厕浴间聚氨酯涂膜防水层(Polyurethanecoatingwaterprooflayerfortoiletandbathroom).pdf
《厕浴间聚氨酯涂膜防水层(Polyurethanecoatingwaterprooflayerfortoiletandbathroom).pdf》由会员分享,可在线阅读,更多相关《厕浴间聚氨酯涂膜防水层(Polyurethanecoatingwaterprooflayerfortoiletandbathroom).pdf(12页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、厕浴间聚氨酯涂膜防水层(Polyurethane coating waterproof layer for toilet and bath room)Polyurethane coating waterproof layer for toilet and bath room The technical disclosure is applicable to the construction of waterproof and cold work with polyurethane coating on toilets,toilets and other floors.1.material re
2、quirements (1)polyurethane coating waterproof material(double component).The factory certificate should be issued.The component A is made of polyurethane and diisocyanate as raw materials,through polymerization and the reaction products containing isocyanate terminated polyurethane Ester prepolymer,
3、the appearance of light yellow thick,barreled 20kg per barrel.The second component is made of accelerator,curing agent,toughening agent,anti mildew agent,bulking agent and diluent mixing process;the appearance of red,black and white,Yellow and coffee paste,bottled,40kg per barrel.The component A is
4、stored in a room ventilated dry place,storage period not exceeding 6 months.The B component is stored in the chamber and the storage period is not more than 12 months.Two sets of materials should be kept separately,no mixing in one room;remaining after use Materials should be tightly sealed to preve
5、nt material failure.Main technical performance:Solid content:93%The tensile strength is not less than 0.7Mpa Elongation at break ranged from 300%to 400%Heat resistance of 80 degrees,not flowing Low temperature flexibility:20 degrees around the 20mm diameter round bar,no crack Water impermeable:0.3Nm
6、m2.(2)No.325 ordinary portland cement is used to prepare cement mortar protective layer.Medium sand:mud content is not greater than 3%.(3)phosphoric acid or benzene sulfonyl chloride:used as retarder.Two lauric acid two butyl tin:used as a coagulant.Ethyl acetate:Rinse gel on hand Xylene:use dilutio
7、n and cleaning tools Polyester nonwoven fabric or glass cloth:Specifications for 60g 2.main machines and tools Should be equipped with an electric mixer(power 0.3 0.5KW,200500 to min),mixing barrel(volume 10L),paint bucket(3L),plastic Material or rubber scraper,rolling brush,paint brush,spring scale
8、,dry powder fire extinguisher,etc.3.operating conditions (1)the basic surface coating waterproof layer,dust and other debris must be cleaned,the surface residual mortar lumps and protrusions should shovel Flat,clean,light pressure,yin and Yang Kok should put into arc or obtuse angle.(2)the surface c
9、oating of the waterproof layer should be kept dry,and to smooth,firm,no hollowing,cracks and other defects from the sand.(3)the floor drain at the leveling layer,the Guan Gen,the outlet and the root(edge)of the sanitary ware should be rounded.The slope meets the design requirements.The components mu
10、st be firmly installed and tightly sealed.(4)to highlight the ground pipe root,floor drain,drainage,yin and Yang corner,etc.,should first do additional layer wall repair treatment,brush polyurethane bottom adhesive After inspection and completion of the hidden works acceptance.(5)all kinds of materi
11、als used for waterproof layer,the base treatment agent,xylene and other flammable substances,storage and storage should be far away from the source,construction exercises Fireworks should be strictly prohibited during the process.(6)the construction of waterproof layer shall not be carried out on ra
12、iny days or windy days,and the environmental temperature during winter construction shall be no less than 5 degrees centigrade.4.operation process Technological process:Clean the surface of the base layer,detail treatment,preparation of base rubber,brushing the bottom rubber,brushing the bottom glue
13、(equivalent to cold base oil),adding the additional layer of detail The first coating second times coating third times coating waterproof layer construction waterproof layer test water protection layer finishing layer construction waterproof layer Two water test to waterproof layer acceptance (1)bef
14、ore the construction of waterproof layer,the dust,debris and so on on the base surface should be removed and cleaned with a clean damp cloth.(2)the basic surface coating waterproof layer,no uneven,loose sand,hollowing,cracking and other defects.Water content is generally not greater than 9%,The surf
15、ace of the base uniform white,no watermark.(3)brushing the base rubber is equivalent to cold base oil:1)prepare the base rubber.First,add a polyurethane and B material to toluene,the ratio is 1:1.5:2(weight ratio),and stir evenly.The amount of preparation should be specific Circumstances should not
16、be too much.2)brushing the base adhesive,Will be prepared by the top of the rubber mixture,with a long roll brush evenly coated at the base surface,brushing amount of 0.15:0.2kgm,Painted after the normal temperature season 4h,when the handle is not sticky,you can do the next process.(4)coating water
17、proof layer construction:1.material preparation:Polyurethane waterproof material is polyurethane nail material,polyurethane,ethyl material and xylene,the ratio is 1:1.5:3(weight ratio);in the construction,coating waterproof material The mixture ratio should be measured accurately,and the electric mi
18、xer must be used for stirring.2)make additional layers in detail:Prominent floor drain,Guan Gen,water outlet,sanitary ware and so on root(edge),yin and yang angle and so on weak parts,should do before large-area besmear brushs A cloth,two oil waterproof additional layer,after the drying of the rubbe
19、r table,the fabric will be cut into the same size as the floor drain,pipe root and the same shape,and will be widened around 20cm cloth cover In the pipe,root and other details,and besmear coating waterproof material,after the normal temperature 4H table dry,and then brush second coating waterproof
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 厕浴间 聚氨酯 防水层 Polyurethanecoatingwaterprooflayerfortoiletandbathroom
链接地址:https://www.taowenge.com/p-80830639.html
限制150内