1、Bill of ProcessManufacturing Requirements ProcessBill of EquipmentBOP-MR training class4.pptPage Bill of ProcessBOP-MR training class4.pptPage Global Bill of Process(BOP)Globally common,balanced,and documented approach for Manufacturing and Assembling VehiclesBuild sequenceOperation contentDimension
2、al strategySubassembly design strategyMajor tool and equipment interfaces to the productThe BOP impacts both the process and the product and consists of the following:The BOP does not prescribe specific equipment,level of automation/manpower,or plant layoutBOP-MR training class4.pptPage Press and Di
3、eBODYPAINTGA(General Assembly)GMs Manufacturing Systems:Each has a Bill of Process(BOP)PowertrainBOP-MR training class4.pptPage Global Bill of Process(BOP)Global Bill of Process(BOP)Common Build Sequence and Operation ContentCommon Build Sequence and Operation ContentBOP-MR training class4.pptPage G
4、lobal Bill of Process(BOP)Global Bill of Process(BOP)Common Build Sequence and Operation ContentCommon Build Sequence and Operation ContentBOP-MR training class4.pptPage Global Bill of Process(BOP)Global Bill of Process(BOP)Common Build Sequence and Operation ContentCommon Build Sequence and Operati
5、on ContentBOP-MR training class4.pptPage A common,global,world-class,flexible manufacturing system to deliver high quality at competitive cost exceeding customer expectationsBOP VisionGuiding PrinciplesBOP-MR training class4.pptPage Protect Manufacturing Portfolio FlexibilityCommon Flexible Main Lin
6、eProcess Driven Product Design RequirementsOptimize Manufacturing EfficiencyProduct Differentiation and Differences in Content Level are Driven to Subassemblies or Modules off of the Main LineRegional Requirements Determine Automation LevelOn-Line Pilot with Zero Lost UnitsPhased ImplementationBOP C
7、ompatible BOM ComponentsConcurrent with Product Architecture ChangesGlobal BOP ObjectivesBOP-MR training class4.pptPage BOP Implementation StrategyMigrate to BOP Compatible Product ArchitecturesConvert Uncommon,Inflexible Manufacturing Systems to Common,Flexible Manufacturing Footprint(BOP)-BUT-Spen
8、d Money to Implement BOP Only When Product&Manufacturing Systems MUST Be ChangedNew Product and New“Greenfield”Plant:BOP CompliantBOP-MR training class4.pptPage Compliance vs.CompatibilityCompliance:This specific product or process meets 100%of the applicable BOP requirements.Compatibility:This spec
9、ific product does not meet 100%of the applicable BOP requirements,but it can be processed on a BOP compliant process-OR-This specific process does not meet 100%of the applicable BOP requirements,but it can accommodate a BOP compliant product.BOP-MR training class4.pptPage Manufacturing Requirements
10、ProcessCompliance vs.CompatibilityBOP-MR training class4.pptPage What Do We Mean by“Manufacturing Requirements(MR)”?Global,Common Method to Bring BOP Directly Into Vehicle Development and Manage Program Manufacturing RequirementsInitial List Brought in From the BOPTargeted BOP Implementation Based o
11、n Program SpecificsImplement BOP When Money Is Spent on Product or ProcessCriteria That Enable a Vehicle to Be Built in GM Plants,Comprehending:Assembly&Build SequenceEquipmentVehicle Size EnvelopeEfficiency,Ergonomics,etc.Two Types:1.Product(a.k.a.PDPD,or Process Driven Product Design)2.Process BOP
12、-MR training class4.pptPage MR Example Subassembly Design Strategy:103Product1.7 A spider subassembly will consist of:a right and left motor compartment lower rail subassembly,a#1 bar subassembly,and a bumper beam or rigid cross member to tie the right and left rails together at the front.203 Produc
13、t 1.9 Front wheel house assembly is brought to the motor compartment main line as a completed subassembly/module.Station LevelManufacturing RequirementTypeBOP-MR training class4.pptPage MR ObjectivesEstablish Lean,Globally Common Process&Tools Integrated with Existing Corporate ProcessesImprove Comm
