1、2023年河南PMP资格认证考试考试真题卷(1)本卷共分为1大题50小题,作答时间为180分钟,总分100分,60分及格。一、单项选择题(共50题,每题2分。每题的备选项中,只有一个最符合题意) 1.Which of the followings is far from Integrated Change ControlA) Influencing the factors that create change to ensure that changes are agreed upon.B) Determining that a change has occurred.C) Ensuring
2、the integrated performance baseline doesnt change.D) Managing the actual changes when and as they occur.2.While the project is being completed, management requests a change. What is the FIRST thing the project manager should doA) Comply with the request if possible.B) Obtain a complete understanding
3、 of the scope of the change.C) Teel the customer that a change will be coming.D) Ask the team to accept the change.3.All of the following are part of an effective change control system EXCEPTA) proceduresB) standards for reportsC) meetingsD) lessons learned4.When should a project baseline be changed
4、A) When a major delay occurs.B) When an official change is made.C) When a cost increase occurs.D) Changes should never be made in the baseline.5.Your companys project review committee (PRC) meets quarterly to review any project with a budget exceeding $2 million. You recently were promoted to senior
5、 project manager and were assigned one of these largest projects, the development of a next-generation, computer-aided manufacturing process. The PRC asked you to present the projects objectives, work content, and deliverables at its next meeting. Accordingly, you need to prepare which one of the fo
6、llowing documentsA) project charter.B) product description.C) scope statement.D) WBS.6.All of the following is true for a project baseline EXCEPT _.A) it is the original approved planB) it includes approved scope changesC) it is useful in detecting project variancesD) it is useful in preparing the W
7、BS7.Your project has a number of different work results. You are collecting information about these work results such as what costs have been incurred or committed and which deliverables have been completed and which remain outstanding. You will use this information in which of the following process
8、esA) Direct and manage project execution.B) Perform integrated change control.C) Reprot performance.D) Verify scope.8.You are a project manager who was just assigned to take over a project from another project manager who is leaving the company. The old project manager tells you that the project is
9、on schedule only because he has had to constantly push the team to perform. What is the FIRST thing you should do as the new project managerA) Check risk status.B) Check cost performance.C) Determine a management strategy.D) Tell the team your objectives.9.Close procurements is a process that involv
10、esA) customer satisfaction analysis and final paymentB) administrative closure and archiving recordsC) final contractor payment and lessons learnedD) product verification and administrative closure10.What is a project management information systemA) Computerized status tracking system.B) Manual stat
11、us tracking system.C) Method to determine and archive how the project is doing.D) Method to gather, integrate, and disseminate what and how the project is doing.11.The project is not going well and many changes are being made. Which of the following should you do FIRST to gain control of the project
12、A) Review the scope of work with the stakeholders.B) Create a new change form.C) Remind everyone of the change procedures.D) Ask management for help.12.At the end of each project, the project team should prepare a lessons learned summary that focuses on all the following EXCEPTA) sharing best practi
13、ces with other project teams in the organizationB) warning others of potential problemsC) suggesting methods to mitigate risks effectively to ensure successD) sharing only positive aspects of the project for future replication elsewhere in the organization13.Close procurements is similar to close pr
14、oject in that they both involve:A) Product verification.B) Kick off meetings.C) Quality assurance activities.D) Creation of the scope verification plan.14.An important task of project managers is to identify the relevant goals of each project. An approach that can help managers set up and achieve th
15、ose goals is management by objectives (MBO). MBO specifically addresses all the following EXCEPT _.A) establishing unambiguous and realistic objectivesB) periodically evaluating whether project objectives have been achievedC) promoting participation, team building, and commitment to the projectD) an
16、alyzing and reducing risk and determining how to handle it when it occurs15.Which two process groups provide potentially cyclical inputs to each otherA) Executing processes and controlling processes.B) Planning processes and executing processes.C) Planning processes and controlling processes.D) Cont
17、rolling processes and closing processes.16.Administrative closure should not be delayed until project completion becauseA) useful information may be lostB) the project manager may be reassignedC) project team members may be reassigned by that timeD) sellers are anxious for payments17.The competitive
18、, complex project management environment has increased pressure for on-line performance Schedule control is one important way of avoiding schedule delay. Time management corrective action often involves expediting certain activities to ensure that they are completed in a timely manner or to ensure t
19、hat they are completed with the least possible.delay. To plan and execute schedule recovery, corrective action frequently requires _.A) making unpopular decisionB) immediately re-baselineC) root cause analysisD) resource leveling18.A project planning methodology is any structured approach used to gu