1、21年项目管理师考试真题及详解5卷21年项目管理师考试真题及详解5卷 第1卷 159 The Delphi Method is _ .A. used to derive a consensus arriving at a convergent solutionB. useful in determining probability relating to future events.C. used with questionnaires based on established scenarios.D. continued as an iterative process until a sol
2、ution is reached.E. All of the above正确答案:E 在风险应对控制中,纠错行动主要由( )组成?A执行已计划的风险应对B改变进度和成本基准计划C更新概率和价值的估算D更新风险管理计划正确答案:A LOB 技术是最适用于_的一种项目执行情况报告技术.a. 展示未来工作以推动相关任务分析b. 向顾客展示在生产或工艺过程中不同工序之间的关系.c. 确定哪种工作顺序将花费最长的项目完工时间d. 向客户保证当其需要时其所购买的货物一定可用.e. 确定已完成的努力哪些是正面的,哪些是负面的以期将注意力着重于应改进的领域.正确答案:D70. d. Assure the cu
3、stomer that the articles it is buying will be available when needed Best suited for large-quantity production jobs, the LOB technique shows the status of the effort at a given point in time. LOB is often used in firm-fixed-price contracts. Assigning resources in an attempt to find the shortest proje
4、ct schedule consistent with fixed resource limits is called resource _.A.Allocation.B.PartitioningC.LevelingD.Quantification.E.None of above.正确答案:AA 10 Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:A. Capital budgeting proces
5、s.B. Overhead rates.C. Contracts and administration costing system.D. Fringe benefits packages.E. None of the above正确答案:B21年项目管理师考试真题及详解5卷 第2卷 182 The use of the project reports:A. are not necessary on small projectsB. provides a means whereby various levels of authority can judge project performanc
6、eC. provides insight into project areas and the effectiveness of the control systemsD. All of the aboveE. B and C正确答案:E 关键路径的时差为负20(-20)天,如果关键路径有两个活动,这可能意味着什么?( )A必须评估关键路径以决定实际的时差。B预期提前20天完成项目C每个活动时差为负20天,D要满足项目完工要求,可能需要采取历时压缩正确答案:D Which of the following impacts the critical path?A.Changing the tas
7、k duration.B.Reduce the free float of an activity.C.Executing a backward passD.A or BE.None of the above.正确答案:AA 如果把活动H的历时缩短两个星期(H的历时为4),那么总历时是多少(见图一)A、16星期B、17星期C、15星期D、18星期正确答案:B 在项目工作网络中有几种类型的浮动期。那些在特定活动中使用并且不影响后来活动的浮动期被称作( )A多余的浮动期B自由的浮动期C总的浮动期D预期的浮动期正确答案:B21年项目管理师考试真题及详解5卷 第3卷 在下列哪类网络图中不使用虚拟活动?