1、滑模施工方法【实用文档】doc文档可直接使用可编辑,欢迎下载MS106 Date: 20/06/2021Method StatementFOR: Cement silo concrete casting scheme水泥库施工方案Owner: LafargeContractor: CBMIEstablished by:Checked by:Safety manager:Owner Approve(Site Manager) : yes yes with comment NOSafety Manager : yes yes with comment NOCBMI Construction Co。
2、, LTD.Uganda ProjectVersion:1MS001 DATE 05/5/08 Method StatementFor : Excavation less than 2 metersOwner : LafargeContractor: CBMIEstabliSafety manager:Owner Approve(Site Manager) :yes yes with comment NOSafety Manager : yes yes with comment NO 1。 Work title: Slipform construction 工作名称:滑模The method
3、statement includes: slip form work for cement silo包括:水泥库滑模。2。 Description:(说明)1) Explanation of the process(过程说明)Surveying测量放线Foundation construction have been finished 基础部分施工Revise the reinforcement 钢筋绑扎效正 Fixing and aligning brackets支承开支架组对调平Fixing and aligning formwork模板拼装加固、找正Connecting and layi
4、ng oil pipes各油路管连接铺设Fixing board on work platform铺设平台板并固定Setting up platform for reinforcement and other material. 搭设支承架放钢筋等材料Fit climbing rod and hydraulic equipment and aligning扒杆就位、液压设备就位效正Leveling and aligning the whole assembly work platform整体调平、找正Connect electrical equipment with power电气设备电源连接
5、Commissioning滑模设备就位调试Check hydraulic equipment to make sure all the equipments are in good condition ;检查液压设备状态是否良好Safety induction regarding slip forming works was delivered to operators and other workers, everybody wears the right PPE;安全交底,并穿戴PPEBarricade the working area。安全围护Set up emergency passa
6、ge 。修建逃生通道上部做防护Switch on after checking。 检查并合上电闸Slip form work starting. 滑模正式开始After going up 2m setting up lower work platform and protect it properly起滑到2米以后下平台搭设并做安全防护Checking verticality by plumb bob垂直度检查定位、定点并挂好垂球Checking verticality during the course for acceptance过程垂直度效正检查验收Transporting materi
7、al vertically by tower crane材料垂直运输采用塔式起重机提升2) Time/duration: daytime(工作时间及期限:白天/晚上)3。 Resources:(资源)1) Personnel:(人员)Mixer driver (4) (汽车司机4人)Tower crane operator (2) (塔吊司机2人)Crane operator (2) (吊车司机2人)Steel fixer (15) (钢筋工15人/)Mason(25) (混凝土工25人)Carpenter(12) (木工12人)Electrician (1) (电工2人)2) Supervi
