1、F20DLElectric Power Industry Standard of the Peoples RepubKc of ChinaDL/T 4002019Replace DL/T 4002010Technical Guide for Live Working in500kV AC Compact Transmission LineIssue Date: June 4, 2019Implementation Date: October 1, 2019Issued by National Energy Administration of the Peoples Republic of Ch
2、ina1.1.5 When overhauling and replacing insulator strings on the power-off circuit by means of power-off maintenance, the workers shall hang and set up personal security cables first before installing the tools (double hooks and lever hoists) for lifting the insulator strings. The hanging and disman
3、tling methods of the personal security cable are the same as those of the maintenance earthing cable.1.1.6 The requirements and safety precautions for working on the ground wire above the power-off circuit are the same as those when both circuits are live.5.5 Work carried out with protective gaps5.5
4、.1 When the working distance or combined gap of live working does not meet the requirements, the work mode of installing protective gaps shall be adopted.5.5.2 The earthing cable connected to the protective gaps shall adopt the multi-strand soft copper wire, and its cross section shall meet the requ
5、irements of ground short circuit capacity, but shall not be less than 25mm2.5.5.3 When the work is carried out with protective gaps, the insulation coordination between the values of the working distance, the combined gap, the minimum effective length of insulating tools and the minimum number of go
6、od insulators and the set values of the protective gaps shall meet the requirements of DL/T 876.5.5.4 The worker who installs or disassembles the protective gaps shall wear a full set of conductive clothing.5.5.5 Before the protective gaps are installed, contacting the dispatcher to stop reclosing s
7、hall be done.5.5.6 The protective gaps shall be installed on the adjacent towers to the work location. The earthing cable of each protective gap shall be reliably connected with the metal components of the tower first, and then the other end shall be hung on the conductor of the maintained phase, an
8、d the contact shall be good. The dismantling procedure is reversed.5.5.7 See Table 6 for the reference set values of the protective gaps. Before the protective gaps are used, the values of the protective gaps may be checked and corrected according to the actual size of the tower head.Table 6 Set val
9、ues of the protective gapsAltitude H/mSet values of the protective gaps/mH10001.21000H20001.42000H30001.65.5.8 During installation, the distance of the protective gap shall be adjusted to the maximum value first, and then the distance shall be adjusted to the set value of the protective gap with ins
10、ulating tools after the protective gap is installed in place. Before the protective gap is dismantled, its distance shall be set back to the maximum value, and then it shall be dismantled according to the dismantling procedure.5.5.9 For the two upper phase conductors of the three phase conductors ar
11、ranged in an inverted triangle, the protective gap may be vertically installed between the conductor and the frame which is between the two hanging points of the V-shaped insulator string, or may be horizontally installed between the tower frame and the conductor. In terms of the lower phase conduct
12、or, the protective gap may be horizontally installed between the tower frame and the conductor.5.6 Safety protection5.6.1 The live working safety protection equipment of 500kV conventional lines may be used for live working of 500kV compact lines.5.6.2 The performance of the conductive clothing shal
13、l comply with GB/T 6568.5.6.3 Both the equipotential worker and the mid-potential worker shall wear a full set of qualified conductive clothing, and flame resistant underwear shall also be worn under the conductive clothing.5.6.4 The ground potential worker on the tower must wear a full set of condu
14、ctive clothing or electrostatic protective clothing and conductive shoes before climbing the tower. It is strictly prohibited to wear other clothes over conductive clothing or electrostatic protective clothing.5.6.5 The overhead ground wire shall be regarded as a live conductor, and the workers shal
15、l keep a distance of over0.4m from it. If it is necessary to work on the overhead ground wire, it shall be grounded well through dedicated earthing cables. The methods and steps for installing or dismantling the dedicated earthing cables on the overhead ground wire are the same as those for installi
16、ng or dismantling the earthing cables on a power-off line.5.6.6 If it is necessary to enter the overhead ground wire for maintenance, the working distance and mechanical strength of the work location after bearing concentrated load shall be checked.5.6.7 When using insulating ropes to transfer large
17、 metal objects(including tools and materials), the workers on the tower or on the ground shall ground the metal objects before touching them.5.6.8 With regard to large metal objects (e.g. automobiles, etc.) insulated from the ground and placed near strong electric fields, attention shall be paid to
18、protecting people from induced electrical injury. These metal objects must be grounded before they can be touched.5.6 Potential transfer5.7.1 The equipotential worker shall obtain permission from the person in charge of the work before potential transfer.5.7.2 When the equipotential worker transfers
19、 potential, the distance between the human body and the live conductors shall not be less than 0.4m It is strictly prohibited to touch the live conductors with bare hands or with bare parts.5.7.3 During potential transfer, the action shall be smooth, accurate and fast.6 Enter or leave equipotential6
20、.1 Enter or leave equipotential on a suspension tower6.1.1 The worker shall not enter or leave equipotential from cross arms vertically or along insulator strings.6.1.2 The hanging basket (hanging chair and hanging ladder) method, the insulating flexible ladder method and other methods may be used t
21、o enter or leave equipotential.6.1.3 The hanging baskets (hanging chairs and hanging ladders) shall be stably suspended by slings. The length of the slings for fixing shall be accurately calculated or actually measured to ensure that the equipotential workers head shall not exceed the grading ring o
22、n the conductor side.6.1.4 The moving speed of the hanging baskets (hanging chairs and hanging ladders) shall be strictly controlled to achieve a uniform and steady speed.6.1.5 When entering or leaving high electric fields, the equipotential worker shall avoid excessive body movements. All the elect
23、rical gap distances (including the working distances and the combined gaps) between the equipotential worker and the earthing conductors and the live conductors shall meet the requirements of Chapter 5.6.2 Enter or leave equipotential on a tension tower6.2.1 The worker may enter or leave equipotenti
24、al along tension insulator strings or via other methods.6.2.2 When the equipotential worker moves along the tension insulator strings, the cross-two-short-three method shall be generally adopted. The positions of the workers hands and feet must be kept consistent, and the number of insulators short-