14、unication Between Product and Manufacturing EngineeringStrengthen Voice of Manufacturing in Vehicle Line Teams(VLTs)Implement Process Driven Product Designs(PDPD)Facilitate Engineering to RequirementsDrive BOP ImplementationEnable Capital ReuseBOP-MR training class4.pptPage 70 3 Product1.30 The cowl
15、 must have fore-aft and cross car slip to the dash sub assembly.Station Level Address Manufacturing Requirement MR Example Dimensional Strategy-BodyBOP-MR training class4.pptPage 543Product543 Product3Product543 Product541.20 (See drawing Item A)Design of motor compartment lower side rails R/L inclu
16、des a tooling datum locator for F/A and C/C,consisting of a 40.1+0.1/-0.0 mm hole,pierced and flanged upward.(NOA 001)1.20.2 (See drawing Item C).Design of motor compartment lower side rails R/L includes principal U/D locators carried throughout the motor compartment and underbody build process.Heig
17、ht is held as a pattern for targeted plants and is symmetrical left to right.(NOA 001)1.20.1 (See drawing Item B)Design of motor compartment lower side rails R/L includes 40.1+0.1/-0.0 mm carrier hole,pierced and flanged at the same time as holes at “A”,pierced and flanged upward,located 15.5 mm for
18、ward of location“A”.(NOA 001)MR ExampleMajor Tool and Equipment Interfaces-Body BOP-MR training class4.pptPage Agreement MilestonesPre-VPI RequirementsArchitecture-InitialBOM Row SelectionConcept PartsStructure PartsIntegration PartsBOP-MR training class4.pptPage Manufacturing RequirementsProcess Fl
19、ow-ExampleMVNSxx/xx/xxxx/xx/xxEOASFSOPCSOG/APaintBodyBOPReqtsLoad MRDBComplete BOP&BOE TargetsMR Game PlanMR Game PlanMRRMRRAVDRVPIRManagement ApprovalsVDP Execution WorkBoundary ConditionsDesign IntentAlternatives DevelopmentDesign Theme AlternativeVPI PrepGMNA OnlyCSPRVPIDSI-164-145-131-117-106+26
20、-176-158Add Additional Program MRsPre-VPI AgreesExecute ProductVerify T2Arch BOM AgreesBody Arch BOM AgreesProcessVerify Integration Agrees(SORs)IntegrationAgrees(others)Execute T2ProductVerify ProcessVerify Structure Agrees(SORs)StructureAgrees(others)Execute T2ProductVerify ProcessVerify Concept A
21、grees(SORs)ConceptAgrees(others)Execute T2ProductVerify ProcessVerify BOP-MR training class4.pptPage BOP-MR training class4.pptPage AgreementAn indication of acceptance of a design intent for either the product or process discussed in the manufacturing requirement.The owner is agreeing to and will s
22、upport the words in the program requirement text of a manufacturing requirement.It is not necessary that the owner(s)of a manufacturing requirement have everything finalized,merely that they agree on what they should be designing to.When the owners agree,the manufacturing requirement becomes locked.
23、BOP-MR training class4.pptPage BOP-MR training class4.pptPage ExecutionIncorporate agreed manufacturing requirements into the product and process designs This is the responsibility of each Manufacturing Engineer and Product EngineerProgram Vehicle DesignProgramManufacturingSystem DesignBOP-MR traini
24、ng class4.pptPage GBIST 9/18/01VerificationWhat is Verification?A confirmation of what the program executed relative to the agreed Manufacturing RequirementsWhy Perform Verification?Have we created potential problems/cost for the program (or the next off this design)?Did we do what we said we would
25、do?Are we driving to the common manufacturing system(BOP)?BOP-MR training class4.pptPage BOP-MR training class4.pptPage ME ResponsibilitiesReview initial BOP requirementsWrite/modify program requirement textEstablish all PROCESS requirements Evaluate and set BOP Target and StatusEnter ME Agreement S