桩基施工方案-中文英文对照273.pdf
《桩基施工方案-中文英文对照273.pdf》由会员分享,可在线阅读,更多相关《桩基施工方案-中文英文对照273.pdf(14页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、 塞拉利昂水泥厂项目桩基施工方案 Cement terminal project pile foundation construction program in Sierra Leone 一、旋挖成孔灌注桩施工 Rotary drilling hole pile construction 1工程量 1000M3 砼 The project amount 1000M3 concrete 2施工技术 Construction Technology 本工程项目桩基施工采用旋挖成孔工程钻机,在施工前须对场地进行清表、清障、平整、压实,使场地表面耐力不小于 100Kpa。施工时设置泥浆池、沉定池、泥浆循
2、环系统和废浆池,沉淀池的容积两倍于一根桩的体积,储浆池容积大于 16m3,以满足钻孔需要.Pile Foundation Construction of the project use a rotary drilling rig,before construction,we need to cleared the table,wrecker,leveling,compaction venue to make sure the surface endurance is not less than 100Kpa.During construction,we need to set Mud pool
3、s,sedimentation tanks,mud circulation system and waste slurry pond.To meet drilling demand,Sedimentation tank volume is twice the volume of a pile,storage slurry pond volume should be greater than 16m3 3工艺流程 Process 桩位定位埋设护筒钻机就位钻孔成孔质量检测钢筋笼吊放泥浆制备,注浆跟进砼浇筑养护成桩检测钢筋笼制作、验收 4操作工艺 Operation process(1)测量定位 M
4、easurement Positioning(a)采用全站仪按照图纸测定位置并做好标色。Use total station measurement position in accordance with the drawings and make a standard color。(b)利用水准仪测定护筒标高其误差不大于 10MM.Level determination Casings for elevation of the error should not more than 10MM(2)栓桩:桩位位置确定后,用两根相互垂直的十字线中心相交于桩点,并定出他的控制点,做好标识妥善保护。Bo
5、lt piles:once piles bit position is determined,we use two mutually perpendicular crosshairs center intersect at the pile point,set his control point and marked properly protected。(3)钻机就位:履带坐落的位置应平整,坡度不大于3 度,避免因场地不平整产生动力损失,倾斜、位移,重心高时还会引起安全事故。Rig in place:Tracked located position should be flat,the sl
6、ope is not greater than 3 degrees and avoid venue uneven loss of power,tilt,displacement,high center of gravity will also cause accidents(4)对准桩位:首先调整旋挖机的桅杆,使之处于垂直状态,让钻头对准桩点.Alignment Pile:First adjust the auger mast in a vertical state and the drill bucket should be align with the pile point。(5)埋设护筒
7、:定出十字控制点后,可采用钻机进行取土,钻至设计深度进行护筒埋设。Bury casing:set cross control point the we use the rig dig the hole until the depth we can start to bury the casing.护筒采用厚度6mm的钢板制作而成,长度在2m左右,护筒的直径为850mm,为防止钻进施工中护筒外圈返浆造成塌孔和护筒脱落,护筒底部应坐落在稳定的土层上,并且进入原土 0.3-0。5m.护筒埋设位置应准确其中心点与桩定位点误差不大于 50mm,并应保证护筒的垂度和水平度。The casing was m
8、ade by 6mm thick steel plate,the length should be around 2m and the casing diameter is 850mm。In order to prevent the outer tube Protection Drilling returned to the pulp caused the hole collapse and retaining barrel off the bottom of the pile casing should be located in the stable on the soil and int
9、o the original soil 0.3-0。5m。Casing laying position should be accurate center point,pile anchor point error is not more than 50mm and also should ensure Casing for vertical and horizontal(6)泥浆制作:采用现场所泥浆搅拌机或人工制作,宜先加水并计算体积,在搅拌下加入规定的膨润土,纯碱以溶液的方式在搅拌下缓缓加入,搅拌时间一般不少于 3 分钟,必要时还可加入其他外加剂,以增大泥浆比重。另拌制泥浆应根据工艺和穿越
10、土层情况进行配合调整,膨润土泥浆性能指标制备可按下列参数(砂土层);粘度 1925;比重 1.18-1.30;含沙率小于 6%,胶体率 95,PH 值 7。0-9.0。Mud production:site slurry mixer or artificially produced advised adding water and calculating the volume,after that added with stirring a predetermined bentonite,soda ash solution with stirring was slowly added and
11、the stirring time is generally less than 3 minutes,if necessary we can also add other admixtures to increase the mud weight。Besides,Mixing mud with the adjustment should be based on the process and through the soil,and the bentonite slurry performance indicators prepared according to the following p
12、arameters(sand layer);viscosity 19-25%;proportion 1.18 1。30;sandy rate less than 6%,colloidal rate 95,PH value 7。0-9。0.(7)旋挖钻钻进成孔 Rotary Drill drilling hole(a)以钻具钻头自重和液压缸加压作为钻进压力,每一回次的钻进量应以深度仪所示值为参考依据,以钻机说明书钻速,钻压扭矩为指导,进尺适当,不多钻也不少钻。钻多,辅助时间加长。钻少,回次进尺少,效率降低。We take drill weight and hydraulic cylinder p