8、sion:(管理)Engineer (2) (工程师2人)Foremen (2) (工长2人)3) Plant/Equipment(设备)A set of hydraulic equipment (液压设备一套)Concrete mixer (汽车)Crane (汽车吊)Tower crane (塔吊)Tape measure (卷尺)Water level (水准仪)Wrench (扳手)Hammer (手锤)Plasterers tools (抹灰工具)Other materials (其他原料)Solid barricade or warning tape(围栏、警示带)4。 PPE:
9、gloves/goggles/ helmet/safety shoes/nose mask安全用品:安全带/手套/防护眼镜/安全帽/安全鞋/口罩5。 Risk Assessmentoperation(工作步骤)risk(风险源)level(H/M/L)(风险程度)action(措施)final level(措施后风险程度)1。Equipment checking(设备检查)In bad condition(功能不良)MCheck hydraulic equipment, oil pipe and pressure (检查液压设备、油路、压力)-检查塔式起重机运转中钢丝绳、润滑油各部连接是否松动
10、?Check wire cable, lubrication and all connections of tower crane to ensure they function well (检查电气电压是还否稳定或电压过低?Check stability of voltage L2。Vertical material transporting(材料垂直运输)1。 Tower crane gets damaged(吊塔损坏)2.Material falling off ( 材料散落) 3、Unqualified slings are applied (使用不合格吊索具)H1。 Ensure t
11、ower crane is in good condition(保证性能良好)2。 Material must be tied firmly and specified lifting appliance shall be used for this purpose绑扎牢固、采用专用吊具3、Lifting capacity of slings must be validated by calculation to ensure a good condition(保证吊索良好,必须进行计算)L3。Material loading and unloading (材料倒运或装卸)1. Truck m
12、ay get damaged(汽车损坏)2. Unqualified slings are applied使用不合格吊索具) 3. Guiding load without using tagline(没有使用人工导向牵引绳)H1。 Truck must be in good condition(保证运输设备性能良好)2. Adopt qualified slings(保证吊索良好、使用合格的吊绳)3. Tagline is to be used to guide load(使用人工导向牵引绳)L4.Setting up bracket搭设支撑架1. Bracket for keeping r
13、ebars collapses ( 存放钢筋的支撑架倒塌) 2。 Supporting structure is not set properly(各部支撑结构不合理)3。 Workers falling off人员跌落H1。 Quantity of rebars should be below limit(限量存放)2. Load on bracket must be calculated according to work instuctions(按作业指导书组织施工,必须进行荷载计算)3。 All part must be well protected before commenceme
14、nt(施工前做好各部安全防护)L5.Formwork installation安装模板1。 Crack on formwork is found(模板裂缝)2. sharp edges can injure hands(毛刺及利边)3。people walking on the roof may fall down(人员滑落) 5. Formwork slipping up unsymtrically (模板上滑不平行H1. work done only by the dedicated operator(指定专业人员施工上滑时随时检查模板情况)2。 Wear gloves(戴好手套)3、 U
15、se safety harness with shock absorption lanyard(使用安全绳和带缓冲器的安全带)5Adjust it according to operation regulation (按操作规程调整、效正L山西煤炭进出口集团左权宏远煤业土建工程滑模拆除施工方案文件编号:SJ-ZS6ZQHYXM2001-发放编号:审 批:审 核:编 制:山西四建集团山煤左权宏远煤业土建工程项目部二零一二年四月十九日 一、编制依据1。1.建设单位提供的施工招标文件、设计施工图纸及答疑文件; 1.2。与建设单位签订的建设工程施工合同约定的工作内容,工程量、质量及工期要求;1.3.中
