1、CHAPTER 15 AGGREGATE PLANNINGChapter OverviewAggregate planning is the first step in a process that takes the long-range strategic plan and converts it to the operational level. The aggregate plan is maintained primarily for determining the amount of materials and labor requirements for the next 12
2、months. Specifically, this chapter provides an overview of aggregate planning.Major Points of ChapterThe aggregate plan is used to set product rates by broad groups for the intermediate term, generally 6 to 18 months.1. The process of aggregate planning can be very formal or it can be informal. Many
3、 small companies use informal methods of aggregate production planning.2. There are three basic production-planning strategies-chase, stable workforce, and level strategy.3. The relevant costs are basic production costs, labor costs, costs associated with changes in the production rate, inventory ho
4、lding costs, and backlogging costs.4. Many companies use trial-and-error charting and graphical methods for aggregate planning. However, more sophisticated approaches include linear programming, Linear Decision Rule, and various heuristic methods.5. Yield management is used for aggregate planning in
5、 services. It attempts to integrate demand and supply management simultaneously. Specifically, it tries to sell all available capacity, but not turn away a full paying customer.Review and Discussion QuestionsWhat are the basic controllable variables of a production planning problem? What are the fou
6、r major costs?Basic controllable variables: production rate, work force levels, labor costs, and inventories.Major costs: production costs (fixed and variable), production rate change costs, inventory holding costs, and backlog costs.1. Distinguish between pure and mixed strategies in production pla
7、nning.Pure strategies use only one variable to absorb demand fluctuations. Mixed strategies involve two or more pure strategies.180Level StrategyLevel StrategyLa Buena Compania de EspanaJanFebMarAprMayJunTotalForecasted Demand1,7401,7402,4603,2402,2201,86013,260On-Hand Inventory300AveNet Demand1,440
8、1,7402,4603,2402,2201,86012,960 2,160Aggregate Plan:Production2,1602,1602,1602,1602,1602,16012,960Number of Workers363636363636Number Hired1100000Number Fired000000Ending Inventory720420(300)(1,080)(60)300Cumulative Inventory7201,140840(240)(300)0Incremental Costs:Hiring Costs2,200000002,200Firing C
9、osts0000000Inventory Costs1,4402,2801,6800005,400Stockout Costs0002,4003,00005,400Totals:3,6402,2801,6802,4003,000013,000Total Incremental Costs of Level Strategy = 13,000 Based upon cost, the level strategy should be used.Chapter 15La Buena Compania de EspanaLevel Strategy with OvertimeJanFebMarApr
10、MayJunTotalForecasted Demand1,7401,7402,4603,2402,2201,86013,260On-Hand Inventory300360420000AveNet Demand1,4401,3802,0403,2402,2201,86012,180 2,030Aggregate Plan:Production1,8001,8001,8001,8001,8001,80010,800Number of Workers303030303030Number Hired500000Number Fired000000Overtime production002401,
11、44042060Ending Inventory3604200000Cumulative Inventory7201,1401,1401,1401,1401,140Overtime Hours:006003,6001,050150Incremental Costs:Hiring Costs1,000000001,000Firing Costs0000000Inventory Costs1,4402,2802,2802,2802,2802,28012,840Stockout Costs0000000Overtime Premium002,40014,4004,20060021,600Totals
12、:2,4402,2804,68016,6806,4802,88035,440Total Incremental Costs of Overtime Strategy = 35,440The level strategy is still the best.2. An alternate plan would be to go with a level work force of 36 people and then work overtime to eliminate any stockouts. One problem with working overtime, especially du
13、ring the peak month is that workers will become very tired. This can cause a decrease in productivity and poor workmanship.190Compare the best plans in the C&A Company and the Tucson Parks and Recreation Department. What do they have in common?The plans have little in common. The C&A plans used a co
14、nstant low work force and subcontracting. The Tucson Parks plan, on the other hand, used a constant high work force and no subcontracting.3. How does forecast accuracy relate, in general, to the practical application of the aggregate planning models discussed in the chapter?A highly accurate forecas
15、t encourages the use of deterministic techniques such as linear programming which in turn permits the development of near optimal plans. Clearly, though, any reduction in uncertainty enhances the likely accuracy of any production planning method.4. In which way does the time horizon chosen for an ag
16、gregate plan determine whether it is the best plan for the firm?Many factors affect the selection of an appropriate time horizon. Perhaps, the most important is what the firm intends to plan during that time period. An aggregate plan implies a period of up to 18 months wherein the firm takes its for
17、ecast and plans production using inventory, work force size, overtime and under time, subcontracting, and backlogging orders to achieve a reasonable schedule at reasonable costs. A very stable firm in a very stable environment with a very stable demand really doesnt need to go out very far with its
18、aggregate plan. However, when there is variation, especially when this variation is considerable, then a longer aggregate plan will show the need to find subcontractors, new workforce availability, etc. Planning for these can start early.5. Under what conditions is the concept of yield management mo
19、st appropriate for service operations?To gain the maximum from yield management, a service should have the ability to segment its markets, high-fixed and low variable costs, product perishability, and the ability to presell capacity.ProblemsProblemType of ProblemDifficultyCheck Figure in Appendix DA
20、ggregate planning1YesModerateYes2YesModerate3YesModerate4YesModerateYes5YesModerate6YesModerate7YesModerateChapter 15ForecastBeginning Production Production Production Overtime ActualEnding inventoryWorkers Workers hired laid offinventoryrequiredhours requiredhours availablehoursproductionFall1000()
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 运营管理基础 4E-戴维斯英文IMChap015 运营 管理 基础 戴维 英文 IMChap015
限制150内