《新整理施工方案》室外电缆沟施工方案(中英文).doc
《《新整理施工方案》室外电缆沟施工方案(中英文).doc》由会员分享,可在线阅读,更多相关《《新整理施工方案》室外电缆沟施工方案(中英文).doc(11页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、电缆沟开挖施工方案Work Method of Cable Trench Excavation 编 制:Compiled by: 审 核:Reviewed by:2009年10月21日October 21, 2009目 录Content一. 概况 OVERVIEW31.1 工程概况 PROJECT OVERVIEW31.2 施工范围 SCOPE OF WORK3二编制依据 COMPILATION BASIS4三 施工工艺流程CONSTRUCTION PROCESS:4四. 前期准备PREPARATIONS44.1 技术准备TECHNICAL PREPARATION44.2 材料准备MATERI
2、AL PREPARATION54.3 主要机具准备MAIN EQUIPMENTS PREPARATION54.4 作业环境准备OPERATING ENVIRONMENT PREPARATIONS5五. 电缆沟施工CABLE TRENCH CONSTRUCTION55.1 电缆沟测量、定位CABLE TRENCH MEASUREMENT AND POSITIONING55.2 电缆沟开挖CABLE TRENCH EXCAVATION6六. 质量控制QUALITY CONTROL76.1 电缆沟外形尺寸允许偏差表ALLOWABLE DEVIATED EXTERNAL DIMENSIONS OF C
3、ABLE TRENCH TABLE76.2 应注意的质量问题QUALITY ISSUES8七. 成品保护FINISHED PROTECTION8八. 施工记录CONSTRUCTION OF RECORD8九. 安全生产、文明施工要求和措施SAFETY AND CIVILIZED CONSTRUCTION REQUESTS AND MEASURES9附厂区电缆沟图: ATTACHED: CABLE TRENCH DRAWING9一. 概况 Overview1.1 工程概况 Project Overview项目名称:本工程涉及三个变电站,分别是现有的220/35kV A472变电站、现有的35/1
4、0kV B301S变电站以及新建的35/10kV C581变电站,工作内容为三个变电站之间和从三个变电站接至MV用户的电力电缆、控制电缆、接地电缆敷设所需电缆沟的开挖工程。The project involves three substations, namely the existing 220/35kV A472 substation, the existing 35/10kV B301S the 35/10kV C581 substation and a new substation. This is the power, control and grounding cable tren
5、ch excavation project among three substations and for MV users connected to the three substations. 1.2 施工范围 Scope of Work1) 由A472变电站引出3路35kV出线。其中:一路引至B301S建筑(35/10kV变电站)原1#主变,原1#主变电缆将抽出,与新增4#主变连接;另两路引至35/10kV C581变电站1#主变和2#主变。回路采用FS-YJY-26/35kV-1*300mm2单芯电缆,直埋敷设。去C581的两路35kV线路,敷设时沿不同路径,以避免两回线路同时受损。P
6、ull three 35V outgoings from A472 substation. Of which: The first outgoing is led to B301S Building (35/10kV substation) the original one # main transformer, pull the original one # main transformer cable out, and connect to the adding 4 # main transformer; the other two outgoings are led to 35/10kV
7、 C581 # 1 and substation 2 # main transformer. Use FS-YJY-26/35kV-1 * 300mm2 single-core cables for Loop and buried pulling. Two 35kV lines to C581 are laid along different paths to avoid damage of the two loops.2) 由B301S变电站引出7路10kV出线。全部引至B399中心制冷站。回路采用10kV截面为95mm2的三芯铠装电缆,由B301S南面现有的电缆井引出直埋至装置。Pull
8、7 10kV outgoings from B301S substation to B399central refrigeration station. Loop uses 10kV three-core armored cable with cross-section 95mm2 and pull out from the existing cable well in the south of B301S then buried lay to the device. 3) 由C581引出10路10kV线路,分别为A507的四台变压器,B551的两台变压器,B553TDA装置氢气压缩机2台,C
9、521盐酸装置氯气压缩机1台,盐酸压缩机1台提供电源。其中,变压器回路采用10kV截面为185mm2的三芯铠装电缆,马达回路采用10kV截面为95mm2的三芯铠装电缆。以上电缆线路均沿规划路径埋地敷设。10 10kV lines led from C581 are used to supply power to A507s four transformers, B551 two transformers, B553TDA 2 sets of hydrogen compressor unit, C521 hydrochloric acid chlorine gas compressor unit
10、, and hydrochloric acid compressor unit respectively. Among them, transformer circuit uses x 3-core armored cable with 10kV cross-section 185mm2, motor circuit uses three-core armored cable with 10kV cross-section 95mm2. All cable lines will be laid underground along the planning path.4) 接地电缆回路:Grou
11、nd cable loop: 从A472敷设一根95mm2裸铜线去C581,同时从C581敷设四根95mm2裸铜线,分别引至B551、A507、B553和C521,作等电位联结。以上电缆线路均沿规划路径埋地敷设。Lay a 95mm2 bare copper wire to C581 from A472. Meanwhile lay four bare copper wires to B551, A507, B553 and C521 for equipotential bonding. All cable lines will be laid underground along the pl
12、anning path.5)本工程电缆沟走向如下:The cable trench directions are as follows:电缆沟南线为A472至C581,全长约850米,根据K-K断面图:开挖深度为1米,沟槽底宽0.6米,沟槽面宽约1.1米。 Cable trench south line is from A472 to C581 about 850 meters long. According to KK sectional drawing, excavation depth is of 1 meter with trench bottom width 0.6 m and fa
