1、2022项目管理师考试题目下载5节2022项目管理师考试题目下载5节 第1节 191 The term that best describes the right to manipulate or change others is called?A. AuthorityB. PowerC. LeadershipD. CoercivenessE. Project charter正确答案:A Ensuring that all work is both authorized and funded by contractual documentation is the responsibility
2、of:AThe project managerBThe functional managerCThe project sponsorDThe clientEAll of the above正确答案:A 项目经理应该A、 控制所有信息B、 尽力控制沟通C、 委托控制沟通D、 通过沟通系统获得足够的关于冲突的信息正确答案:B 在下列哪类网络图中不使用虚拟活动?A、 CPMB、 DetailedC、 PDMD、 PERTC正确答案:C 148 Which of the following is a formal invitation that requests a formal response t
3、hat describes the method of work and associated compensation.A. Request for quotation (RFQ)B. Request for proposal (RFP)C. Request for bids (RFB)D. Invitation for bids (IFB)E. Letter of intent (LOI)正确答案:B2022项目管理师考试题目下载5节 第2节 Upon completion of 75% of the project, the original schedules and cost est
4、imates that were submitted at the inception of the project are referred to as the:A . Baseline costsB . Budgeted costs.C . Estimates upon completion costsD . Scheduled costsE . None of the above正确答案:A 29 When working in an environment that uses learning curves, the most effective plan for creating t
5、he perception that pay is related to performance is to provide the team members with an individual salary plus bonus based uponA. Individual productivityB. Cost effectivenessC. Group or team productivityD. Rating system developed by the project managerE. All of the above正确答案:A 157 Sensitivity analys
6、is can be used in risk analysis to:A. Substitute for uncertainty analysis in risk quantificationB. estimate the level of risk aversion adopted by managementC. estimate the effect of change of one project variable on the overall projectD. A and BE. All of the above正确答案:C 109 Monte Carlo simulation:A.
7、 Was originally developed by Dr. CarloB. Is a European technique for assessing project risksC. assumes the future risk events will occur at random according to predetermined probability distributionsD. is a technique to stimulate create risk event resolutionE. A, B and C only正确答案:C 以下哪一项使项目小组建设的基本原则
8、A、 进行经常性的绩效评估B、 保证每个团队成员向他的职能经理和项目经理报告工作C、 尽早开始团队建设D、 尽力解决团队的政治问题正确答案:C2022项目管理师考试题目下载5节 第3节 A work breakdown structure is most useful for:A.identifying individual tasks for a projectB.scheduling the start of tasksC.developing a cost estimateD.determining potential delaysE.A and C正确答案:EE 哪一个术语对要求潜在卖