1、7、Identify the main types of personnel employed in an information systems department.(1)Requirements elicitation and analysisThis might involve:business analysts,systems analysts,sales manaaers,pre-salessupport,sales enaineers deDendinq on the environment and the particularcircumstances of the proje
2、ct(e.g.is it being developed for an internal or external client?).The ISO 12207 suggests that human factors engineering specifications,would beproduced at this stage which implies the possible deployment of humac-computsrinterface specialistsOther specialists might be involved to deal with other,tec
3、hnical areas,for examplesecurity.Note,also,that you would have to have some user and/or client representativesavailable to provide details of their needs.(2)Architectural designSystem architect-many organizations now have a single person or group that isresponsible for ensuring new system components
4、 are designed according toorganizational standardSoftware designers(3)Detailed designSoftware designers,software developers(4)Code/testSoftware designers,software developers(5)IntegrationSoftware designers,software developers(to deal with problems)hardware designers,testers(6)Qualification testingSy
5、stem testers,end-users,software designers and developers(to resolve problemsand issues)(7)InstallationBusiness analysts,technical support,trainers,local user management2、A software house has developed a customised order processing system for a client.Youare an employee of the software house that has
6、 been asked to organize a training coursefor the end-users of the system.At present,a user handbook has been produced,but nospecific training material.A plan is now needed for the project which will set up thedelivery of the training courses.The project can be assumed to have been completedwhen the
7、first training course starts.Among the things that will need to be considered arethe following:Training materials will need to be designed and created;A timetable will need to be drafted and agreed;Date(s)for the course will need to be arranged;The people attending the course will need to be identif
8、ied and notified;Rooms and computer facilities for the course will need to be provided for.Questions:A.Identify the main stakeholders for this project;B.Draw up a statement of the objectives for this project;C.For the objectives,identify the measures of effectiveness;Main stakeholdersThese might inc
9、lude:Client management User management-at a lower level than the above,they would share the highermanagement concerns,but also have operational ones such as cover in the officewhen staff attend training course.Users Trainers Technical support-set up in a training environment Premises management(培训场所
10、管31 人员)一 availability of rooms for training Catering services(餐饮月艮务)-to provide refreshments for course delegates Reprographics services(复E|1 月 艮 务)一 to produce copies of training material correctlyand on timeObjectivesTo have in place by dd/mm/yy all the materials and arrangements needed for the de
11、liveryof the training courses relating to the user of the accounting package ABC atorganization XYZ within the budget specified,.Note that the actual delivery of the material and training of staff is just outside the boundary ofthe project:Measures of effectivenessAn obvious one is that the training
12、 courses can actually go ahead.However,this is rather lateif things are missing.An alternative would be to produce a checklist that can be used ondd/mm/yy to ensure that the necessary arrangements are in place.e.g.Rooms and equipment booked Delegates notified Training materials prepared横线部分为我加注(第2章)
13、1.List the products created by the Step Wise planning process.This can be seen as a follow-up to Exercise 2.6 in text.The pointers for this show how thesteps in the Step Wise planning process could map onto the various sections of a planningdocument which can be seen as the final deliverable of plan
14、ning.The further exercise ineffect asks the students to identify intermediate products in the process.I find it useful to encourage students to discuss how they are going to do an exercise-afterall this is a subject to do with planning.One approach would be to go through each of thesteps in the Step
15、 Wise framework,identifying the products created.You might end up withsomething like this.0.Select project:feasibility report1.Identify project scope and objectives;Terms of reference(责权范围)2.Identify project infrastructure:Standards,procedures relating to progress reporting,change control,Version Co
16、ntrol tool,cost evaluation tools,vtc3.Analyse project characteristics:Technical plan,risk register4.Identify the products and activities:Product breakdown structure,productdescriptions,product flow diagrams,IdeaH activity network(Coarse one cot refined one)5.Estimate effort for each activity:Schedul
17、e of task durations and costs6.Identify activity risks.Updated schedule of task durations and costs,updated riskregister7.Allocate resources:Gantt chart8.Review/publicize plan:Publicized plan9.Lower level planning:Detailed plans2.What products must exist before the activity test program can take pla
18、ce?What productsdoes this activity create?Pre-test.Software specification,testing environment,test cases(including input details andexpected results),software to be tested,test planPost-test Actual results,list of discrepancies(不一致f生),error reports5.Question 4 in the Further Exercises for Chapter 1
19、refers to a scenario relating to a trainingexercise.Using that scenario,draw up a Product Breakdown Structure,a Product FlowDiagram and a preliminary activity network.FeedbackTrainingPlan2.P57 llliness;Other commitments interfering with work e.g.familiy,work;Hardware or software facilities not being
20、 available when needed;Ambiguity in the assignment speficifcation leadintg to misunderstandings;Lack of understanding of the techniques to be used Hostile a情tude amon。stakeholders3.discounted cash flow better than net profit or return on investment?DCF takes more account of the possibility that inve
21、stment might more profitablybe placed elsewhere than the proposed project;Projects where the major benefits are only experienced after several years arenot favoured.There is more uncertainty about estimates of income and costs ofthe future that you gaze.NPV values can be calculated for a number of d
22、ifferent feasible interest rates-different projects might be favoured as a result.5.Details are given below of the estimated income and outgoings of Projects A.Calculate thereturn on investment,the payback period and the net present value of the project andcomment in which appears to be the most att
23、ractive.Assume a discount rate of 5%ProjectAdiscountaccum.yearincomeoutgoingscashflowrateNPVcashflow0120000-1200001-120000-12000014200010000320000.952430476.19-8800024700010000370000.907033560.09-510003510009000420000.863836281.18-900044000012000280000.822723035.671900019000ROINPVpayback3.96%3353.13
24、4四、1.A building society has a long history of implementing computer-based informationsystems to support the work of its branches.It uses a proprietary structured systemsanalysis and design method.It has been decided to create a computer model of theproperty market.This would attempt for example to c
25、alculate the effect of changes ofinterest rates on house values.There is some concern that the usual methodology usedfor IS development would not be appropriate for the new project.(a)Why might there be this concern and what alternative approaches should beconsidered?(b)Outline a plan for the develo