13、ce width1.1 m.电缆沟北线为A472至C581和B301,其中共线约220米,根据A-A断面图有:开挖深度为1米,沟槽底宽1米,沟槽面宽约1.5米;Cable trench north line is from A472 to C581 and B301 and the collinear is about 220 meters. According to AA sectional drawing, excavation depth is 1 meter trench with trench bottom width 1 m and face width1.5 m.至C581支线约
14、430米,根据E-E断面图有:开挖深度为1米,沟槽底宽0.6米,沟槽面宽约1.1米;至B301支线约300米,根据B-B断面图有:开挖深度为1米,沟槽底宽0.6米,沟槽面宽约1.1米。The sub-line the C581 is about 430 meters. According to EE sectional drawing excavation depth is 1 meter trench with trench bottom width 1 m and face width1.1 m. The sub-line to B301the is about 300 meters. A
15、ccording to BB sectional drawing , excavation depth is 1 meter trench with trench bottom width 1 m and face width1.1 m.二编制依据 Compilation Basis1)根据电气包(中压部分)招标文件及招标图纸编制而成。According to Electric package (MV) the tender and tender drawings.2)在充分研究工程的客观情况和施工特点,结合我公司类似工程施工经验的基础上编制的。Based on full study on c
16、onstruction characteristics and objective situation and combined with similar construction experience.3)在本方案编制过程中,严格执行国家现行建筑和安装工程施工及验收规范、规程、标准、设计规范。具体如下:In this compilation process, strictly implement current national construction and installation construction, acceptance norms, procedures, standard
17、s, and design specifications. As follows:电气装置安装工程电缆线路施工及验收规范 GB50168-2006 Electrical installation cable construction and acceptance standards GB50168-2006 电气装置安装工程接地装置施工及验收规范 GB50169-2006 Electrical installation earthing construction and acceptance standard GB50169-2006 建筑电气工程施工质量验收规范 GB503032002 Bu
18、ilding Electrical Construction Quality Acceptance GB50303-2002三 施工工艺流程:Construction Process:前期准备电缆沟测量、定位确定开挖顺序沿灰线切出槽边轮廓线分层开挖修整槽边清底preparation cable trench measurements excavation ordercutting contour line along the calcareousness stratified excavation finishing cable trench edgeclear up四. 前期准备Prepar
19、ations4.1 技术准备technical preparation1) 针对本工程特点编审详细的电缆沟施工作业指导书,及时组织图纸会审。Compile particular cable trench construction engineering guide book as per project characteristics and organize promptly drawings joint examination.2) 根据上海市电力建设工程施工工艺实施细则结合本工程实际编写电缆沟施工工艺卡,并组织实施。Compile construction technique cards
20、 according to the Shanghai Municipal Electric Power Construction Engineering Construction Technology Implementation Details and organize its implementation.3) 施工人员全面了解电缆敷设来路、终点及敷设路径。Construction workers have comprehensive understanding antecedents, destination, and laying path of laying cables. 4.2
21、材料准备Material preparation根据材料计划采购所有的材料。所有材料规格型号及电压等级应符合设计要求,并有产品合格证。Purchase materials as per the plan. All materials specification models and the voltage level should meet the design requirements and have product certificates.4.3 主要机具准备Main equipments preparation尖、平头铁锹、手锤、手推车、梯子、铁镐、撬棍、钢尺、坡度尺、小线或20铅丝
22、等。Sharp, flat head shovel, hand hammers, wheelbarrows, ladders, picks, crowbars, steel ruler, slope-foot, small lead wire or 20 #lead wire and so on.4.4 作业环境准备operating environment preparations1)土方开挖前,应根据施工方案的要求,将施工区域内的地上、地下障碍物清除和处理完毕。Prior to earth excavation, clear up obstructions on the ground or
23、 underground as per construction plan.2)建筑物或构筑物的位置或场地的定位控制线(桩)、标准水平桩及基槽的灰线尺寸,必须经过检验合格,并办完预检手续。The location building or structure and the calcareousness of site positioning control lines (piles), standard level pile and the groove base size must be tested qualified, and finished pre-screening procedu
24、res.3)场地要清理平整,做好排水坡度,在施工区域内,要挖临时性排水沟。Clean up the site and make drainage slope. Excavate temporary drains in the construction area.4)夜间施工时,应合理安排工序,防止错挖或超挖。施工场地应根据需要安装照明设施,在危险地段应设置明显标志。Arrange night construction procedures properly to prevent wrong dig or super-dug. Install the lighting facilities as