16、华人民共和国工程建设标准强制性条文;1。4.液压滑动模板施工安全技术规程:JGJ652021 1.5. 滑动模板工程技术规范:GB5011320051.6.建筑施工高处作业安全技术规程:JGJ8091 1.7.施工现场临时用电安全技术规范:JGJ462005;1。8.建筑机械使用安全技术规程:JGJ33-2001;1.9。塔式起重机安装、使用、拆卸安全技术规程:JGJ1962021 二、工程概况本工程为山煤集团左权宏远煤业土建工程一标段的筒仓,位于左权县城北约20KM处的寒王乡平王煤矿,筒仓建筑形式为两仓联体,筒仓总高度结构形式为钢筋混凝土筒体结构,仓上建筑为混合结构,筒仓总高度31。85m,
17、整个建筑总高度为42。55m,筒仓内径为16m,单仓容量为4200m,共2个。三、滑模拆除施工方案选择滑模滑升仓顶HL2底时,先将滑模脱模滑空后,筒壁模板与筒壁砼夹200mm300mm,利用塔吊吊索将提升架绷紧后,分段拆除滑模装置。四、滑模拆除准备工作4。1、辅助设备及工具材料准备项目名称数量工具专用扳手1套活口(15)2把活口(10)2把电工工具1套撬棍2把大锤1把手锤1把氧气乙炔3套切割机2台电焊机3台材料钢绳卡扣7个铁丝10米安全带12条安全帽12个设备TNZ5013塔吊一台4。2、滑模拆除现场情况及准备工作滑模拆除期间,正值矿区出煤时间,因筒仓周边均为矿区运煤道路与储煤场地,在拆除期间
18、,协调建设单位,派专人协调现场车辆运输,筒仓周边20m范围为滑模拆除警戒线范围,并派专人警卫与管理。禁止任何车辆、人员入内。因施工现场有限,需协调建设单位提供滑模装置堆放场地,待滑模分段吊装至地面后,再对各段滑模装置进行分类拆除堆放,全部滑模装置拆除完成后,及时调运出场.4。3拆除人员配备工 种人数工 作 内 容滑模拆除总指挥1指挥、负责台上、台下的滑升施工安全员2负责安全管理和监控,协调现场拆卸区域车辆通行滑模工4负责滑模拆除等电焊工2滑模设备分割拆除普 工6负责筒仓下面工作及材料堆放整理起重工2负责滑模吊卸指挥塔吊司机2负责滑模吊卸合 计194。3滑模拆除进度计划计划滑模拆除时间为2021
19、年4月22日至28日。五、滑模拆除工艺5.1滑模拆除流程:滑模平台清理 滑模脱空 拆除内外平台与吊篮架板 拆除中心拉盘 塔吊吊索将提升架绷紧 分段割除滑模装置 吊卸至地面分割区 分割滑模装置 材料整理堆放 5.2筒壁砼浇筑至环梁底(设计标高17。53m)处时,筒壁浇筑砼全部完成,将所有平台上部砼施工垃圾、钢材、水泥、水桶等物件全部清理至地面,并分类堆放整齐。5。3滑模脱空:在正常情况下,模板的夹固作用要大于模板下口早期混凝土对支承杆的嵌固作用。混凝土对支承杆的嵌固作用是在混凝土早期强度大于0.2Mpa时开始产生,并随混凝土强度增高而增强。而由于支承杆为细长杆件,当混凝土早期强度大于0。7Mpa
20、时,混凝土的嵌固作用将趋于稳定。滑模装置待砼达到初凝强度后开始脱空,砼早期强度大于0。7MPA时,利用滑模下口夹固作用及支撑杆的嵌固作用,保证滑模脱空后整体稳定性。空滑完成后,须对滑模系统进行仔细检查,检查的主要内容:支承杆有无弯曲变形;平台是否水平,有无侧移、倾斜、扭转等现象。如发现问题,须及时调整和纠正。此外,空滑时需减缓千斤顶的回油速度,延长回油时间,避免千斤顶回油时的下坠冲击力过大。5.4拆除平台板:分段拆除平台板,将吊架底部架板全部上传至平台上部,统一吊装至地面,全部平台板拆除完成后,再将平台板底支撑用钢筋全部分段拆除,吊装至地面。5。5拆除中心拉盘:拆除中心拉盘时,在保证滑模装置整
21、体受力均匀前提下,对称拆除每根拉盘钢筋。5。6分段拆除滑模装置:当拆除工作利用在施工结构作主支承点时,对结构混凝土强度的要求不低于15MPa。本工程使用塔吊为DT5013,塔吊位于两仓交界处,塔吊中心距两仓中心交点为12.1m,塔吊距筒仓外壁最远距离为23.4m,塔吊臂长50m,根据计算两个提升架与模板分段4m重量,塔吊起重完全可以满足施工需要.塔吊吊索分别先挂在两提升架中心上,然后吊索将提升架绷紧后,分段切割支撑杆、围圈及模板连接部位,两提升架两侧分段模板重量一致,切割完成后吊运至地面滑模装置分割区进行地面切割.所有吊运至地面的滑模装置分类切割完成后,将滑模装置材料分类堆放整齐,待所有装置切
22、割完成后,及时外运出场。六、安全技术措施6。1、施工安全的组织和制度保证(1)组建项目安全生产领导机构,健全安全生产责任制,项目部设专职安全员,各作业队队长为兼职安全员。(2)严格按施工规范和安全操作规程施工,严禁违章作业。(3)坚持现场安全检查,由项目经理组织每周一次安全检查,对重点部位、危险岗位要有记录。建立安全台帐。对查出的隐患要定人、定时、定措施,及时处理解决。(4)对进场工人要进行安全教育,特殊工种必须持证上岗,对参加滑模施工人员,事先进行安全技术培训.(5)施工前对操作人员进行体检,严禁存在各种职业疾病的人员上岗施工。(6)针对滑模体系施工中施工区域内极可能发生高空坠落、模板坍塌、