloric acid compressor unit respectively.Among them,transformer circuit uses x 3-core armored cable with 10kV cross-section 185mm2,motorcircuit uses three-core armored cable with 10kV cross-section
17、95mm2.All cable lines will be laidunderground along the planning path.4)4)接地电缆回路:接地电缆回路:Ground cable loop:Ground cable loop:从 A472 敷设一根 95mm2裸铜线去 C581,同时从C581 敷设四根 95mm2裸铜线,分别引至B551、A507、B553 和 C521,作等电位联结。以上电缆线路均沿规划路径埋地敷设。Lay a 95mm2barecopper wire to C581 from A472.Meanwhile lay four bare copper w
18、ires to B551,A507,B553 and C521for equipotential bonding.All cable lines will be laid underground along the planning path.Overview5)5)控制电缆回路:控制电缆回路:Control cable circuit:Control cable circuit:安装在 HCL 装置现场的 3.6MW 马达上的电流信号通过一根直埋敷设的铠装控制电缆直接接入10KV 开关柜。The current signal installed on 3.6MW motor in the H
19、CL devices site passes through aburied armored control cable direct access to 10KV switchgear.由变压器出线柜去 C581 以外的变压器,接受两根分别为 10*2.5mm2、4*2.5mm2屏蔽铠装控制电缆,由中压转接柜引出,与中压电缆同路径敷设至相关变压器室。其中,10*2.5mm2 电缆直接接至温控箱,4*2.5mm2 电缆可集中从某间变压器室引出,沿桥架至相关 PCS 楼 ATS柜。Transformeroutlet cabinets are connected to other transfor
20、mers not in C581 by using two 10*2.5mm2,4*2.5mm2shield sheathed control cable respectively.The 10*2.5mm2 cable directly is connected to thetemperature control box and 4*2.5mm2 cable are led out from transformer room,along the bridge tothe relevant PCS floor A TS cabinet.二编制依据二编制依据 Compilation BasisC
21、ompilation Basis1)依据电气包(中压部分)招标文件及招标图纸编制而成。According to Electric package(MV)thetender and tender drawings.2)在充分争辩工程的客观状况和施工特点,结合我公司类似工程施工阅历的基础上编制的。Basedon full study on construction characteristics and objective situation and combined with similarconstruction experience.3)在本方案编制过程中,严格执行国家现行建筑和安装工程施工
22、及验收规范、规程、标准、设计规范。具体如下:In this compilation process,strictly implement current national construction andinstallation construction,acceptance norms,procedures,standards,and design specifications.Asfollows:电气装置安装工程电缆线路施工及验收规范GB50168-2006 Electrical installation cableconstruction and acceptance standards
23、 GB50168-2006电气装置安装工程接地装置施工及验收规范GB50169-2006 Electrical installation earthingconstruction and acceptance standard GB50169-2006建筑电气工程施工质量验收规范GB503032002 Building Electrical Construction QualityAcceptance GB50303-2002三三 施工工艺流程:施工工艺流程:Construction ProcessConstruction Process前期预备电缆直埋敷设施工铺沙盖砖回填土埋标志桩挂标志牌P
24、reparationCable buried pulling spread sand and build bricks backfillbury sign stakehang signs四四.前期预备前期预备 PreparationPreparation4.14.1技术预备技术预备 Technical PreparationTechnical Preparation1)针对本工程特点编审具体的电缆沟施工作业指导书,及时组织图纸会审。Compile particular cabletrench construction engineering guide book as per project
25、characteristics and organize promptlydrawings joint examination.2)依据上海市电力建设工程施工工艺实施细则结合本工程实际编写电缆沟施工工艺卡,并组织实施。Compile construction technique cards according to the Shanghai Municipal Electric PowerConstructionEngineeringConstructionTechnology ImplementationDetailsandorganizeitsimplementation.3)施工人员全面