管理经济学第七版英文教辅chapter_10.pdf
《管理经济学第七版英文教辅chapter_10.pdf》由会员分享,可在线阅读,更多相关《管理经济学第七版英文教辅chapter_10.pdf(16页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、1 Managerial Economics,7e(Keat)Chapter 12 Capital Budgeting and Risk(Appendix 12A)Multiple-Choice Questions 1)The term capital budgeting refers to decisions A)which are made in the short run.B)which concern the spreading of expenditures over a period lasting less than one year.C)where expenditures a
2、nd receipts for a particular undertaking will continue over a relatively long period of time.D)where a receipt of cash will occur simultaneously with an outflow of cash.Answer:C Diff:2 2)Capital budgeting projects include all of the following except A)the purchase of a six-month treasury bill.B)the
3、expansion of a plant.C)the development of a new product.D)the replacement of a piece of equipment.Answer:A Diff:2 3)If$1,000 is placed in an account earning 8%annually,the balance at the end of seven years will be A)$1,080.B)$1,560.C)$2,000.D)$1,714.Answer:D Diff:3 4)The payback period for a project
4、,requiring an initial outlay of$10,000 and producing ten uniform annual cash inflows of$1,500,is A)six years.B)six years and eight months.C)six years and six months.D)seven years.Answer:B Diff:3 5)The net present value of a project is calculated as A)the future value of all cash inflows minus the pr
5、esent value of all outflows.B)the sum of all cash inflows minus the sum of all cash outflows.C)the present value of all cash inflows minus the present value of all cash outflows.D)None of the above Answer:C Diff:2 2 6)A proposed project should be accepted if the net present value is A)positive.B)neg
6、ative.C)larger than the internal rate of return.D)smaller than the internal rate of return.Answer:A Diff:2 7)When future events cannot be assigned probabilities,we are talking about A)risk.B)uncertainty.C)a clouded future.D)financial risk.Answer:B Diff:1 8)Probabilities,which can be obtained by repe
7、tition or are based on general mathematical principles,are called A)statistical.B)empirical.C)a priori.D)subjective.Answer:C Diff:2 9)Other things being equal,the higher the cost of capital A)the higher the NPV of a project.B)the higher the IRR of the project.C)the lower the NPV of the project.D)The
8、 cost of capital has no effect on the NPV of the project.Answer:C Diff:3 10)The internal rate of return of a project can be found by A)discounting all cash flows at the cost of capital.B)averaging all cash inflows,and calculating the interest rate,which will make them equal to the average investment
9、.C)calculating the interest rate,which will equate the present value of all cash inflows to the present value of all cash outflows.D)None of the above Answer:C Diff:3 3 11)In finance,risk is most commonly measured by A)the probability distribution.B)the standard deviation.C)the average deviation.D)t
10、he square root of the standard deviation.Answer:B Diff:2 12)A project whose acceptance eliminates another project from consideration is called A)independent.B)mutually exclusive.C)replacement.D)complementary.Answer:B Diff:1 13)The internal rate of return equals the cost of capital when A)NPV=0.B)NPV
11、 0.C)NPV 0.D)None of the above Answer:A Diff:2 14)When two mutually exclusive projects are considered,the NPV calculations and the IRR calculations may,under certain circumstances,give conflicting recommendations as to which project to accept.The reason for this result is that in the NPV calculation
12、,cash inflows are assumed to be reinvested at the cost of capital,while in the IRR solution,reinvestment takes place at A)the hurdle rate.B)the accounting rate of return.C)the prime rate.D)the projects internal rate of return.Answer:D Diff:3 15)When analyzing a capital budgeting project,the analyst
13、must include in his calculation all of the following except A)all revenues and costs in terms of cash flows.B)only those cash flows that will change if the proposal is accepted(i.e.,incremental cash flows).C)interest payments on debt financing connected with the project.D)any effect(impact)the accep
14、tance of the project under consideration will have on other projects now in operation.Answer:C Diff:3 4 16)The use of the same cost of capital(risk adjusted discount rate)for all capital projects in a corporation A)is usually the correct procedure.B)is incorrect since different divisions of the corp
15、oration may be faced with different levels of risk.C)is incorrect since different capital projects,even in the same division,may be faced with different levels of risk.D)Both B and C Answer:D Diff:3 17)If a risky cash flow of$10,000 is equivalent to a riskless cash flow of$9,300,the certainty equiva
16、lent factor is A)0.93.B)0.07.C)1.07.D)1.93.Answer:A Diff:2 18)If,at the end of the project life,a piece of equipment having a book value of$4,000 is expected to bring$3,000 upon resale,and the income tax rate is 40%,how much will be the cash flow?A)$2,800 B)$3,000 C)$3,400 D)$4,000 Answer:C Diff:3 1
17、9)If the risk adjusted discount rate method and the certainty equivalent methods are to give the same results,then the certainty equivalent factor(at)must equal(where rf is the risk-free interest rate,and k is the risk adjusted cost of capital)A)(1+rf)t times(1+k)t.B)(1+k)t divided by(1+rf)t.C)(1+rf
18、)t divided by(1+k)t.D)(1+k)t minus(1+rf)t.Answer:C Diff:3 5 20)Two projects have the following NPVs and standard deviations:Project A Project B NPV 200 200 Standard deviation 75 100 A person who selects project A over project B is A)risk seeking.B)risk indifferent.C)risk averse.D)None of the above A
19、nswer:C Diff:2 21)An increase in net working capital required at the beginning of an expansion project must be considered to be A)a cash inflow.B)a reallocation of assets.C)a cash outflow.D)None of the above Answer:C Diff:2 22)Usually,the cost of capital for newly issued stock is _ the cost of retai
20、ned earnings.A)lower than B)higher than C)same as D)either higher or lower than Answer:B Diff:2 23)A stock whose rate of return fluctuates less than the rate of return of a market portfolio will have a beta that equals A)1.B)less than 1.C)more than 1.D)Either A or C above Answer:B Diff:2 6 24)A comp
21、anys capital structure is made up of 40%debt and 60%common equity(both at market values).The interest rate on bonds similar to those issued by the company is 8%.The cost of equity is estimated to be 15%.The income tax rate is 40%.The companys weighted cost of capital is A)11.5%.B)12.2%.C)10.9%.D)8.9
22、%.Answer:C Diff:3 25)Capital rationing A)exists when a company sets an arbitrary limit on the amount of investment it is willing to undertake,so that not all projects with an NPV higher than the cost of capital will be accepted.B)generally does not permit a company to achieve maximum value.C)seems t
23、o occur quite frequently among corporations.D)All of the above Answer:D Diff:3 26)The time value of money can be best described as A)a dollar today is worth more than a dollar tomorrow.B)the basis on which net present values are calculated.C)the basis on which internal rates of return are calculated
24、.D)All of the above Answer:D Diff:2 27)Net present value and internal rate of return capital budgeting decisions can differ because A)the initial costs of the capital outlays differ.B)the cash flow streams differ.C)the discount rates differ for different time periods.D)All of the above Answer:D Diff
25、:2 28)Simulation analysis A)permits the calculation of expected value and standard deviation.B)does not permit the calculation of expected value and standard deviation.C)is too complex to ever be used in actual business situations.D)does not consider probabilities.Answer:A Diff:2 7 29)The expected v
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 管理 经济学 第七 英文 教辅 chapter_10
限制150内