13、ressure as the drilling pressure,drilling depth meter should be shown the value reference for speed drilling rig manual the WOB torque for guidance,footage appropriate,not much drill is also a lot of drilling.Drill multi Auxiliary longer.Drilling less footage back to the times,reducing efficiency(b)
14、当钻头内装满土、砂后,将其提升上来,注意地下水位变化情况,并灌注泥浆。When the drill is filled with soil and sand,we raise it up and pay attention to the groundwater level changes then perfuse mud(c)旋转钻机将钻头内的土卸出,用铲车及时运走,运离不影响施工作业区.Rotary rig to drill within the soil unloaded then transported with a forklift in a timely manner and tra
15、nsported from the impact of the construction work area(d)关闭钻头活门,将钻头转回孔口,降下钻头继续钻进。Close the shutter then reversal of the drill orifice,lower the drill bit to continued drilling (e)为保证孔壁稳定,应视表土松散层厚度,孔口下入长度适当的护筒,并保持泥浆面高度,随泥浆损耗及孔深增加,应及时向孔内补充泥浆,以维持孔内压力平衡。Should be considered to ensure the stability of ho
16、le wall the topsoil loose layer thickness orifice into the appropriate length casing Protection,then keep the mud surface height with mud loss and deep hole should be timely supplement to the hole in the mud,in order to maintain the hole pressure balance.(f)提升钻头过快,易产生负压,造成塌孔.一般钻头提升速度控制在,装满渣土钻头提升 0.9
17、37M/S,空钻头升降 1.210M/S.If we improve drill too fast,its easy to produce negative pressure,which will result in hole collapse.Usually when a drill filled with muck,the lifting speed should be controlled within 0.937M/S and for empty drill,the speed should be 1。210M/S(g)在桩端持力层钻进时右能会由于钻头的提升引起持力层的松驰,因此在接近
18、孔底标高时应注意减小钻头的提升速度.Due to the enhancement of the drill in the pile end bearing stratum drilling may cause relaxation of the bearing layer elevation thus when drilling near the bottom of the hole we should pay attention to reduce the lifting speed of the drill(h)清孔:因旋挖钻用泥浆循环,在保障泥浆稳定的情况下,(清除孔底沉渣一般用双层底捞
19、砂钻头,在不进尺的情况下,回转钻头使沉渣尽可能地进入斗内,反转,封闭斗门,即可达到目的。因本工程地质24M 以下为粘土层,视具体情况,确定清孔方法,确保沉渣厚度符合要求。Clean-up holes:Because rotary drilling use mud circulation,so under the circumstance of stable mud protection(when clear the hole bottom sediment generally we do with double bottom bailing bit,in the case of footage
20、,rotary drill bit so that sediment went into the bucket,inverted closed shutter and this can achieve the purpose.Because of the engineering geology-24M below are the clay layer so we should depend on the specific situation then determine hole cleaning methods,to ensure the sediment thickness require
21、d(i)钢筋笼制作:钢筋笼按设计图纸及相关规定要求制作.钢筋表面应洁净,使用前应将表面污垢、漆皮、鳞锈等清除干净;钢筋应平直,无局部弯曲、无裂纹、断伤。钢筋接头焊缝均匀、饱满、光滑;不得有裂纹、塌陷、咬边、夹渣,钢筋表面无明显烧伤等缺陷。每批焊条都应有出厂合格证。The reinforcement cage production:steel cage was designed according to drawings and related regulations requirements。Reinforced surface should be clean before using.We
22、should clean surface dirt,patent leather,scaly rust and the reinforcement should be straight with no local bending,no cracks,off injured。Reinforced joints should be uniform weld,full,smooth,without cracks,collapse,undercut,slag,steel surface burns and other defects。Each batch of electrodes should ha
23、ve factory certification 钢筋笼安装,视设计桩长的配筋长度及配备的工程吊车技术参数的实际情 况,进行分段制作,遂段吊放钢筋笼,各段之间根据主筋直径按设计要求采用单面电焊连接.双点起吊,确保钢筋笼不变形。当钢筋笼吊放至设计位置后,在孔口固定钢筋笼上端。Reinforcement cage installation:According to the actual situation of the design length of pile reinforcement length and with engineering crane technical parameters
24、,we should produce in segment,then the segment dipping steel cage main reinforcement diameter between paragraphs design requires single-sided welding。Using twopoint lifting to ensure no deformation of the reinforcement cage.When the reinforcement cage was dipping to the design position,we fixed rein
25、forcement cage in the upper of the orifice.钢筋笼保护层垫块采用现场预制砂浆圆块。The protective layer of the reinforcement cage pads use the site prefabricated mortar round block(j)下钢筋笼,钢筋笼场内运输可采用人工抬运或加托架转运,不可使钢筋笼产生永久变形;钢筋笼采用双点起吊,对正后缓缓下入,不准强行压入。Reinforcing Steel Cage:Reinforcement cage inside can be transported by art