混凝土表面处理及涂装基本工艺.doc
《混凝土表面处理及涂装基本工艺.doc》由会员分享,可在线阅读,更多相关《混凝土表面处理及涂装基本工艺.doc(26页珍藏版)》请在淘文阁 - 分享文档赚钱的网站上搜索。
1、1.0Purpose目This procedure covers the application of all concrete coating systems applied by CELEB.本施工工艺规程规范所有北京九州华清防腐混凝土涂装系统施工。2.0Scope范畴This procedure will be followed in all applications.本规程应贯彻于所有施工过程中。3.0Responsibilities责任3.1The Project Manager 项目经理- Operation and management of grinding and paint
2、ing works. Plan work schedules. Maintained strict conformance to clients required specifications.负责研磨和涂装作业管理及运作工作。准备工作进度表。严格遵循客户规定涂装系统及规范施工。-Liaise with Engineers,Production,Q.C. Personnel and other contractors on work schedules,job performance and implementation on quality control requirements. Exe
3、rcised quality control surveillance on conformance to required specifications.协调施工各方,保证按质量按进度施工作业,控制质量以符合业主涂装系统规范。3.2The Supervisor 监理 - To ensure that all tests are undertaken and,in the case of witness tests the client representative is present.保证执行各项检测工作,检测时应有客户代表在场。3.3The Forman -领班 - To ensure
4、that all work conforms to specifications and is done in a workman like manner.保证按原则施工,施工人员工作态度端正。4.0References原则Where referred to in this specification,the latest edition of the following specifications,standards and other documents apply.本规程参照如下原则及规范制定:ASTM D4227-99 “Standard Practice for the Quali
5、fication of Coating Applicators for Application of Coatings to Concrete Surfaces”ASTM D4258-83 “Standard Practice for Surface Cleaning Concrete for Coating”ASTM D4259-88 “Standard Practice for Abrading Concrete”ASTM D4261“Standard Practice for Surface Cleaning Concrete Unit Masonry for Coating” 5.0D
6、ocumentation文献Daily Work Report / 每日工作报告Daily Q.C Report / 质量日报表6.0Procedure规程6.1 Inspection of the Concrete Substrate混凝土基层检测It is to determine the concretes general condition,soundness,presence of contaminants,presence of moisture vapor emissions and the best methods to use in preparation of the su
7、rface to meet the requirements of the client or the manufacturers recommendation.对混凝土通过现场堪察及基层检测,掌握混凝土总体状况、表面坚实度、污染状况及潮气含量,从而决定表面解决最佳方式,以达到客户和材料生产商规定。6.2Pre-clean all surfaces by brooming and if necessary accomplished by scrubbing with heavy duty cleaner / degreaser or low pressure water cleaning (l
8、ess than 5,000 psi) or chemical washing to remove oils,grease,wax,fatty acids and other contaminations.先用扫帚清洁地表,必要时使用深度清洁剂去除地表污渍,或用低压水冲洗(不超过5,000 psi),也可以使用化学溶液去除油污,油脂,表腊,脂肪酸或其他污染。6.3 Removal of Surface Laitance and Creation of Surface Profile去除水泥翻沫,提供粗糙度Removal of surface laitance and /or curing co
9、mpound and creation of surface profile can be accomplished by a number of methods each utilizing a selection of tools,equipment and materials to accomplish the intended purpose,(See table below). Selection is dependent upon the type of surface to be prepared and the type of system to be installed. I
10、n addition,floors,walls,ceilings,trenches,tanks and sumps each have their own particular requirements. The type and thickness of the selected coating system also plays an important role in the selection process. Regardless of the method selected or tools employed,we must provide a surface that will
11、accept the application of polymer-based products and allow the mechanical bond of the polymer securely to the concrete. 去除水泥翻沫及养护剂、脱模剂需使用手动工具或设备来完毕。依照待涂装地坪表面以及不同涂装系统,选取不同作业工具和作业办法(见下表)。此外,地坪、墙壁、天花板、地沟、水槽和水罐对工具使用会有不同规定。并且工具选取与所选用涂装厚度和类型也关于系。无论选取哪种类型工具,咱们必须提供一种适合聚合树脂材料涂装表面,且保证涂装材料与地坪有良好机械附着力。 The foll
