沉管隧道介绍英文.pptx
《沉管隧道介绍英文.pptx》由会员分享,可在线阅读,更多相关《沉管隧道介绍英文.pptx(44页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、第1页/共44页Immersed tunnels are,more advantegous as a subaquous solution in soft soilsincreasingly used alternative to traditionally used shield tunnelling,without having the risks associated with pressure chambers and inrush of water.also suitable in water deeper than it is possible with the shield me
2、thod,which essentially is restricted to less than 30 m of water(concerning the maximum air pressure at which workers can safely work).Advantegous as there is less loss in height than with tunnelling deeply under the riverbed,and the tunnel may therefore be shorter overall.第2页/共44页The worlds longest
3、and deepest application to date is the twin-tube subway crossing of San Francisco Bay,constructed between 1966 and 1971 with a length of 3.6 miles(5,8 km)in a maximum water depth of 41 m.The 100 m long,15 m wide sections were constructed of steel plate and launched by shipbuilding procedures.The fir
4、st tunnel of the concrete type was constructed in 1940 in Rotterdam under the Maas estuary.第3页/共44页The most profound effect of an immersed tunnel on the environment concerns the element it is meant to bypasswater.The influence of the tunnel on the groundwater and the surface water in the area plays
5、a predominant role in the tunnel design and construction methods.An aspect of more recent concern affecting construction is the possible presence of contaminated soils that must be removed for the tunnel trench.Ways of removing these soils and transporting them to depositories that are especially eq
6、uipped to receive them are environmental problems requiring novel techniques and quality control procedures.The more traditional environmental aspects are those encountered on any construction job:noise,dirt,and traffic hindrance.第4页/共44页The top of the tunnel should be protected by adequate protecti
7、ve backfill,extending about 30 m on each side of the structure and confined within dykes or bunds.The fill must be protected against erosion by currents with a rock blanket,protective rock dykes or other means.Tides and current effects of the waterway must be evaluated to determine conditions during
8、 dredging and tube sinking operations.Importantly,dredging and backfilling operations should be executed in such a manner as to limit disturbance in the natural ecological balance at the construction site.Governmental agencies having jurisdiction over environmental protection,natural resources or lo
9、cal conditions must be consulted and approval of authorities should be obtained in the preliminary design stage.第5页/共44页FoundationThe foundation method to be used must be chosen with due consideration,first of all,for the subsoil conditions and the degree to which the tunnel will be subject to dynam
10、ic loadings,and earthquake loadings in particular.Pile foundations are an option but this solution has been used for a few tunnels only.For both steel and concrete types of tunnels,the main tasks are:Excavation of a tunnel trench to specifications and to keep it free of siltation that may be detrime
11、ntal to the permanent foundation until this foundation has been constructed and the tunnel has been brought to rest on it.Construction of watertight and durable tunnel elements.Installation of the tunnel elements in the tunnel trench.Construction of watertight and durable joints between the tunnel e
12、lements.Construction of a durable foundation for the tunnel.第6页/共44页Once completed,an immersed tunnel is no different operationally from any other tunnel.However,it is built in a completely different way.The Construction technique:A trench is dredged in the bed of the water channel.第7页/共44页Tunnel Tr
13、ench DredgingThe dredging works required for the construction of an immersed tunnel will normally comprise some,or all,of the following items:Dredging of a casting or launching basin.Dredging of test pits in the waterway for evaluation of siltation of tunnel trench.Widening of the existing navigatio
14、n channel in order to provide temporary navigation channels outside the marine working area.Compensation grouting to make up for the reduction of the waterway cross section caused by the permanent tunnel works,and thereby avoiding changes in hydrographical and biological conditions in the waterway.D
15、redging of the tunnel trench for the immersed tunnel section.Dredging of an access channel between the casting/launching basin and the tunnel trench.Maintenance dredging.第8页/共44页The dredging volume is generally in the order of l million m3 per km for a typical four-lane motorway tunnel.The excavatio
16、n must provide space for the prefabricated tunnel body;the sand or gravel foundation under the body as wells as the protective backfill on the sides and on the top of the tunnel.Because the top of the backfill has to be kept below the existing or future navigation channel profile,a trench bottom lev
17、el at between 25 and 30 m below Low Water level is quite common.Immersed tunnels in deep or open sea may require specially built dredgers.第9页/共44页Except for cases where very soft subsoil,deemed unsuitable for support of the tunnel,has to be removed and replaced by suitable materials,the general requ
18、irements for the dredging of the trench bottom are:A clean,even surface,as close as possible to the upper acceptable limit in order to avoid the economic consequences of having to fill overdredged areas;A minimum disturbance of the remaining exposed upper soil layers in the trench bottom,in order to
19、 limit the changes in the geotechnical characteristics of the subsoil.The possible physical disturbance and softening of the exposed soil layers in the trench bottom,particularly in cohesive subsoils,can have a considerable influence on the geotechnical behaviour of these soil layers later-and,hence
20、,on the quality of the tunnel support as a whole.This in turn influences the design of the structural tunnel body and,thus,eventually the overall economy.These technical requirements are met by:Using the proper type of dredger(s).Careful controlling the position of the cutting tool,bearing in mind t
21、hat the dredging normally has to be done in tidal waters and sometimes in waters subject to swell and waves.Careful planning the dredging operation in order to avoid undesirable failures of the slopes.Timing of the dredging operation,in order to limit the time that the trench bottom is exposed and,a
22、t the same time,to limit the sedimentation caused by subsequent dredging nearby.第10页/共44页第11页/共44页Construction of Tunnel Elements The tunnel elements are made fully or partially buoyant by means of temporary bulkheads installed at the element ends.In addition to providing proper structural strength
23、and controlling the weight of the element,the main design and construction task of the reinforced concrete tunnel is to provide a watertight structure.For many years,the answer was to wrap the tunnel element in a watertight membrane composed of steel on the bottom,outer walls and even on the roof.Al
24、ternatively,bituminous membrane has been used on the outer walls and roof.In recent years,reinforced concrete tunnels without a membrane at all are being used.Above all,this will require sophisticated control of concrete temperature during hardening to avoid cracking.In order to reduce the developme
25、nt of cracks during hardening,primarily in the walls when they are cast after the bottom slab,cooling of the lower part of the walls has been the practice for many years.Insulation of the formwork and careful sequencing of stripping of the forms are also used to control the concrete temperature.Impr
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 隧道 介绍 英文
限制150内