厦门EG钢结构厂房基础钢筋工程施工方案.docx
《厦门EG钢结构厂房基础钢筋工程施工方案.docx》由会员分享,可在线阅读,更多相关《厦门EG钢结构厂房基础钢筋工程施工方案.docx(7页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、厦门 EGX 钢构造厂房根底钢筋工程施工方案摘要:厦门 EGX 钢构造厂房根底钢筋工程的重难点把控,钢筋翻样的理论依据,钢筋翻样的部位和翻样内容,钢筋算量和材料的购置,购置钢筋材料的入场检查和检测,钢筋现场的制作和安装。Construction Scheme of Foundation Reinforcement Engineering of Xiamen EGX Steel Structure Factory Building ZhangsonglinSchool of Management, Shanghai University, Shanghai 202344, ChinaAbstra
2、ct: The key and difficult points of the foundation rebar engineering of Xiamen EGX steel structure workshop are controlled, the theoretical basis of rebar sampling, the position and content of rebar sampling, the calculation of rebar and the purchase of rebar materials, the entrance inspection and t
3、esting of the purchase of rebar materials, the production and installation of rebar on site.随着我国工业的进展,各类厂房建筑越来越多,对于多数生产性的工业厂房一般主体构造承受的是钢构造框架形式,地基根底多承受桩根底和独立根底,根底为整个建筑主体的重要组成局部,而根底的配筋正确,也是整个根底工程能够到达质量标准的保证。本工程工场栋主体构造为钢构造,地基根底为预制管桩桩根底和独立根底, 钢柱承受混凝土柱脚包裹,主体建筑面积为 32928m2。1 钢筋翻样的依据和预备工作1.1 构造施工图构造施工图主要内容主
4、要包括1.1.1 桩位图,桩工程主要承受预制管桩,桩芯填充钢筋混凝土。1.1.2 根底布置图,根底主要承受桩根底和独立根底,局部电梯基坑底部承受筏型根底。1.1.3 梁平法施工图,连接混凝土柱脚承受框架梁的形式连接。1.1.4 框架柱的布置及配筋图,框架柱的主要作用是包裹主体钢柱的短柱脚。1.1.5 一层楼板配筋图,构造地坪承受桩上板带和跨中板带进展配筋。1.2 配筋标准图集图集依据:国标 16G-101 平法施工图并结合企业内部标准详图,本工程主体配筋均承受三级钢 HRB400E.1.2.1 保护层打算,框架梁柱地上室内构造,保护层厚度为 40mm,接触土部位保护层厚度为 50mm,基础保护
5、层厚度一般为 70mm,地坪接触土保持厚度为 40mm,非接触土保护层厚度为 30mm。1.2.2 钢筋锚固长度和搭接长度,锚固长度一般为 37d,搭接长度一般为 52d。1.2.3 弯曲和弯曲标准,纵向受力钢筋 d25,弯钩角度为 90 度时,弯曲内径一般为 4d,弯钩角度为 180 度时,弯曲内径一般为 4d。1.3 钢筋加工机具及弯曲工具预备。1.3.1 钢筋加工机具包括自动调直切割机,钢筋弯曲机,钢筋切断机,砂轮切割机,型号和功率见图 1.3.1图 1.3.1设备名称型数功号量率(KW)自动调直GT17.切割机4-145钢筋弯曲GW13机50钢筋切割GQ12.机504砂轮切割JG12.