12、owing table provides a guide for the degree of surface profile required for the coating or overlay to be applied and the preparation methods used to generate each profile to the specified standard.如下表格为各类涂装系统所需达到粗糙度进行分类并对相应表面解决办法提供了指南。 Classification ofCoating System涂装系统分类DFT厚度(micron)Methods of Sur
13、face Preparation地坪表面解决办法Sealers封闭剂0-100Detergent Scrub / 清洁剂清洗Low Pressure Water Cleaning低压水洗Grinding / 研磨Thin Film封闭薄涂100-400Grinding / 研磨Abrasive Blasting / 喷砂Steel Shot Blasting / 钢丸喷砂High-Build厚涂400-1000Abrasive Blasting / 研磨Steel Shot Blasting / 钢丸喷砂自流平Self-Levelling1,000-3,000Abrasive Blasting
14、 / 研磨Steel Shot Blasting / 钢丸喷砂 Scarifying / Milling / 铣刨Needle Scaling / 针枪High Pressure Water Jetting高压水洗聚合砂浆Polymer Overlay3,000-6,000Abrasive Blasting / 研磨Steel Shot Blasting / 钢丸喷砂Scarifying / Milling / 铣刨Needle Scaling / 针枪High Pressure Water Jetting高压水洗Scabbling / 粗琢Surfaces to receive the bo
15、nded coating system must be inspected after the surface is prepared to insure that the substrate is sound,clean,textured and structurally durable. Areas found to be unsound or non-durable must be removed and replaced as stated in section 7.5. Dust or other deleterious substances not removed after th
16、e initial surface preparation must be vacuumed,leaving the surface dust free and clean.表面解决完毕后,检查地坪以保证地坪表面良好、清洁、有适当纹理且表层构造牢固。如发既有不良不坚实表面,应及时进行解决,详细见第7.5章。经初次表面解决未能移去灰尘或表面碎屑,应真空吸尘,使地表干净无尘。 6.4Removal and Replacement of Non-durable Concrete修复混凝土缺陷Localized weak or deteriorated concrete must be removed
17、 to sound concrete and replaced with PC cementitious or polymer concrete repair mortars,or an engineered concrete mix design utilizing polyacrylate polymer additive. For application of these systems and compatibility with the selected polymer sealer,coating,lining or topping refer to the Technical D
18、ata Sheets. Occasionally,plain fresh concrete is required and must be bonded to existing concrete. When bonding fresh concrete to existing,prepare the existing concrete surface by scabbling,scarifying,abrasive (sand) blasting,needle scaling,high pressure water jetting (5,000 to 45,000 psi),or steel
19、shot blasting.除去薄弱或损坏混凝土表层,然后使用聚合混凝土或聚合砂浆进行修补。也可使用聚合改良混凝土进行修补。关于选取和施工兼容密封剂、地坪涂装材料、贴面材料及聚合面层材料,参照技术阐明书。有时,需要在已有混凝土层上浇筑混凝土,应当对原有混凝土层表面进行表面解决。使用粗琢、铣刨、喷砂、针枪、高压水泵(5,000psi 至 45,000psi)或钢丸喷砂来保证新旧混凝土层之间附着力。Standard / 原则:ACI 503.4-92 “Standard Specification for Repairing Concrete with Epoxy Mortar”6.5 Repai
20、r of Surface Irregularities修补砼表面不平整处All surface irregularities including bugholes,spalls,cracks,deteriorated joints,slopes,areas near transition zones,such as around drains and doorways,etc. must be filled and resurfaced with a specified quick-setting cementitious grout or solvent-free epoxy mortar,
21、in accordance with the manufacturers recommendations,prior to coating.对于砼表面不平整,涉及蜂窝、散裂、裂缝、伸缩缝损坏、倾斜、过渡区域如地沟或门廊周边等,用专用快干水泥砂浆或无溶剂环氧砂浆填充。填充作业依照材料供应商建议在涂装此前完毕。6.6 Isolation / Bridging of Cracks or Joints分隔 / 跨接裂缝或伸缩缝For additional crack bridging capabilities a proper isolation / bridging system with fibe
22、rglass scrim cloth and / or elastic sealant shall be applied before coating of the entire surfaces.必要时,在对整个表面进行涂装前,使用纤维布或弹性密封胶来构成一种裂缝跨接系统。6.7 Painting / Coating涂装6.7.1 General / 概述All surfaces to be coated shall be clean,sound and dry before application of the first coat.涂装前,砼表面应清洁、干燥、坚实。 The water
23、/ vapor content of the concrete substrate shall not exceed 4% or specifiedin the manufacturers recommendation. 依照材料供应商建议,混凝土基层水份含量不应当超过4%。No coating shall be applied when substrate temperature is less than 3C above dew point,or the relative humidity is higher than 85%,so as to avoid the risk of cond